Ambiance Aura-PhaseII

by Parvati Constructions · Kirkatwadi, Pune

Possession date of Ambiance Aura-PhaseII: 5 July 2024, moved from 6 July 2023 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100021658. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2024) has passed.

What do you want to know about Ambiance Aura-PhaseII?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Ambiance Aura-PhaseII

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100021658
Status
Lapsed (registration period ended)
Builder
Parvati Constructions
Location
Kirkatwadi, Pune · 411024
Project type
Residential / Group Housing
Registered on
19 Jul 2019
Completion date at registration
July 2023
Latest completion date
July 2024
Delay so far
12 months
Homes
32
Towers
8
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Ambiance Aura-PhaseII, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A -5Th Floor100%100%100%100%
B-5TH FLOOR100%100%100%100%
C-5TH FLOOR100%100%100%100%
D-5TH FLOOR100%100%100%100%
E-5TH FLOOR100%100%100%100%
F-5TH FLOOR100%100%100%100%
G-5TH FLOOR100%100%100%100%
H-5TH FLOOR100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ambiance Aura-PhaseII every month.

Ambiance Aura-PhaseII: buildings, flats and land, as filed on MahaRERA

  • Buildings: A -5Th Floor (7 floors) · B-5TH FLOOR (7 floors) · C-5TH FLOOR (7 floors) · D-5TH FLOOR (7 floors) · E-5TH FLOOR (7 floors) · F-5TH FLOOR (7 floors) · G-5TH FLOOR (7 floors) · H-5TH FLOOR (7 floors)
  • Land: 1,487 sq m (about 0.4 acres) · sanctioned built-up 1,738 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Ambiance Aura-PhaseII →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ambiance Aura-PhaseII: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Ambiance Aura-PhaseII

What is the possession date of Ambiance Aura-PhaseII?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Ambiance Aura-PhaseII in Kirkatwadi, Pune is 5 July 2024 — 12 months later than 6 July 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Ambiance Aura-PhaseII?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ambiance Aura-PhaseII's builder has filed on MahaRERA, the official one, is 5 July 2024, already 12 months later than the 6 July 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Ambiance Aura-PhaseII?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Ambiance Aura-PhaseII in Kirkatwadi, Pune is P52100021658.

Is Ambiance Aura-PhaseII registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ambiance Aura-PhaseII is registered as P52100021658 and its status is "Lapsed (registration period ended)".

What is the construction status of Ambiance Aura-PhaseII?

According to GharKundli's check of MahaRERA records (updated November 2026), Ambiance Aura-PhaseII's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 8 towers. GharKundli's full report compares construction progress with the deadline.

Does Ambiance Aura-PhaseII have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Ambiance Aura-PhaseII safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Ambiance Aura-PhaseII is registered on MahaRERA as P52100021658, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Ambiance Aura-PhaseII's possession date changes?

The latest dates are on Ambiance Aura-PhaseII's MahaRERA page (P52100021658). GharKundli's Kundli Watch sends a free WhatsApp update on Ambiance Aura-PhaseII every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ambiance Aura-PhaseII have?

According to GharKundli's check of MahaRERA records (updated November 2026), Ambiance Aura-PhaseII has 8 buildings filed: A -5Th Floor with 7 floors; B-5TH FLOOR with 7 floors; C-5TH FLOOR with 7 floors; D-5TH FLOOR with 7 floors; E-5TH FLOOR with 7 floors; F-5TH FLOOR with 7 floors; and 2 more.

How big is the land of Ambiance Aura-PhaseII?

According to GharKundli's check of MahaRERA records (updated November 2026), Ambiance Aura-PhaseII stands on 1,487 sq m of land (about 0.4 acres), with 1,738 sq m of sanctioned built-up area.

Where can I read reviews of Ambiance Aura-PhaseII?

Google Maps has reviews of Ambiance Aura-PhaseII written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Ambiance Aura-PhaseII?

Ambiance Aura-PhaseII by Parvati Constructions is in Kirkatwadi, Pune (pincode 411024), Maharashtra, and is registered on MahaRERA as P52100021658, per GharKundli's check of MahaRERA records.

How many homes are in Ambiance Aura-PhaseII?

According to GharKundli's check of MahaRERA records (updated November 2026), Ambiance Aura-PhaseII has 32 homes in 8 towers registered on MahaRERA.

When was Ambiance Aura-PhaseII registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Ambiance Aura-PhaseII was registered on MahaRERA on 19 July 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Ambiance Aura-PhaseII?

No court cases are listed for Ambiance Aura-PhaseII on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Ambiance Aura-PhaseII?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Parvati Constructions, which has 1 other project registered on MahaRERA.

All projects in Kirkatwadi (411024) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.