GOLDEN LEAF
by GOLDEN ERECTORS · Haveli, Pune
Possession date of GOLDEN LEAF: 30 April 2024, moved from 31 March 2018 (73 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100005057. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (April 2024) has passed.
What do you want to know about GOLDEN LEAF?
How the possession date of GOLDEN LEAF has moved
31 March 2018
Completion date given when the project was registered
31 March 2019
Extended at the builder's request (MahaRERA application EXT52100000623)
Reason the builder gave MahaRERA: “FUNDS NOT AVAILABLE. FUNDS NOT RECEIVED FROM SOLD FLATS”
30 April 2024
Extended at the builder's request (MahaRERA application EXT52100012735)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 78.31% allottees for purpose of extension of RERA registration period of the said project.”
Source: GOLDEN LEAF’s extension records on MahaRERA (P52100005057), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GOLDEN LEAF
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100005057
- Status
- Lapsed (registration period ended)
- Builder
- GOLDEN ERECTORS
- Location
- Haveli, Pune · 411048
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- March 2018
- Latest completion date
- April 2024
- Delay so far
- 73 months
- Homes
- 125
- Sold or booked
- 39%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of GOLDEN LEAF, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GOLDEN LEAF | 1% | 8% | 90% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GOLDEN LEAF every month.
GOLDEN LEAF: buildings, flats and land, as filed on MahaRERA
- Buildings: GOLDEN LEAF (13 floors)
- Land: 2,250 sq m (about 0.6 acres) · sanctioned built-up 2,542 sq m
- Boundaries filed include: 12 MTS ROAD
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of GOLDEN LEAF →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GOLDEN LEAF: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GOLDEN LEAF
What is the possession date of GOLDEN LEAF?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GOLDEN LEAF in Haveli, Pune is 30 April 2024 — 73 months later than 31 March 2018, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for GOLDEN LEAF?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GOLDEN LEAF's builder has filed on MahaRERA, the official one, is 30 April 2024, already 73 months later than the 31 March 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GOLDEN LEAF extended?
According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN LEAF's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2019, giving the reason "FUNDS NOT AVAILABLE. FUNDS NOT RECEIVED FROM SOLD FLATS"; to 30 April 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 78.31% allottees for purpose of extension of RERA registration period of the said project.".
What is the RERA number of GOLDEN LEAF?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GOLDEN LEAF in Haveli, Pune is P52100005057.
Is GOLDEN LEAF registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN LEAF is registered as P52100005057 and its status is "Lapsed (registration period ended)".
What is the construction status of GOLDEN LEAF?
According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN LEAF's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on GOLDEN LEAF is 8% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does GOLDEN LEAF have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is GOLDEN LEAF safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN LEAF is registered on MahaRERA as P52100005057, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 73 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GOLDEN LEAF's possession date changes?
The latest dates are on GOLDEN LEAF's MahaRERA page (P52100005057). GharKundli's Kundli Watch sends a free WhatsApp update on GOLDEN LEAF every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GOLDEN LEAF have?
According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN LEAF has one building filed: GOLDEN LEAF with 13 floors.
How big is the land of GOLDEN LEAF?
According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN LEAF stands on 2,250 sq m of land (about 0.6 acres), with 2,542 sq m of sanctioned built-up area.
Where can I read reviews of GOLDEN LEAF?
Google Maps has reviews of GOLDEN LEAF written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GOLDEN LEAF?
GOLDEN LEAF by GOLDEN ERECTORS is in Haveli, Pune (pincode 411048), Maharashtra, and is registered on MahaRERA as P52100005057, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 MTS ROAD.
How many homes are in GOLDEN LEAF?
According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN LEAF has 125 homes in 1 tower registered on MahaRERA, and 39% of them are sold or booked.
When was GOLDEN LEAF registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GOLDEN LEAF was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on GOLDEN LEAF?
No court cases are listed for GOLDEN LEAF on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of GOLDEN LEAF?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GOLDEN ERECTORS.
Check it yourself on MahaRERA
- How to check the possession date of GOLDEN LEAF
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Haveli
- SnehKunj
- Sukhwani Palmera Reserves Phase I
- Ekaanta
- Calistara Tower 1
- 38 Daffodils
- Bharat Leelaa
- Calistara Tower 3
- Calistara Tower 2
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.