VISTARA
by Buildstrong Estate Realtors LLP · Chikhali, Pune
Possession: VISTARA is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100022491. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about VISTARA?
How the possession date of VISTARA has moved
30 December 2022
Completion date given when the project was registered
30 June 2023
Extended at the builder's request (MahaRERA application EXT52100012862)
Reason the builder gave MahaRERA:
“The municipal authorities initiated the laying of water pipeline, the path of which passes through the road that abuts our project location. Due to this activity, the approach road to the site has been dug up, blocking all kinds of heavy ve…” Read the full reason
“The municipal authorities initiated the laying of water pipeline, the path of which passes through the road that abuts our project location. Due to this activity, the approach road to the site has been dug up, blocking all kinds of heavy vehicles movement and which in turn blocks material transport to the site of our project "Vistara". This work has been ongoing since 8 Aug 2022 and has delayed our scheduled activities that were otherwise planned to be carried out. Due to unexpected and prolonged run of the rainy season, our schedule for the external paint job, waterproofing, and other alli…”
Source: VISTARA’s extension records on MahaRERA (P52100022491), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VISTARA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100022491
- Status
- Completed
- Builder
- Buildstrong Estate Realtors LLP
- Location
- Chikhali, Pune · 412114
- Project type
- Residential / Group Housing
- Registered on
- 25 Sep 2019
- Completion date at registration
- December 2022
- Latest completion date
- June 2023
- Delay so far
- 6 months
- Homes
- 74
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of VISTARA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VISTARA every month.
VISTARA: buildings, flats and land, as filed on MahaRERA
- Buildings: A (11 floors)
- Land: 2,800 sq m (about 0.7 acres) · sanctioned built-up 3,930 sq m · recreational space 262 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VISTARA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VISTARA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VISTARA
What is the possession date of VISTARA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VISTARA in Chikhali, Pune is 30 June 2023 — 6 months later than 30 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for VISTARA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VISTARA's builder has filed on MahaRERA, the official one, is 30 June 2023, already 6 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VISTARA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), VISTARA's builder applied to MahaRERA to extend the completion date once: to 30 June 2023, giving the reason "The municipal authorities initiated the laying of water pipeline, the path of which passes through the road that abuts our project location. Due to this activity, the approach road to the site has been dug up, blocking all kinds of heavy vehicles movement and which in turn blocks material transport to the site of our project "Vistara". This work has been ongoing since 8 Aug 2022 and has delayed our scheduled activities that were otherwise planned to be carried out. Due to unexpected and prolonged run of the rainy season, our schedule for the external paint job, waterproofing, and other alli…".
What is the RERA number of VISTARA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VISTARA in Chikhali, Pune is P52100022491.
Is VISTARA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VISTARA is registered as P52100022491 and its status is "Completed".
What is the construction status of VISTARA?
According to GharKundli's check of MahaRERA records (updated November 2026), VISTARA's status on MahaRERA is "Completed". As filed by the builder, slab work on A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does VISTARA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is VISTARA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), VISTARA is registered on MahaRERA as P52100022491, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VISTARA's possession date changes?
The latest dates are on VISTARA's MahaRERA page (P52100022491). GharKundli's Kundli Watch sends a free WhatsApp update on VISTARA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VISTARA have?
According to GharKundli's check of MahaRERA records (updated November 2026), VISTARA has one building filed: A with 11 floors.
How big is the land of VISTARA?
According to GharKundli's check of MahaRERA records (updated November 2026), VISTARA stands on 2,800 sq m of land (about 0.7 acres), with 3,930 sq m of sanctioned built-up area and 262 sq m of recreational open space.
Where can I read reviews of VISTARA?
Google Maps has reviews of VISTARA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VISTARA?
VISTARA by Buildstrong Estate Realtors LLP is in Chikhali, Pune (pincode 412114), Maharashtra, and is registered on MahaRERA as P52100022491, per GharKundli's check of MahaRERA records.
How many homes are in VISTARA?
According to GharKundli's check of MahaRERA records (updated November 2026), VISTARA has 74 homes in 1 tower registered on MahaRERA.
When was VISTARA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VISTARA was registered on MahaRERA on 25 September 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on VISTARA?
No court cases are listed for VISTARA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of VISTARA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Buildstrong Estate Realtors LLP.
Check it yourself on MahaRERA
- How to check the possession date of VISTARA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Chikhali
All Pune projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.