Possession date of YASHOBHOOMI PHASE II: 30 April 2027, moved from 30 June 2025 (18 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100045296, and currently active. Its completion date has moved from June 2025 to April 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about YASHOBHOOMI PHASE II?
How the possession date of YASHOBHOOMI PHASE II has moved
30 June 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT52100013824)
Reason the builder gave MahaRERA: “PROPOSED EXTENDED DATED OF COMPLETION 31/12/2026”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: YASHOBHOOMI PHASE II’s extension records on MahaRERA (P52100045296), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on YASHOBHOOMI PHASE II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100045296
- Status
- Registered and active
- Builder
- RAMESHWAR CONSTRUCTIONS
- Location
- Regular Track, Pune · 411015
- Project type
- Residential / Group Housing
- Registered on
- 12 May 2022
- Completion date at registration
- June 2025
- Latest completion date
- April 2027
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 91
- Sold or booked
- 87%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of YASHOBHOOMI PHASE II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| YASHOBHOOMI PHASE II | 75% | 80% | 50% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- YASHOBHOOMI PHASE II: covers G+9
Want to know when this changes? Kundli Watch sends a free WhatsApp update on YASHOBHOOMI PHASE II every month.
YASHOBHOOMI PHASE II: buildings, flats and land, as filed on MahaRERA
- Buildings: YASHOBHOOMI PHASE II (10 floors, 91 units)
- Land: 4,200 sq m (about 1.0 acres) · sanctioned built-up 6,952 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of YASHOBHOOMI PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
YASHOBHOOMI PHASE II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about YASHOBHOOMI PHASE II
What is the possession date of YASHOBHOOMI PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for YASHOBHOOMI PHASE II in Regular Track, Pune is 30 April 2027 — 18 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for YASHOBHOOMI PHASE II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date YASHOBHOOMI PHASE II's builder has filed on MahaRERA, the official one, is 30 April 2027, already 18 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of YASHOBHOOMI PHASE II extended?
According to GharKundli's check of MahaRERA records (updated November 2026), YASHOBHOOMI PHASE II's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "PROPOSED EXTENDED DATED OF COMPLETION 31/12/2026". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of YASHOBHOOMI PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of YASHOBHOOMI PHASE II in Regular Track, Pune is P52100045296.
Is YASHOBHOOMI PHASE II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), YASHOBHOOMI PHASE II is registered as P52100045296 and its status is "Registered and active".
What is the construction status of YASHOBHOOMI PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), YASHOBHOOMI PHASE II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on YASHOBHOOMI PHASE II is 80% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does YASHOBHOOMI PHASE II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is YASHOBHOOMI PHASE II safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), YASHOBHOOMI PHASE II is registered on MahaRERA as P52100045296, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if YASHOBHOOMI PHASE II's possession date changes?
The latest dates are on YASHOBHOOMI PHASE II's MahaRERA page (P52100045296). GharKundli's Kundli Watch sends a free WhatsApp update on YASHOBHOOMI PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does YASHOBHOOMI PHASE II have?
According to GharKundli's check of MahaRERA records (updated November 2026), YASHOBHOOMI PHASE II has one building filed: YASHOBHOOMI PHASE II with 10 floors and 91 units.
How big is the land of YASHOBHOOMI PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), YASHOBHOOMI PHASE II stands on 4,200 sq m of land (about 1.0 acres), with 6,952 sq m of sanctioned built-up area.
Where can I read reviews of YASHOBHOOMI PHASE II?
Google Maps has reviews of YASHOBHOOMI PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is YASHOBHOOMI PHASE II?
YASHOBHOOMI PHASE II by RAMESHWAR CONSTRUCTIONS is in Regular Track, Pune (pincode 411015), Maharashtra, and is registered on MahaRERA as P52100045296, per GharKundli's check of MahaRERA records.
How many homes are in YASHOBHOOMI PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), YASHOBHOOMI PHASE II has 91 homes in 1 tower registered on MahaRERA, and 87% of them are sold or booked.
When was YASHOBHOOMI PHASE II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), YASHOBHOOMI PHASE II was registered on MahaRERA on 12 May 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on YASHOBHOOMI PHASE II?
No court cases are listed for YASHOBHOOMI PHASE II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of YASHOBHOOMI PHASE II?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAMESHWAR CONSTRUCTIONS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of YASHOBHOOMI PHASE II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Haveli
- SnehKunj
- QUE 101 PHASE I
- SIDDHI AURUM
- MADHUGHAT
- DYNAMIC SOLITAIRE – PHASE II
- CULLINAN
- ATS - THE CONDOMINIUMS
- ADI PRIME
Other projects by RAMESHWAR CONSTRUCTIONS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.