Skyi Star Town Phase V
by Enerrgia Skyi Properties Pvt Ltd · Behind Shell Petrol Pump, Pune
Possession: Skyi Star Town Phase V is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100021041. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Skyi Star Town Phase V?
How the possession date of Skyi Star Town Phase V has moved
28 August 2023
Completion date given when the project was registered
29 February 2024
Extended at the builder's request (MahaRERA application EXT52100017446)
Reason the builder gave MahaRERA:
“The Project “Skyi Star Town Phase V” is located outside from the City of Pune in the Village Bhukum, Taluka Mulshi, Dist Pune. The Village Bhukum falls under a substantial rainfall area. In the year 2019, we have experienced unprecedented r…” Read the full reason
“The Project “Skyi Star Town Phase V” is located outside from the City of Pune in the Village Bhukum, Taluka Mulshi, Dist Pune. The Village Bhukum falls under a substantial rainfall area. In the year 2019, we have experienced unprecedented rainfall leading to severe flood situation, which derailed construction activities almost for five months. The Construction status are as below: - RCC Work – 100% Completed Block Work – 100% Completed Internal Plaster – 100% Completed External Plaster – 100% Completed Flooring – 100% Completed We have submitted an application to PMRDA dated 18/04/2023 to g…”
Source: Skyi Star Town Phase V’s extension records on MahaRERA (P52100021041), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Skyi Star Town Phase V
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the February 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Skyi Star Town Phase IVP52100019226
- MahaRERA registration
- P52100021041
- Status
- Completed
- Builder
- Enerrgia Skyi Properties Pvt Ltd
- Location
- Behind Shell Petrol Pump, Pune · 412115
- Project type
- Residential / Group Housing
- Registered on
- 31 May 2019
- Completion date at registration
- August 2023
- Latest completion date
- February 2024
- Delay so far
- 6 months
- Homes
- 207
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Skyi Star Town Phase V, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 6 | 90% | 60% | 75% | 60% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Skyi Star Town Phase V every month.
Skyi Star Town Phase V: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 6 (15 floors)
- Land: 13,373 sq m (about 3.3 acres) · sanctioned built-up 12,730 sq m · recreational space 3,117 sq m
The builder’s record and reviews
Enerrgia Skyi Developers (a group of 8 linked companies) has 48 projects on MahaRERA since 2019, this one included. Of the 29 GharKundli has checked: 1 finished, all within the promised date; 22 still being built, 3 past the promised date (typically 3 months late); 6 lapsed. 19 complaints on MahaRERA across 9 projects.
Read Google reviews of Skyi Star Town Phase V →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Skyi Star Town Phase V: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Skyi Star Town Phase V
What is the possession date of Skyi Star Town Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Skyi Star Town Phase V in Behind Shell Petrol Pump, Pune is 29 February 2024 — 6 months later than 28 August 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Skyi Star Town Phase V?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Skyi Star Town Phase V's builder has filed on MahaRERA, the official one, is 29 February 2024, already 6 months later than the 28 August 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Skyi Star Town Phase V extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star Town Phase V's builder applied to MahaRERA to extend the completion date once: to 29 February 2024, giving the reason "The Project “Skyi Star Town Phase V” is located outside from the City of Pune in the Village Bhukum, Taluka Mulshi, Dist Pune. The Village Bhukum falls under a substantial rainfall area. In the year 2019, we have experienced unprecedented rainfall leading to severe flood situation, which derailed construction activities almost for five months. The Construction status are as below: - RCC Work – 100% Completed Block Work – 100% Completed Internal Plaster – 100% Completed External Plaster – 100% Completed Flooring – 100% Completed We have submitted an application to PMRDA dated 18/04/2023 to g…".
What is the RERA number of Skyi Star Town Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Skyi Star Town Phase V in Behind Shell Petrol Pump, Pune is P52100021041.
Is Skyi Star Town Phase V registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star Town Phase V is registered as P52100021041 and its status is "Completed".
What is the construction status of Skyi Star Town Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star Town Phase V's status on MahaRERA is "Completed". As filed by the builder, slab work on Building No 6 is 60% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.
Does Skyi Star Town Phase V have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Skyi Star Town Phase V safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star Town Phase V is registered on MahaRERA as P52100021041, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Skyi Star Town Phase V have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Skyi Star Town Phase IV (P52100019226). Check that your agreement names the registration of your own wing.
How can I get updates if Skyi Star Town Phase V's possession date changes?
The latest dates are on Skyi Star Town Phase V's MahaRERA page (P52100021041). GharKundli's Kundli Watch sends a free WhatsApp update on Skyi Star Town Phase V every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Skyi Star Town Phase V have?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star Town Phase V has one building filed: Building No 6 with 15 floors.
How big is the land of Skyi Star Town Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star Town Phase V stands on 13,373 sq m of land (about 3.3 acres), with 12,730 sq m of sanctioned built-up area and 3,117 sq m of recreational open space.
What is the track record of Skyi Star Town Phase V's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Enerrgia Skyi Developers (a group of 8 linked companies) has 48 projects on MahaRERA since 2019, this one included. Of the 29 GharKundli has checked: 1 finished, all within the promised date; 22 still being built, 3 past the promised date (typically 3 months late); 6 lapsed. 19 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Skyi Star Town Phase V?
Google Maps has reviews of Skyi Star Town Phase V written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Skyi Star Town Phase V?
Skyi Star Town Phase V by Enerrgia Skyi Properties Pvt Ltd is in Behind Shell Petrol Pump, Pune (pincode 412115), Maharashtra, and is registered on MahaRERA as P52100021041, per GharKundli's check of MahaRERA records.
How many homes are in Skyi Star Town Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star Town Phase V has 207 homes in 1 tower registered on MahaRERA.
When was Skyi Star Town Phase V registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star Town Phase V was registered on MahaRERA on 31 May 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Skyi Star Town Phase V?
No court cases are listed for Skyi Star Town Phase V on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Skyi Star Town Phase V?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Enerrgia Skyi Properties Pvt Ltd, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Skyi Star Town Phase V
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mulshi
- Nirman Serenopolis
- Signature Park Phase - I
- LOTUS CREST
- Mahindra Rivenza Phase 2
- West World
- Mahindra Rivenza Phase 1
- Goodland Phase-III
- VYOMORA PHASE 1
Other projects by Enerrgia Skyi Properties Pvt Ltd
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.