Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA
by B.P. ENTERPRISES · Mangalwar Peth, Pune 411011Also near Kasba Peth, Pune City, S.P. College
What’s in the report? →Possession: Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA (MahaRERA P52100024692) is marked completed on MahaRERA. It has 28 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100024692. Status: Completed.
Source: MahaRERA website — records for P52100024692, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA has moved
30 June 2021
Completion date given when the project was registered
31 March 2022
Extended at the builder's request (MahaRERA application EXT52100009100)
Reason the builder gave MahaRERA:
“THE PROJECT HAS BEEN ALREADY BEEN 80% COMPLETED. THE REASON FOR DELAYED FOR NON-COMPLETION IS THAT THERE WAS SOME DISPUTES BETWEEN ONE COMMERCIAL TENANT AND DEVELOPERS AND FINANCIAL OBLIGATION AMD THEREAFTER COVID 19 PANDEMIC. FURTHER, THE…” Read the full reason
“THE PROJECT HAS BEEN ALREADY BEEN 80% COMPLETED. THE REASON FOR DELAYED FOR NON-COMPLETION IS THAT THERE WAS SOME DISPUTES BETWEEN ONE COMMERCIAL TENANT AND DEVELOPERS AND FINANCIAL OBLIGATION AMD THEREAFTER COVID 19 PANDEMIC. FURTHER, THE DISPUTE HAS BEEN RESOLVED.”30 September 2022
Revised completion date on MahaRERA
Source: Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA’s extension records on MahaRERA (P52100024692), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100024692
- Status
- Completed
- Builder
- B.P. ENTERPRISES
- Location
- Mangalwar Peth, Pune · 411011
- Project type
- Residential / Group Housing
- Registered on
- 28 Feb 2020
- Completion date at registration
- June 2021
- Latest completion date
- September 2022
- Delay so far
- 15 months
- Homes
- 28
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHRI HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA | 100% | 85% | 15% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA every 1–2 months.
Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA: buildings, flats and land, as filed on MahaRERA
- Buildings: SHRI HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA (9 floors)
- Land: 358 sq m (about 0.1 acres) · sanctioned built-up 872 sq m · recreational space 323 sq m
- Land, as filed: 106/2
- Map: Get directions
The builder’s record and reviews
B P Enterprises (a group of 3 linked companies) has 4 projects on MahaRERA since 2019, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 3 months); 2 still being built, 2 past the promised date (typically 27 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project.
Read Google reviews of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA
What is the possession date of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA in Mangalwar Peth, Pune is 30 September 2022 — 15 months later than 30 June 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA's builder has filed on MahaRERA, the official one, is 30 September 2022, already 15 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA's builder applied to MahaRERA to extend the completion date once: to 31 March 2022, giving the reason "THE PROJECT HAS BEEN ALREADY BEEN 80% COMPLETED. THE REASON FOR DELAYED FOR NON-COMPLETION IS THAT THERE WAS SOME DISPUTES BETWEEN ONE COMMERCIAL TENANT AND DEVELOPERS AND FINANCIAL OBLIGATION AMD THEREAFTER COVID 19 PANDEMIC. FURTHER, THE DISPUTE HAS BEEN RESOLVED.".
What is the RERA number of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA in Mangalwar Peth, Pune is P52100024692.
Is Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA is registered as P52100024692 and its status is "Completed".
What is the current construction status of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA's status on MahaRERA is "Completed". As filed by the builder, slab work on SHRI HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA is 85% done and internal work 15%. GharKundli's full report compares construction progress with the deadline.
Does Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA is registered on MahaRERA as P52100024692, its MahaRERA status is "Completed", its completion date has moved 15 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA: gharkundli.com/tools/property-cost-calculator
Has Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA completed?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA is marked completed on MahaRERA, and the completion date filed there is 30 September 2022. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA's possession date changes?
The latest dates are on Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA's MahaRERA page (P52100024692). GharKundli's Kundli Watch sends a free WhatsApp update on Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA has one building filed: SHRI HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA with 9 floors.
How big is the land of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA stands on 358 sq m of land (about 0.1 acres), with 872 sq m of sanctioned built-up area and 323 sq m of recreational open space.
What is the track record of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), B P Enterprises (a group of 3 linked companies) has 4 projects on MahaRERA since 2019, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 3 months); 2 still being built, 2 past the promised date (typically 27 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA?
Google Maps has reviews of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA?
Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA by B.P. ENTERPRISES is in Mangalwar Peth, Pune, pincode 411011 (near Kasba Peth, Pune City, S.P. College), Maharashtra, and is registered on MahaRERA as P52100024692, per GharKundli's check of MahaRERA records. Its land is filed as 106/2. GharKundli lists all 77 MahaRERA projects in Kasba Peth (411011).
How many flats are in Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA has 28 homes in 1 tower registered on MahaRERA.
When was Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA was registered on MahaRERA on 28 February 2020. GharKundli did not find a title report on the land on file there.
Does Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA have any legal issues or court cases?
No court cases are listed for Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is B.P. ENTERPRISES.
Check it yourself on MahaRERA
- How to check the possession date of Shri. HARIKRIPA SAHAKARI GRIHA RACHANA SANSTHA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kasba Peth (411011)
- Siddhivinayak Residency
- Opulent Starlit
- Heramb Plaza
- Wyng
- Suyash Tower
- Antriksh Towers
- Antriksh Towers 22-32
- Anandi Madhav Smruti
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.