Vrundavan Park
by Sunil Ganpati Aitavadekar · Sikandar Nagar, Pune 413102
What’s in the report? →Possession date of Vrundavan Park (MahaRERA P52100053452): 30 April 2028, moved from 7 April 2025 (32 months later). It has 288 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100053452, and currently active. Its completion date has moved from April 2025 to April 2028: 32 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100053452, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Vrundavan Park?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Vrundavan Park has moved
7 April 2025
Completion date given when the project was registered
7 April 2027
Extended at the builder's request (MahaRERA application EXT52100019094)
Reason the builder gave MahaRERA: “The project, initially scheduled to be completed within the stipulated timeframe (i.e. dated 7 April 2025), is facing unforeseen challenges due to its complexity and the volume of work involved.”
31 December 2027
Extended at the builder's request (MahaRERA application EA29122519083)
Reason the builder gave MahaRERA: “Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/12/2027 to complete the project”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Vrundavan Park’s extension records on MahaRERA (P52100053452), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vrundavan Park
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100053452
- Status
- Registered and active
- Builder
- Sunil Ganpati Aitavadekar
- Location
- Sikandar Nagar, Pune · 413102
- Project type
- Residential / Group Housing
- Registered on
- 6 Nov 2023
- Completion date at registration
- April 2025
- Latest completion date
- April 2028
- Delay so far
- 32 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 288
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Vrundavan Park, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Vrundavan Park Building A | 0% | 40% | 10% | 0% |
| Vrundavan Park Building B | 0% | 40% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Vrundavan Park Building A: covers G+1st to 9th floors
- Vrundavan Park Building B: covers G+1st to 9th floors
Latest CC order on MahaRERA: dated 29/03/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vrundavan Park every 1–2 months.
Vrundavan Park: buildings, flats and land, as filed on MahaRERA
- Buildings: Vrundavan Park Building A (10 floors, 144 units) · Vrundavan Park Building B (10 floors, 144 units)
- Car parking: 88 covered
- Land: 10,800 sq m (about 2.7 acres) · sanctioned built-up 17,076 sq m · recreational space 1,065 sq m
- Land, as filed: 205/2
- Map: Get directions
The builder’s record and reviews
Sunil Ganpati Aitavadekar has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 15 months late). No complaints on MahaRERA.
Read Google reviews of Vrundavan Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vrundavan Park: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vrundavan Park
What is the possession date of Vrundavan Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vrundavan Park in Sikandar Nagar, Pune is 30 April 2028 — 32 months later than 7 April 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 32 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Vrundavan Park?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vrundavan Park's builder has filed on MahaRERA, the official one, is 30 April 2028, already 32 months later than the 7 April 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vrundavan Park extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Park's builder applied to MahaRERA to extend the completion date 2 times: to 7 April 2027, giving the reason "The project, initially scheduled to be completed within the stipulated timeframe (i.e. dated 7 April 2025), is facing unforeseen challenges due to its complexity and the volume of work involved."; to 31 December 2027, giving the reason "Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/12/2027 to complete the project". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Vrundavan Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vrundavan Park in Sikandar Nagar, Pune is P52100053452.
Is Vrundavan Park registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Park is registered as P52100053452 and its status is "Registered and active".
What is the current construction status of Vrundavan Park? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Park's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 40% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Vrundavan Park have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vrundavan Park safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Park is registered on MahaRERA as P52100053452, its completion date has moved 32 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vrundavan Park?
Vrundavan Park is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vrundavan Park?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vrundavan Park: gharkundli.com/tools/property-cost-calculator
Has Vrundavan Park received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Park is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Vrundavan Park uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vrundavan Park was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Vrundavan Park's possession date changes?
The latest dates are on Vrundavan Park's MahaRERA page (P52100053452). GharKundli's Kundli Watch sends a free WhatsApp update on Vrundavan Park every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vrundavan Park have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Park has 2 buildings filed: Vrundavan Park Building A with 10 floors and 144 units; Vrundavan Park Building B with 10 floors and 144 units.
How much parking does Vrundavan Park have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 88 covered car parking spaces for Vrundavan Park.
How big is the land of Vrundavan Park?
According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Park stands on 10,800 sq m of land (about 2.7 acres), with 17,076 sq m of sanctioned built-up area and 1,065 sq m of recreational open space.
What is the track record of Vrundavan Park's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunil Ganpati Aitavadekar has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 15 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Vrundavan Park?
Google Maps has reviews of Vrundavan Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vrundavan Park?
Vrundavan Park by Sunil Ganpati Aitavadekar is in Sikandar Nagar, Pune, pincode 413102, Maharashtra, and is registered on MahaRERA as P52100053452, per GharKundli's check of MahaRERA records. Its land is filed as 205/2. GharKundli lists all 373 MahaRERA projects in Baramati (413102).
How many flats are in Vrundavan Park, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Park has 288 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.
When was Vrundavan Park registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vrundavan Park was registered on MahaRERA on 6 November 2023. GharKundli did not find a title report on the land on file there.
Does Vrundavan Park have any legal issues or court cases?
No court cases are listed for Vrundavan Park on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Vrundavan Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sunil Ganpati Aitavadekar, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vrundavan Park
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Pune →
Other projects in Baramati
- Shree Ganesha Icon
- Shreeram Icon
- Capital Tower & Silver Leaf
- Shrihari Vishwa
- Shree Heights
- Sharada Baug
- Ankur Infra
- Shivshri Heights
Other projects by Sunil Ganpati Aitavadekar
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.