Mist Aqua

by GM Promoters LLP (Gokhale) · Erandwane, Pune 411042

What’s in the report? →

Possession date of Mist Aqua (MahaRERA P52100005785): 30 October 2020, moved from 31 August 2018 (26 months later), and it has already passed. It has 150 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100005785. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100005785, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (October 2020) has passed.

What do you want to know about Mist Aqua?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Mist Aqua has moved

  1. 31 August 2018

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT52100000632)

    Reason the builder gave MahaRERA: “The building construction is completed, however, Completion certificate application is pending for installation of transformer on the project land which will be installed within 2 months.”
  3. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT52100003970)

    Reason the builder gave MahaRERA: “The construction of the building is completed, however formation of society is in process. After which Conveyance Deed will be executed in favour of Society”
  4. 30 October 2020

    Revised completion date on MahaRERA

Source: Mist Aqua’s extension records on MahaRERA (P52100005785), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mist Aqua

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100005785
Status
Lapsed (registration period ended)
Builder
GM Promoters LLP
Location
Erandwane, Pune · 411042
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
August 2018
Latest completion date
October 2020
Delay so far
26 months
Homes
150
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Mist Aqua, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Aqua B100%100%100%100%
Aqua C100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mist Aqua every 1–2 months.

Mist Aqua: buildings, flats and land, as filed on MahaRERA

  • Buildings: Aqua B (14 floors) · Aqua C (14 floors)
  • Land: 7,157 sq m (about 1.8 acres) · sanctioned built-up 6,458 sq m · recreational space 1,165 sq m
  • Land, as filed: S No 121
  • Map: Get directions

The builder’s record and reviews

Gokhale Constructions (a group of 17 linked companies) has 53 projects on MahaRERA since 2017, this one included. Of the 51 GharKundli has checked: 26 finished, 16 within the promised date and 10 needed more time (typically 14 months); 10 still being built, 4 past the promised date (typically 5 months late); 15 lapsed. 38 complaints on MahaRERA across 19 projects.

Read Google reviews of Mist Aqua →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mist Aqua: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Mist Aqua

What is the possession date of Mist Aqua?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mist Aqua in Erandwane, Pune is 30 October 2020 — 26 months later than 31 August 2018, the date given at registration. That date has already passed.

The date has already moved 26 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Mist Aqua?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mist Aqua's builder has filed on MahaRERA, the official one, is 30 October 2020, already 26 months later than the 31 August 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Mist Aqua extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Mist Aqua's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2020, giving the reason "The building construction is completed, however, Completion certificate application is pending for installation of transformer on the project land which will be installed within 2 months."; to 30 April 2020, giving the reason "The construction of the building is completed, however formation of society is in process. After which Conveyance Deed will be executed in favour of Society".

What is the RERA number of Mist Aqua?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mist Aqua in Erandwane, Pune is P52100005785.

Is Mist Aqua registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mist Aqua is registered as P52100005785 and its status is "Lapsed (registration period ended)".

What is the current construction status of Mist Aqua? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Mist Aqua's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Mist Aqua have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Mist Aqua safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Mist Aqua is registered on MahaRERA as P52100005785, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 26 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Mist Aqua?

Mist Aqua isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Mist Aqua?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Mist Aqua: gharkundli.com/tools/property-cost-calculator

Has Mist Aqua received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Mist Aqua isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 October 2020 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Mist Aqua?

According to GharKundli's check of MahaRERA records (updated November 2026), Mist Aqua's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 October 2020) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Mist Aqua uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Mist Aqua was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Mist Aqua's possession date changes?

The latest dates are on Mist Aqua's MahaRERA page (P52100005785). GharKundli's Kundli Watch sends a free WhatsApp update on Mist Aqua every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mist Aqua have?

According to GharKundli's check of MahaRERA records (updated November 2026), Mist Aqua has 2 buildings filed: Aqua B with 14 floors; Aqua C with 14 floors.

How big is the land of Mist Aqua?

According to GharKundli's check of MahaRERA records (updated November 2026), Mist Aqua stands on 7,157 sq m of land (about 1.8 acres), with 6,458 sq m of sanctioned built-up area and 1,165 sq m of recreational open space.

What is the track record of Mist Aqua's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Gokhale Constructions (a group of 17 linked companies) has 53 projects on MahaRERA since 2017, this one included. Of the 51 GharKundli has checked: 26 finished, 16 within the promised date and 10 needed more time (typically 14 months); 10 still being built, 4 past the promised date (typically 5 months late); 15 lapsed. 38 complaints on MahaRERA across 19 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Mist Aqua?

Google Maps has reviews of Mist Aqua written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Mist Aqua?

Mist Aqua by GM Promoters LLP (Gokhale) is in Erandwane, Pune, pincode 411042, Maharashtra, and is registered on MahaRERA as P52100005785, per GharKundli's check of MahaRERA records. Its land is filed as S No 121. GharKundli lists all 67 MahaRERA projects in Swargate (411042).

How many flats are in Mist Aqua?

According to GharKundli's check of MahaRERA records (updated November 2026), Mist Aqua has 150 homes in 2 towers registered on MahaRERA.

When was Mist Aqua registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mist Aqua was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Does Mist Aqua have any legal issues or court cases?

No court cases are listed for Mist Aqua on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Mist Aqua?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GM Promoters LLP, the company Gokhale files this project under, which has 1 other project registered on MahaRERA.

Other projects in Swargate (411042)

All 67 projects in Swargate (411042) →

Other projects by GM Promoters LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.