Skip to content
GharKundli

Nemichand Bhumi Siddhi

by Nemichand Bhandari Associates · Mangalwar Peth, Pune 411044Also near Ravet, Punawale, Nigdi PradhikaranRegistered on MahaRERA as “Bhumi Siddhi”

What’s in the report? →

Possession: Nemichand Bhumi Siddhi (MahaRERA P52100011705) is marked completed on MahaRERA. It has 63 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100011705. Status: Completed.

Source: MahaRERA website — records for P52100011705, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Nemichand Bhumi Siddhi?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Nemichand Bhumi Siddhi has moved

  1. 31 December 2017

    Completion date given when the project was registered

  2. 31 December 2018

    Extended at the builder's request (MahaRERA application EXT52100000325)

    Reason the builder gave MahaRERA: “We have already applied for the Complication Certificate to PCNTDA on Dated - 15/03/2017. Their internal document is pending they will take up the same. We expecting Certificate very soon.”

Source: Nemichand Bhumi Siddhi’s extension records on MahaRERA (P52100011705), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Nemichand Bhumi Siddhi

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2018 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100011705
Status
Completed
Builder
Nemichand Bhandari Associates
Location
Mangalwar Peth, Pune · 411044
Project type
Others
Registered on
31 Aug 2017
Completion date at registration
December 2017
Latest completion date
December 2018
Delay so far
12 months
Homes
63
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Nemichand Bhumi Siddhi, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Bhumi B WING100%100%100%100%
Bhumi A wing100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nemichand Bhumi Siddhi every 1–2 months.

Nemichand Bhumi Siddhi: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Nemichand Bhandari Associates has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA.

Read Google reviews of Nemichand Bhumi Siddhi →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Nemichand Bhumi Siddhi: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Nemichand Bhumi Siddhi

What is the possession date of Nemichand Bhumi Siddhi?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Nemichand Bhumi Siddhi in Mangalwar Peth, Pune is 31 December 2018 — 12 months later than 31 December 2017, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Nemichand Bhumi Siddhi?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Nemichand Bhumi Siddhi's builder has filed on MahaRERA, the official one, is 31 December 2018, already 12 months later than the 31 December 2017 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Nemichand Bhumi Siddhi extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhumi Siddhi's builder applied to MahaRERA to extend the completion date once: to 31 December 2018, giving the reason "We have already applied for the Complication Certificate to PCNTDA on Dated - 15/03/2017. Their internal document is pending they will take up the same. We expecting Certificate very soon.".

What is the RERA number of Nemichand Bhumi Siddhi?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Nemichand Bhumi Siddhi in Mangalwar Peth, Pune is P52100011705.

Is Nemichand Bhumi Siddhi registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhumi Siddhi is registered as P52100011705 and its status is "Completed".

What is the current construction status of Nemichand Bhumi Siddhi? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhumi Siddhi's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Nemichand Bhumi Siddhi have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Nemichand Bhumi Siddhi safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhumi Siddhi is registered on MahaRERA as P52100011705, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Nemichand Bhumi Siddhi?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhumi Siddhi is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Nemichand Bhumi Siddhi?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Nemichand Bhumi Siddhi: gharkundli.com/tools/property-cost-calculator

Has Nemichand Bhumi Siddhi received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhumi Siddhi is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Nemichand Bhumi Siddhi completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhumi Siddhi is marked completed on MahaRERA, and the completion date filed there is 31 December 2018. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Nemichand Bhumi Siddhi uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Nemichand Bhumi Siddhi was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Nemichand Bhumi Siddhi's possession date changes?

The latest dates are on Nemichand Bhumi Siddhi's MahaRERA page (P52100011705). GharKundli's Kundli Watch sends a free WhatsApp update on Nemichand Bhumi Siddhi every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Nemichand Bhumi Siddhi have?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhumi Siddhi has 2 buildings filed: Bhumi B WING with 9 floors; Bhumi A wing with 9 floors.

How big is the land of Nemichand Bhumi Siddhi?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhumi Siddhi stands on 3,000 sq m of land (about 0.7 acres), with 2,998 sq m of sanctioned built-up area.

What is the track record of Nemichand Bhumi Siddhi's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhandari Associates has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Nemichand Bhumi Siddhi?

Google Maps has reviews of Nemichand Bhumi Siddhi written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Nemichand Bhumi Siddhi?

Nemichand Bhumi Siddhi by Nemichand Bhandari Associates is in Mangalwar Peth, Pune, pincode 411044 (near Ravet, Punawale, Nigdi Pradhikaran), Maharashtra, and is registered on MahaRERA as P52100011705, per GharKundli's check of MahaRERA records. GharKundli lists all 70 MahaRERA projects in P.C.N.T. (411044).

How many flats are in Nemichand Bhumi Siddhi?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhumi Siddhi has 63 homes in 2 towers registered on MahaRERA.

When was Nemichand Bhumi Siddhi registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Nemichand Bhumi Siddhi was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Does Nemichand Bhumi Siddhi have any legal issues or court cases?

No court cases are listed for Nemichand Bhumi Siddhi on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Nemichand Bhumi Siddhi?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Nemichand Bhandari Associates, which has 1 other project registered on MahaRERA.

Other projects in P.C.N.T. (411044)

All 70 projects in P.C.N.T. (411044) →

Other projects by Nemichand Bhandari Associates

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.