Possession date of FLOW BAVDHAN: 31 December 2031, moved from 31 March 2026 (69 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100033942, and currently active.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about FLOW BAVDHAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of FLOW BAVDHAN has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 December 2031

    Extended at the builder's request (MahaRERA application EA24082622373)

    Reason the builder gave MahaRERA: “We have completed 57 shops out of 62 shops and received Occupancy Certificate for the same (as attached). Remaining 5 shops have not been built as yet and not sold as well.”

Source: FLOW BAVDHAN’s extension records on MahaRERA (P52100033942), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on FLOW BAVDHAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100033942
Status
Registered and active
Builder
VMC LANDMARK REALTY LLP
Location
Bavdhan, Pune · 411021
Project type
Commercial
Registered on
14 Mar 2022
Completion date at registration
March 2026
Latest completion date
December 2031
Delay so far
69 months
Homes
0
Sold or booked
81%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of FLOW BAVDHAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Flow Bavdhan100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Flow Bavdhan: covers 1 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on FLOW BAVDHAN every month.

FLOW BAVDHAN: buildings, flats and land, as filed on MahaRERA

  • Buildings: Flow Bavdhan (7 floors, 62 units)
  • Land: 1,736 sq m (about 0.4 acres) · sanctioned built-up 9,136 sq m · recreational space 145 sq m

The builder’s record and reviews

Triaa Lifespaces (a group of 7 linked companies) has 13 projects on MahaRERA since 2021, this one included. Of the 9 GharKundli has checked: 8 still being built, 2 past the promised date (typically 12 months late); 1 lapsed. 20 complaints on MahaRERA across 5 projects.

Read Google reviews of FLOW BAVDHAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

FLOW BAVDHAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about FLOW BAVDHAN

What is the possession date of FLOW BAVDHAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for FLOW BAVDHAN in Bavdhan, Pune is 31 December 2031 — 69 months later than 31 March 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for FLOW BAVDHAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date FLOW BAVDHAN's builder has filed on MahaRERA, the official one, is 31 December 2031, already 69 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of FLOW BAVDHAN extended?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW BAVDHAN's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "We have completed 57 shops out of 62 shops and received Occupancy Certificate for the same (as attached). Remaining 5 shops have not been built as yet and not sold as well.".

What is the RERA number of FLOW BAVDHAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of FLOW BAVDHAN in Bavdhan, Pune is P52100033942.

Is FLOW BAVDHAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW BAVDHAN is registered as P52100033942 and its status is "Registered and active".

What is the construction status of FLOW BAVDHAN?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW BAVDHAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Flow Bavdhan is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does FLOW BAVDHAN have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is FLOW BAVDHAN safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW BAVDHAN is registered on MahaRERA as P52100033942, its completion date has moved 69 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if FLOW BAVDHAN's possession date changes?

The latest dates are on FLOW BAVDHAN's MahaRERA page (P52100033942). GharKundli's Kundli Watch sends a free WhatsApp update on FLOW BAVDHAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does FLOW BAVDHAN have?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW BAVDHAN has one building filed: Flow Bavdhan with 7 floors and 62 units.

How big is the land of FLOW BAVDHAN?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW BAVDHAN stands on 1,736 sq m of land (about 0.4 acres), with 9,136 sq m of sanctioned built-up area and 145 sq m of recreational open space.

What is the track record of FLOW BAVDHAN's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Triaa Lifespaces (a group of 7 linked companies) has 13 projects on MahaRERA since 2021, this one included. Of the 9 GharKundli has checked: 8 still being built, 2 past the promised date (typically 12 months late); 1 lapsed. 20 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of FLOW BAVDHAN?

Google Maps has reviews of FLOW BAVDHAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is FLOW BAVDHAN?

FLOW BAVDHAN by VMC LANDMARK REALTY LLP (Triaa) is in Bavdhan, Pune (pincode 411021), Maharashtra, and is registered on MahaRERA as P52100033942, per GharKundli's check of MahaRERA records.

How many homes are in FLOW BAVDHAN?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW BAVDHAN has 0 homes in 1 tower registered on MahaRERA, and 81% of them are sold or booked.

When was FLOW BAVDHAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW BAVDHAN was registered on MahaRERA on 14 March 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on FLOW BAVDHAN?

No court cases are listed for FLOW BAVDHAN on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of FLOW BAVDHAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VMC LANDMARK REALTY LLP, the company Triaa files this project under, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2031 in Pune →

Other projects in Bavdhan

All 226 projects in Armament (411021) →

Other projects by VMC LANDMARK REALTY LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.