Neumec Niwara
by Neumec Venture · Oak Lane, Fort, MumbaiAlso near Vile Parle East, Vile Parle West, Vileparle East
Possession date of Neumec Niwara: 30 September 2027, moved from 30 March 2020 (90 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800003319, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Neumec Niwara?
GharKundli’s full report on Neumec Niwara
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800003319
- Status
- Registered and active
- Builder
- Neumec Venture
- Location
- Oak Lane, Fort, Mumbai · 400057
- Project type
- Others
- Registered on
- 5 Aug 2017
- Completion date at registration
- March 2020
- Latest completion date
- September 2027
- Delay so far
- 90 months
- Homes
- 14
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Neumec Niwara, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NEUMEC NIWARA | 100% | 100% | 100% | 60% |
Commencement certificate (CC), as filed on MahaRERA
- NEUMEC NIWARA: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Neumec Niwara every month.
Neumec Niwara: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 332 – 502 | 9 |
| 2 BHK | 695 | 5 |
| Shops | 292 | 1 |
| Office Space | 477 | 1 |
- Buildings: NEUMEC NIWARA (11 floors, 16 units)
- Land: 650 sq m (about 0.2 acres) · sanctioned built-up 526 sq m · recreational space 120 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Neumec Estate Developer (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 1 finished, all within the promised date; 7 still being built, 6 past the promised date (typically 40 months late); 2 lapsed. 12 complaints on MahaRERA across 4 projects.
Read Google reviews of Neumec Niwara →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Neumec Niwara: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Neumec Niwara
What is the possession date of Neumec Niwara?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Neumec Niwara in Oak Lane, Fort, Mumbai is 30 September 2027 — 90 months later than 30 March 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Neumec Niwara?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Neumec Niwara's builder has filed on MahaRERA, the official one, is 30 September 2027, already 90 months later than the 30 March 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Neumec Niwara?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Neumec Niwara in Oak Lane, Fort, Mumbai is P51800003319.
Is Neumec Niwara registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neumec Niwara is registered as P51800003319 and its status is "Registered and active".
What is the construction status of Neumec Niwara?
According to GharKundli's check of MahaRERA records (updated October 2026), Neumec Niwara's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NEUMEC NIWARA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Neumec Niwara have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Neumec Niwara safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Neumec Niwara is registered on MahaRERA as P51800003319, its completion date has moved 90 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Neumec Niwara's possession date changes?
The latest dates are on Neumec Niwara's MahaRERA page (P51800003319). GharKundli's Kundli Watch sends a free WhatsApp update on Neumec Niwara every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Neumec Niwara have?
According to GharKundli's check of MahaRERA records (updated October 2026), Neumec Niwara has one building filed: NEUMEC NIWARA with 11 floors and 16 units.
What are the flat sizes (carpet area) in Neumec Niwara?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Neumec Niwara: 1 BHK: 332 to 502 sq ft carpet (9 homes); 2 BHK: 695 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Neumec Niwara?
According to GharKundli's check of MahaRERA records (updated October 2026), Neumec Niwara stands on 650 sq m of land (about 0.2 acres), with 526 sq m of sanctioned built-up area and 120 sq m of recreational open space.
What is the track record of Neumec Niwara's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Neumec Estate Developer (a group of 7 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 1 finished, all within the promised date; 7 still being built, 6 past the promised date (typically 40 months late); 2 lapsed. 12 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Neumec Niwara?
Google Maps has reviews of Neumec Niwara written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Neumec Niwara?
Neumec Niwara by Neumec Venture is in Oak Lane, Fort, Mumbai (pincode 400057), near Vile Parle East, Vile Parle West, Vileparle East, Maharashtra, and is registered on MahaRERA as P51800003319, per GharKundli's check of MahaRERA records.
How many homes are in Neumec Niwara?
According to GharKundli's check of MahaRERA records (updated October 2026), Neumec Niwara has 14 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Neumec Niwara registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Neumec Niwara was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Neumec Niwara?
No court cases are listed for Neumec Niwara on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Neumec Niwara?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Neumec Venture, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Neumec Niwara
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
All projects in Vile Parle East (400057) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.