TULSI CHAMBERS
by SURANA CONSTRUCTION (CHEMBUR ) · Opp Union Bank, MumbaiAlso near Chembur, Kurla, Ghatla
Possession date of TULSI CHAMBERS: 30 June 2026, moved from 30 June 2021 (60 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800012437. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 14 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (June 2026) has passed.
What do you want to know about TULSI CHAMBERS?
GharKundli’s full report on TULSI CHAMBERS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 14 complaints and 2 court cases, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800012437
- Status
- Lapsed (registration period ended)
- Builder
- SURANA CONSTRUCTION (CHEMBUR )
- Location
- Opp Union Bank, Mumbai · 400071
- Project type
- Commercial
- Registered on
- 1 Sep 2017
- Completion date at registration
- June 2021
- Latest completion date
- June 2026
- Delay so far
- 60 months
- Homes
- 0
- Sold or booked
- 96%
- Towers
- 1
- Complaints on MahaRERA
- 14
- Court cases listed
- 2
- Appeals at the tribunal
- 13
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of TULSI CHAMBERS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shivaji Nagar SRA Project Phase 1 | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- Shivaji Nagar SRA Project Phase 1: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on TULSI CHAMBERS every month.
TULSI CHAMBERS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 70 – 1,121 | 129 |
| Shops | 498 – 1,146 | 3 |
- Buildings: Shivaji Nagar SRA Project Phase 1 (17 floors, 132 units)
- Land: 4,017 sq m (about 1.0 acres) · sanctioned built-up 16,068 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Surana Construction Chembur has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. 21 complaints on MahaRERA across 2 projects.
Read Google reviews of TULSI CHAMBERS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
TULSI CHAMBERS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about TULSI CHAMBERS
What is the possession date of TULSI CHAMBERS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TULSI CHAMBERS in Opp Union Bank, Mumbai is 30 June 2026 — 60 months later than 30 June 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for TULSI CHAMBERS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date TULSI CHAMBERS's builder has filed on MahaRERA, the official one, is 30 June 2026, already 60 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of TULSI CHAMBERS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TULSI CHAMBERS in Opp Union Bank, Mumbai is P51800012437.
Is TULSI CHAMBERS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSI CHAMBERS is registered as P51800012437 and its status is "Lapsed (registration period ended)".
What is the construction status of TULSI CHAMBERS?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSI CHAMBERS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Shivaji Nagar SRA Project Phase 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does TULSI CHAMBERS have complaints on MahaRERA?
14 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is TULSI CHAMBERS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSI CHAMBERS is registered on MahaRERA as P51800012437, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 60 months since registration and 14 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if TULSI CHAMBERS's possession date changes?
The latest dates are on TULSI CHAMBERS's MahaRERA page (P51800012437). GharKundli's Kundli Watch sends a free WhatsApp update on TULSI CHAMBERS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does TULSI CHAMBERS have?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSI CHAMBERS has one building filed: Shivaji Nagar SRA Project Phase 1 with 17 floors and 132 units.
How big is the land of TULSI CHAMBERS?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSI CHAMBERS stands on 4,017 sq m of land (about 1.0 acres), with 16,068 sq m of sanctioned built-up area.
What is the track record of TULSI CHAMBERS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Surana Construction Chembur has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 22 months late); 1 lapsed. 21 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of TULSI CHAMBERS?
Google Maps has reviews of TULSI CHAMBERS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 14 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is TULSI CHAMBERS?
TULSI CHAMBERS by SURANA CONSTRUCTION (CHEMBUR ) is in Opp Union Bank, Mumbai (pincode 400071), near Chembur, Kurla, Ghatla, Maharashtra, and is registered on MahaRERA as P51800012437, per GharKundli's check of MahaRERA records.
How many homes are in TULSI CHAMBERS?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSI CHAMBERS has 0 homes in 1 tower registered on MahaRERA, and 96% of them are sold or booked.
When was TULSI CHAMBERS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TULSI CHAMBERS was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on TULSI CHAMBERS?
2 court cases are listed for TULSI CHAMBERS on MahaRERA, and 13 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of TULSI CHAMBERS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SURANA CONSTRUCTION (CHEMBUR ), which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of TULSI CHAMBERS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
All projects in Chembur (400071) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.