by Onyx Promoters LLP (Gagan) · Kharadi, Pune 411014Also near Wagholi, Pune Camp

What’s in the report? →

Possession date of Gagan Avencia (MahaRERA P52100005102): 30 September 2025, moved from 31 March 2021 (54 months later), and it has already passed. It has 307 homes, 98% sold or booked. 13 complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100005102. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project.

Source: MahaRERA website — records for P52100005102, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (September 2025) has passed.

What do you want to know about Gagan Avencia?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Gagan Avencia has moved

  1. 31 March 2021

    Completion date given when the project was registered

  2. 31 March 2022

    Extended at the builder's request (MahaRERA application EXT52100001546)

    Reason the builder gave MahaRERA:
    “1) Our Project was originally proposed to be implemented on a portion admeasuring 10,724.80 sq.mtrs out of land admeasuring Hectares 01=20 Ares bearing Survey No.63 Hissa No.1/1, Village Kharadi, Pune. 2) Accordingly, the Maharashtra Real E…” Read the full reason“1) Our Project was originally proposed to be implemented on a portion admeasuring 10,724.80 sq.mtrs out of land admeasuring Hectares 01=20 Ares bearing Survey No.63 Hissa No.1/1, Village Kharadi, Pune. 2) Accordingly, the Maharashtra Real Estate Regulatory Authority has granted Registration. 3) We are in the process of acquiring some additional adjoining land out of land bearing Survey No.63 Hissa No.2, Kharadi and we propose to amalgamate such additional land with our existing Layout and develop a separate Project known as “GAGAN AVENCIA PHASE II”. The Building to be constructed by us for…”
  3. 30 September 2023

    Extended at the builder's request (MahaRERA application EXT52100013987)

    Reason the builder gave MahaRERA:
    “1) We are the Promoters of the Real Estate Project known as “GAGAN AVENCIA” under implementation by us on land out of Survey No. 63 Hissa No. 1/1 situate, lying and being at Village Kharadi within the Registration Sub-District of Taluka Hav…” Read the full reason“1) We are the Promoters of the Real Estate Project known as “GAGAN AVENCIA” under implementation by us on land out of Survey No. 63 Hissa No. 1/1 situate, lying and being at Village Kharadi within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100005102 dated 09/08/2017. 2) In anticipation that we would complete the said Project on or before 30/03/2023, in our application to you for Registration of our Project, we had mentioned the date of Completion as 30/03/2023. Howeve…”
  4. 30 September 2024

    Extended at the builder's request (MahaRERA application EXT52100017958)

    Reason the builder gave MahaRERA:
    “a. Onyx Promoters LLP is developing a project registered with the MahaRERA under Project Registration No. P52100005102. The Promoter had mentioned the original date of completion as 30th March 2023 and had commenced the construction and dev…” Read the full reason“a. Onyx Promoters LLP is developing a project registered with the MahaRERA under Project Registration No. P52100005102. The Promoter had mentioned the original date of completion as 30th March 2023 and had commenced the construction and development of project accordingly. b. However, on account of COVID-19 outbreak, the development activities at the project were halted. c. Later, during the part-normalcy period of the COVID-19 outbreak, there was acute shortage of skilled and unskilled labours in the Pune region. Due to above reason, the project could not be completed within the specified t…”
  5. 30 September 2025

    Extended at the builder's request (MahaRERA application EXT52100025432)

    Reason the builder gave MahaRERA:
    “1. As per the latest QPR the Construction of the project GAGAN AVENCIA is approximately 90% completed. 2. The proposed completion date for the project was 30/09/2024 but in view of Second wave of COVID-19 pandemic around April 2021, constru…” Read the full reason“1. As per the latest QPR the Construction of the project GAGAN AVENCIA is approximately 90% completed. 2. The proposed completion date for the project was 30/09/2024 but in view of Second wave of COVID-19 pandemic around April 2021, construction workplace came to stand still due to consequent nationwide lockdown.”

Source: Gagan Avencia’s extension records on MahaRERA (P52100005102), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Gagan Avencia

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 13 complaints and 2 court cases, and how it ended
  • Construction pace against the September 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100005102
Status
Lapsed (registration period ended)
Builder
Onyx Promoters LLP
Location
Kharadi, Pune · 411014
Project type
Others
Registered on
9 Aug 2017
Completion date at registration
March 2021
Latest completion date
September 2025
Delay so far
54 months
Homes
307
Sold or booked
98%
Towers
5
Complaints on MahaRERA
13
Court cases listed
2
Appeals at the tribunal
5
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Gagan Avencia, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A100%100%100%100%
B100%100%100%100%
Commercial and Mhada100%100%100%85%
C100%100%100%100%
D100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • A: covers 21 floors
  • B: covers 21 floors
  • Commercial and Mhada: covers 17 floors
  • C: covers 20 floors
  • D: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gagan Avencia every 1–2 months.

Gagan Avencia: buildings, flats and land, as filed on MahaRERA

  • Buildings: A (21 floors, 68 units) · B (21 floors, 67 units) · Commercial and Mhada (17 floors, 92 units) · C (20 floors, 67 units) · D (20 floors, 68 units)
  • Land: 14,025 sq m (about 3.5 acres) · sanctioned built-up 30,889 sq m · recreational space 907 sq m
  • Land, as filed: S.no 63/1/1 & 63/2
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Gagan Landmarks (a group of 8 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 30 months); 5 still being built, 2 past the promised date (typically 18 months late); 5 lapsed. 103 complaints on MahaRERA across 9 projects.

