JANAVI PLAZA, JANAVI TOWER
by JANAVI BUILDERS & DEVELOPERS · Vasai East, Palghar
Possession date of JANAVI PLAZA, JANAVI TOWER: 31 December 2024, moved from 30 May 2022 (31 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P99000022673. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about JANAVI PLAZA, JANAVI TOWER?
How the possession date of JANAVI PLAZA, JANAVI TOWER has moved
30 May 2022
Completion date given when the project was registered
29 May 2023
Extended at the builder's request (MahaRERA application EXT99000011999)
Reason the builder gave MahaRERA:
“DUE TO SOME FINANCIAL PROBLEM AND BYUER NOT IN OPEN MARKET, AS WE ARE HAVING LARGE AMOUNT OF UNSOLD FLAT/S IN OUR PROJECT, WHICH WE WILL SALE WITHIN SHROT PERIOD. SO WE REQUEST YOU TO KINDLY DO THE NEEDFUL FOR EXTENSION OF PROJECT FOR ATLEA…” Read the full reason
“DUE TO SOME FINANCIAL PROBLEM AND BYUER NOT IN OPEN MARKET, AS WE ARE HAVING LARGE AMOUNT OF UNSOLD FLAT/S IN OUR PROJECT, WHICH WE WILL SALE WITHIN SHROT PERIOD. SO WE REQUEST YOU TO KINDLY DO THE NEEDFUL FOR EXTENSION OF PROJECT FOR ATLEAST ONE YEAR”31 December 2024
Extended at the builder's request (MahaRERA application EXT99000017262)
Reason the builder gave MahaRERA:
“Dear Sir, With reference to cited subject, We the undersigned developer of the Project M/S JANAVI BUILDERS & DEVELOPERS would like to inform you that my Maharera Project due date has been expired, Due to covid 19 Pandemic and market slow do…” Read the full reason
“Dear Sir, With reference to cited subject, We the undersigned developer of the Project M/S JANAVI BUILDERS & DEVELOPERS would like to inform you that my Maharera Project due date has been expired, Due to covid 19 Pandemic and market slow down we could not complete the entire project within the stipulated timeline. Thus, our honour, in the larger interest of the Project kindly extends the Project further till 31-12-2024. We hope that a balanced approach keeping in view the object and intent of the enactment and the rights and liabilities of promoter and allottees in larger public interest is…”
Source: JANAVI PLAZA, JANAVI TOWER’s extension records on MahaRERA (P99000022673), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on JANAVI PLAZA, JANAVI TOWER
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000022673
- Status
- Lapsed (registration period ended)
- Builder
- JANAVI BUILDERS & DEVELOPERS
- Location
- Vasai East, Palghar · 401208
- Project type
- Residential / Group Housing
- Registered on
- 12 Oct 2019
- Completion date at registration
- May 2022
- Latest completion date
- December 2024
- Delay so far
- 31 months
- Homes
- 120
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of JANAVI PLAZA, JANAVI TOWER, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| JANAVI PLAZA | 100% | 100% | 100% | 100% |
| JANAVI TOWER | 100% | 100% | 100% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on JANAVI PLAZA, JANAVI TOWER every month.
JANAVI PLAZA, JANAVI TOWER: buildings, flats and land, as filed on MahaRERA
- Buildings: JANAVI PLAZA (2 floors) · JANAVI TOWER (12 floors)
- Land: 4,500 sq m (about 1.1 acres) · sanctioned built-up 5,034 sq m · recreational space 377 sq m
- Boundaries filed include: WALIV GAON ROAD
The builder’s record and reviews
Janavi Builders & Developers has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of JANAVI PLAZA, JANAVI TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
JANAVI PLAZA, JANAVI TOWER: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about JANAVI PLAZA, JANAVI TOWER
What is the possession date of JANAVI PLAZA, JANAVI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for JANAVI PLAZA, JANAVI TOWER in Vasai East, Palghar is 31 December 2024 — 31 months later than 30 May 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for JANAVI PLAZA, JANAVI TOWER?
Builders and listing sites often quote an earlier "target" date for handover. The completion date JANAVI PLAZA, JANAVI TOWER's builder has filed on MahaRERA, the official one, is 31 December 2024, already 31 months later than the 30 May 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of JANAVI PLAZA, JANAVI TOWER extended?
