Possession date of Kalpak: 30 November 2022, moved from 30 June 2022 (5 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100026027. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (November 2022) has passed.

What do you want to know about Kalpak?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Kalpak has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 November 2022

    Extended at the builder's request (MahaRERA application EXT52100012298)

    Reason the builder gave MahaRERA:
    “We faced a lot of issues with regards to material and more particularly labour post the covid imposed lockdowns. Despite all our efforts, unfortunately, we could not get back our labours on time post the second wave of covid last year. Ther…” Read the full reason“We faced a lot of issues with regards to material and more particularly labour post the covid imposed lockdowns. Despite all our efforts, unfortunately, we could not get back our labours on time post the second wave of covid last year. Thereafter the speed of our project was hampered. We had 4 projects ongoing in the covid induced lockwdown period, however the other projects were not as badly hampered and we have completed/ are going to complete within the time frame. We are now almost on the verge of completing the project and expect to finish the project and receive completion certificate…”

Source: Kalpak’s extension records on MahaRERA (P52100026027), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kalpak

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100026027
Status
Lapsed (registration period ended)
Builder
Digamber Parulekar
Location
Gultekadi, Pune · 411037
Project type
Residential / Group Housing
Registered on
9 Aug 2020
Completion date at registration
June 2022
Latest completion date
November 2022
Delay so far
5 months
Homes
10
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Kalpak, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Kalpak100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kalpak every month.

Kalpak: buildings, flats and land, as filed on MahaRERA

  • Buildings: Kalpak (7 floors)
  • Land: 516 sq m (about 0.1 acres) · sanctioned built-up 1,018 sq m

The builder’s record and reviews

Digamber Parulekar has 7 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 3 months); 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Kalpak →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kalpak: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Kalpak

What is the possession date of Kalpak?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Kalpak in Gultekadi, Pune is 30 November 2022 — 5 months later than 30 June 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Kalpak?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kalpak's builder has filed on MahaRERA, the official one, is 30 November 2022, already 5 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Kalpak extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Kalpak's builder applied to MahaRERA to extend the completion date once: to 30 November 2022, giving the reason "We faced a lot of issues with regards to material and more particularly labour post the covid imposed lockdowns. Despite all our efforts, unfortunately, we could not get back our labours on time post the second wave of covid last year. Thereafter the speed of our project was hampered. We had 4 projects ongoing in the covid induced lockwdown period, however the other projects were not as badly hampered and we have completed/ are going to complete within the time frame. We are now almost on the verge of completing the project and expect to finish the project and receive completion certificate…".

What is the RERA number of Kalpak?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Kalpak in Gultekadi, Pune is P52100026027.

Is Kalpak registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kalpak is registered as P52100026027 and its status is "Lapsed (registration period ended)".

What is the construction status of Kalpak?

According to GharKundli's check of MahaRERA records (updated November 2026), Kalpak's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Kalpak is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Kalpak have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Kalpak safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Kalpak is registered on MahaRERA as P52100026027, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 5 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Kalpak's possession date changes?

The latest dates are on Kalpak's MahaRERA page (P52100026027). GharKundli's Kundli Watch sends a free WhatsApp update on Kalpak every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kalpak have?

According to GharKundli's check of MahaRERA records (updated November 2026), Kalpak has one building filed: Kalpak with 7 floors.

How big is the land of Kalpak?

According to GharKundli's check of MahaRERA records (updated November 2026), Kalpak stands on 516 sq m of land (about 0.1 acres), with 1,018 sq m of sanctioned built-up area.

What is the track record of Kalpak's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Digamber Parulekar has 7 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 3 months); 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Kalpak?

Google Maps has reviews of Kalpak written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Kalpak?

Kalpak by Digamber Parulekar is in Gultekadi, Pune (pincode 411037), Maharashtra, and is registered on MahaRERA as P52100026027, per GharKundli's check of MahaRERA records.

How many homes are in Kalpak?

According to GharKundli's check of MahaRERA records (updated November 2026), Kalpak has 10 homes in 1 tower registered on MahaRERA.

When was Kalpak registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kalpak was registered on MahaRERA on 9 August 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Kalpak?

No court cases are listed for Kalpak on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Kalpak?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Digamber Parulekar, which has 6 other projects registered on MahaRERA.

Other projects in Gultekadi

All 112 projects in Bibwewadi (411037) →

Other projects by Digamber Parulekar

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.