Read Google reviews of Gagan Avencia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Gagan Avencia: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Gagan Avencia

What is the possession date of Gagan Avencia?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gagan Avencia in Kharadi, Pune is 30 September 2025 — 54 months later than 31 March 2021, the date given at registration. That date has already passed.

The date has already moved 54 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Gagan Avencia?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Gagan Avencia's builder has filed on MahaRERA, the official one, is 30 September 2025, already 54 months later than the 31 March 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Gagan Avencia extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Avencia's builder applied to MahaRERA to extend the completion date 4 times: to 31 March 2022, giving the reason "1) Our Project was originally proposed to be implemented on a portion admeasuring 10,724.80 sq.mtrs out of land admeasuring Hectares 01=20 Ares bearing Survey No.63 Hissa No.1/1, Village Kharadi, Pune. 2) Accordingly, the Maharashtra Real Estate Regulatory Authority has granted Registration. 3) We are in the process of acquiring some additional adjoining land out of land bearing Survey No.63 Hissa No.2, Kharadi and we propose to amalgamate such additional land with our existing Layout and develop a separate Project known as “GAGAN AVENCIA PHASE II”. The Building to be constructed by us for…"; to 30 September 2023, giving the reason "1) We are the Promoters of the Real Estate Project known as “GAGAN AVENCIA” under implementation by us on land out of Survey No. 63 Hissa No. 1/1 situate, lying and being at Village Kharadi within the Registration Sub-District of Taluka Haveli, District Pune. You were kind enough to grant Registration of the said Project vide your Registration Certificate No. P52100005102 dated 09/08/2017. 2) In anticipation that we would complete the said Project on or before 30/03/2023, in our application to you for Registration of our Project, we had mentioned the date of Completion as 30/03/2023. Howeve…"; to 30 September 2024, giving the reason "a. Onyx Promoters LLP is developing a project registered with the MahaRERA under Project Registration No. P52100005102. The Promoter had mentioned the original date of completion as 30th March 2023 and had commenced the construction and development of project accordingly. b. However, on account of COVID-19 outbreak, the development activities at the project were halted. c. Later, during the part-normalcy period of the COVID-19 outbreak, there was acute shortage of skilled and unskilled labours in the Pune region. Due to above reason, the project could not be completed within the specified t…"; to 30 September 2025, giving the reason "1. As per the latest QPR the Construction of the project GAGAN AVENCIA is approximately 90% completed. 2. The proposed completion date for the project was 30/09/2024 but in view of Second wave of COVID-19 pandemic around April 2021, construction workplace came to stand still due to consequent nationwide lockdown.".

What is the RERA number of Gagan Avencia?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gagan Avencia in Kharadi, Pune is P52100005102.

Is Gagan Avencia registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Avencia is registered as P52100005102 and its status is "Lapsed (registration period ended)".

What is the current construction status of Gagan Avencia? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Avencia's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does Gagan Avencia have complaints on MahaRERA?

13 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

13 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →

Is Gagan Avencia safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Avencia is registered on MahaRERA as P52100005102, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and 13 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Gagan Avencia?

Gagan Avencia isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Gagan Avencia?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Gagan Avencia: gharkundli.com/tools/property-cost-calculator

Has Gagan Avencia received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Avencia isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Gagan Avencia?

According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Avencia's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Gagan Avencia uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Gagan Avencia was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Gagan Avencia have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Gagan Avencia Phase II (PR1261012500098, possession 30 Apr 2031). Check that your agreement names the registration of your own wing.

How can I get updates if Gagan Avencia's possession date changes?

The latest dates are on Gagan Avencia's MahaRERA page (P52100005102). GharKundli's Kundli Watch sends a free WhatsApp update on Gagan Avencia every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Gagan Avencia have?

According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Avencia has 5 buildings filed: A with 21 floors and 68 units; B with 21 floors and 67 units; Commercial and Mhada with 17 floors and 92 units; C with 20 floors and 67 units; D with 20 floors and 68 units.

How big is the land of Gagan Avencia?

According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Avencia stands on 14,025 sq m of land (about 3.5 acres), with 30,889 sq m of sanctioned built-up area and 907 sq m of recreational open space.

What is the track record of Gagan Avencia's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Landmarks (a group of 8 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 30 months); 5 still being built, 2 past the promised date (typically 18 months late); 5 lapsed. 103 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Gagan Avencia?

Google Maps has reviews of Gagan Avencia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 13 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Gagan Avencia?

Gagan Avencia by Onyx Promoters LLP (Gagan) is in Kharadi, Pune, pincode 411014 (near Wagholi, Pune Camp), Maharashtra, and is registered on MahaRERA as P52100005102, per GharKundli's check of MahaRERA records. Its land is filed as S.no 63/1/1 & 63/2. GharKundli lists all 323 MahaRERA projects in Kharadi (411014).

How many flats are in Gagan Avencia, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Avencia has 307 homes in 5 towers registered on MahaRERA, and 98% of them are sold or booked.

When was Gagan Avencia registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Gagan Avencia was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Does Gagan Avencia have any legal issues or court cases?

2 court cases are listed for Gagan Avencia on MahaRERA, and 5 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Gagan Avencia?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Onyx Promoters LLP, the company Gagan files this project under, which has 1 other project registered on MahaRERA.

Other projects in Haveli

All 323 projects in Kharadi (411014) →

Other projects by Onyx Promoters LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.