Aksha Vrundavan II

by AKSHA ENTERPRISES (Concord) · Chikhali, Pune 411062Also near Ravet, Punawale, Pimpri

What’s in the report? →

Possession date of Aksha Vrundavan II (MahaRERA P52100029525): 30 January 2027, moved from 31 December 2024 (21 months later). It has 95 homes, 99% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100029525, and currently active. Its completion date has moved from December 2024 to January 2027: 21 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52100029525, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Aksha Vrundavan II?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Aksha Vrundavan II has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT52100027684)

    Reason the builder gave MahaRERA:
    “we are facing an unforeseen delay in obtaining the Occupancy Certificate (OC) from the concerned authorities. We have already submitted the necessary application, but due to procedural requirements and factors beyond our control, the approv…” Read the full reason“we are facing an unforeseen delay in obtaining the Occupancy Certificate (OC) from the concerned authorities. We have already submitted the necessary application, but due to procedural requirements and factors beyond our control, the approval process is taking longer than expected.”
  3. 30 September 2026

    Extended at the builder's request (MahaRERA application EA16062621380)

    Reason the builder gave MahaRERA:
    “We respectfully submit that the said project has already been completed on 06/03/2026. However, the completion date mentioned on the registration certificate is 30/06/2025, due to which the project registration reflects as lapsed. Since the…” Read the full reason“We respectfully submit that the said project has already been completed on 06/03/2026. However, the completion date mentioned on the registration certificate is 30/06/2025, due to which the project registration reflects as lapsed. Since the project is already completed as on 06/03/2026, we respectfully request that the necessary extension be granted”
  4. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Aksha Vrundavan II’s extension records on MahaRERA (P52100029525), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Aksha Vrundavan II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100029525
Status
Registered and active
Builder
AKSHA ENTERPRISES
Location
Chikhali, Pune · 411062
Project type
Residential / Group Housing
Registered on
4 Jun 2021
Completion date at registration
December 2024
Latest completion date
January 2027
Delay so far
21 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
95
Sold or booked
99%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Aksha Vrundavan II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A BLDG100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • A BLDG: covers 12 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aksha Vrundavan II every 1–2 months.

Aksha Vrundavan II: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Aksha Enterprises (a group of 6 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 27 months); 4 still being built, 2 past the promised date (typically 15 months late); 3 lapsed. 3 complaints on MahaRERA across 2 projects.

Read Google reviews of Aksha Vrundavan II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aksha Vrundavan II: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aksha Vrundavan II

What is the possession date of Aksha Vrundavan II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aksha Vrundavan II in Chikhali, Pune is 30 January 2027 — 21 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 21 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Aksha Vrundavan II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aksha Vrundavan II's builder has filed on MahaRERA, the official one, is 30 January 2027, already 21 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Aksha Vrundavan II extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Aksha Vrundavan II's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "we are facing an unforeseen delay in obtaining the Occupancy Certificate (OC) from the concerned authorities. We have already submitted the necessary application, but due to procedural requirements and factors beyond our control, the approval process is taking longer than expected."; to 30 September 2026, giving the reason "We respectfully submit that the said project has already been completed on 06/03/2026. However, the completion date mentioned on the registration certificate is 30/06/2025, due to which the project registration reflects as lapsed. Since the project is already completed as on 06/03/2026, we respectfully request that the necessary extension be granted". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Aksha Vrundavan II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aksha Vrundavan II in Chikhali, Pune is P52100029525.

Is Aksha Vrundavan II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aksha Vrundavan II is registered as P52100029525 and its status is "Registered and active".

What is the current construction status of Aksha Vrundavan II? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Aksha Vrundavan II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A BLDG is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Aksha Vrundavan II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Aksha Vrundavan II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Aksha Vrundavan II is registered on MahaRERA as P52100029525, its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aksha Vrundavan II?

Aksha Vrundavan II is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aksha Vrundavan II?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Aksha Vrundavan II: gharkundli.com/tools/property-cost-calculator

Has Aksha Vrundavan II received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Aksha Vrundavan II is still under construction, with 30 January 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Aksha Vrundavan II uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aksha Vrundavan II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Aksha Vrundavan II have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: AKSHA VRUNDAVAN (P52100011335, possession 31 Dec 2018); AKSHA VRUNDAVAN II (P52100020747, possession 29 Dec 2024); AKSHA VRUNDAVAN II (P52100029618, possession 30 Dec 2024). Check that your agreement names the registration of your own wing.

How can I get updates if Aksha Vrundavan II's possession date changes?

The latest dates are on Aksha Vrundavan II's MahaRERA page (P52100029525). GharKundli's Kundli Watch sends a free WhatsApp update on Aksha Vrundavan II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aksha Vrundavan II have?

According to GharKundli's check of MahaRERA records (updated October 2026), Aksha Vrundavan II has one building filed: A BLDG with 13 floors and 95 units.

How much parking does Aksha Vrundavan II have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 20 covered car parking spaces for Aksha Vrundavan II.

How big is the land of Aksha Vrundavan II?

According to GharKundli's check of MahaRERA records (updated October 2026), Aksha Vrundavan II stands on 1,833 sq m of land (about 0.5 acres), with 3,055 sq m of sanctioned built-up area.

What is the track record of Aksha Vrundavan II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Aksha Enterprises (a group of 6 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 27 months); 4 still being built, 2 past the promised date (typically 15 months late); 3 lapsed. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Aksha Vrundavan II?

Google Maps has reviews of Aksha Vrundavan II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aksha Vrundavan II?

Aksha Vrundavan II by AKSHA ENTERPRISES (Concord) is in Chikhali, Pune, pincode 411062 (near Ravet, Punawale, Pimpri), Maharashtra, and is registered on MahaRERA as P52100029525, per GharKundli's check of MahaRERA records. Its land is filed as GAT NO. 117, GAT NO. 118 CHIKHALI. GharKundli lists all 193 MahaRERA projects in Chikhali (411062).

How many flats are in Aksha Vrundavan II, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Aksha Vrundavan II has 95 homes in 1 tower registered on MahaRERA, and 99% of them are sold or booked.

When was Aksha Vrundavan II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aksha Vrundavan II was registered on MahaRERA on 4 June 2021. GharKundli did not find a title report on the land on file there.

Does Aksha Vrundavan II have any legal issues or court cases?

No court cases are listed for Aksha Vrundavan II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Aksha Vrundavan II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AKSHA ENTERPRISES, the company Concord files this project under, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2027 in Pune →

Other projects in Chikhali (411062)

All 193 projects in Chikhali (411062) →

Other projects by AKSHA ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.