According to GharKundli's check of MahaRERA records (updated November 2026), JANAVI PLAZA, JANAVI TOWER's builder applied to MahaRERA to extend the completion date 2 times: to 29 May 2023, giving the reason "DUE TO SOME FINANCIAL PROBLEM AND BYUER NOT IN OPEN MARKET, AS WE ARE HAVING LARGE AMOUNT OF UNSOLD FLAT/S IN OUR PROJECT, WHICH WE WILL SALE WITHIN SHROT PERIOD. SO WE REQUEST YOU TO KINDLY DO THE NEEDFUL FOR EXTENSION OF PROJECT FOR ATLEAST ONE YEAR"; to 31 December 2024, giving the reason "Dear Sir, With reference to cited subject, We the undersigned developer of the Project M/S JANAVI BUILDERS & DEVELOPERS would like to inform you that my Maharera Project due date has been expired, Due to covid 19 Pandemic and market slow down we could not complete the entire project within the stipulated timeline. Thus, our honour, in the larger interest of the Project kindly extends the Project further till 31-12-2024. We hope that a balanced approach keeping in view the object and intent of the enactment and the rights and liabilities of promoter and allottees in larger public interest is…".
What is the RERA number of JANAVI PLAZA, JANAVI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of JANAVI PLAZA, JANAVI TOWER in Vasai East, Palghar is P99000022673.
Is JANAVI PLAZA, JANAVI TOWER registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), JANAVI PLAZA, JANAVI TOWER is registered as P99000022673 and its status is "Lapsed (registration period ended)".
What is the construction status of JANAVI PLAZA, JANAVI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), JANAVI PLAZA, JANAVI TOWER's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does JANAVI PLAZA, JANAVI TOWER have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is JANAVI PLAZA, JANAVI TOWER safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), JANAVI PLAZA, JANAVI TOWER is registered on MahaRERA as P99000022673, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 31 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if JANAVI PLAZA, JANAVI TOWER's possession date changes?
The latest dates are on JANAVI PLAZA, JANAVI TOWER's MahaRERA page (P99000022673). GharKundli's Kundli Watch sends a free WhatsApp update on JANAVI PLAZA, JANAVI TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does JANAVI PLAZA, JANAVI TOWER have?
According to GharKundli's check of MahaRERA records (updated November 2026), JANAVI PLAZA, JANAVI TOWER has 2 buildings filed: JANAVI PLAZA with 2 floors; JANAVI TOWER with 12 floors.
How big is the land of JANAVI PLAZA, JANAVI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), JANAVI PLAZA, JANAVI TOWER stands on 4,500 sq m of land (about 1.1 acres), with 5,034 sq m of sanctioned built-up area and 377 sq m of recreational open space.
What is the track record of JANAVI PLAZA, JANAVI TOWER's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Janavi Builders & Developers has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of JANAVI PLAZA, JANAVI TOWER?
Google Maps has reviews of JANAVI PLAZA, JANAVI TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is JANAVI PLAZA, JANAVI TOWER?
JANAVI PLAZA, JANAVI TOWER by JANAVI BUILDERS & DEVELOPERS is in Vasai East, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000022673, per GharKundli's check of MahaRERA records. Its boundaries filed there include WALIV GAON ROAD.
How many homes are in JANAVI PLAZA, JANAVI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), JANAVI PLAZA, JANAVI TOWER has 120 homes in 2 towers registered on MahaRERA.
When was JANAVI PLAZA, JANAVI TOWER registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), JANAVI PLAZA, JANAVI TOWER was registered on MahaRERA on 12 October 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on JANAVI PLAZA, JANAVI TOWER?
No court cases are listed for JANAVI PLAZA, JANAVI TOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of JANAVI PLAZA, JANAVI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is JANAVI BUILDERS & DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of JANAVI PLAZA, JANAVI TOWER
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401208
- Imperial Splendora F wing
- SERENO
- Agarwal Sky Heights
- Sunteck OneWorld -Tower 1
- Akhand Phase 3
- ARVIAN GENESIS
- ANANTA ONE
- Suraksha Smart City - Phase II
Other projects by JANAVI BUILDERS & DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.