BLUE BIRD CO OPERATIVE SOCIETY LTD

by ASHA ARUN SANE · Deccan Gymkhana, PuneAlso near Shivajinagar Bhamburda, Model Colony, Shivaji Nagar

Possession: BLUE BIRD CO OPERATIVE SOCIETY LTD is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100018398. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about BLUE BIRD CO OPERATIVE SOCIETY LTD?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of BLUE BIRD CO OPERATIVE SOCIETY LTD has moved

  1. 30 September 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT52100016919)

    Reason the builder gave MahaRERA:
    “We would like to clarify that there was an alteration in the Additional Parking Spaces for which revision was made and a new commencement certificate was availed as of 14-10-2022 having certificate no. CC/1813/22 and the work was completed…” Read the full reason“We would like to clarify that there was an alteration in the Additional Parking Spaces for which revision was made and a new commencement certificate was availed as of 14-10-2022 having certificate no. CC/1813/22 and the work was completed on 21-10-2022 having completion certificate no. OCC/0715/22. Since we have completed the project work slightly beyond the estimated date of completion i.e. 21 days beyond the estimated date of completion, we have been suggested by your department to take an Extension of the project and the same is being done by us. We further need to inform you that pract…”

Source: BLUE BIRD CO OPERATIVE SOCIETY LTD’s extension records on MahaRERA (P52100018398), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on BLUE BIRD CO OPERATIVE SOCIETY LTD

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100018398
Status
Completed
Builder
ASHA ARUN SANE
Location
Deccan Gymkhana, Pune · 411004
Project type
Residential / Group Housing
Registered on
30 Oct 2018
Completion date at registration
September 2022
Latest completion date
June 2023
Delay so far
9 months
Homes
72
Towers
3
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of BLUE BIRD CO OPERATIVE SOCIETY LTD, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A100%100%100%100%
B100%100%100%100%
C100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BLUE BIRD CO OPERATIVE SOCIETY LTD every month.

BLUE BIRD CO OPERATIVE SOCIETY LTD: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of BLUE BIRD CO OPERATIVE SOCIETY LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

BLUE BIRD CO OPERATIVE SOCIETY LTD: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BLUE BIRD CO OPERATIVE SOCIETY LTD

What is the possession date of BLUE BIRD CO OPERATIVE SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BLUE BIRD CO OPERATIVE SOCIETY LTD in Deccan Gymkhana, Pune is 30 June 2023 — 9 months later than 30 September 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for BLUE BIRD CO OPERATIVE SOCIETY LTD?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BLUE BIRD CO OPERATIVE SOCIETY LTD's builder has filed on MahaRERA, the official one, is 30 June 2023, already 9 months later than the 30 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of BLUE BIRD CO OPERATIVE SOCIETY LTD extended?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BIRD CO OPERATIVE SOCIETY LTD's builder applied to MahaRERA to extend the completion date once: to 30 June 2023, giving the reason "We would like to clarify that there was an alteration in the Additional Parking Spaces for which revision was made and a new commencement certificate was availed as of 14-10-2022 having certificate no. CC/1813/22 and the work was completed on 21-10-2022 having completion certificate no. OCC/0715/22. Since we have completed the project work slightly beyond the estimated date of completion i.e. 21 days beyond the estimated date of completion, we have been suggested by your department to take an Extension of the project and the same is being done by us. We further need to inform you that pract…".

What is the RERA number of BLUE BIRD CO OPERATIVE SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BLUE BIRD CO OPERATIVE SOCIETY LTD in Deccan Gymkhana, Pune is P52100018398.

Is BLUE BIRD CO OPERATIVE SOCIETY LTD registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BIRD CO OPERATIVE SOCIETY LTD is registered as P52100018398 and its status is "Completed".

What is the construction status of BLUE BIRD CO OPERATIVE SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BIRD CO OPERATIVE SOCIETY LTD's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does BLUE BIRD CO OPERATIVE SOCIETY LTD have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is BLUE BIRD CO OPERATIVE SOCIETY LTD safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BIRD CO OPERATIVE SOCIETY LTD is registered on MahaRERA as P52100018398, its MahaRERA status is "Completed", its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if BLUE BIRD CO OPERATIVE SOCIETY LTD's possession date changes?

The latest dates are on BLUE BIRD CO OPERATIVE SOCIETY LTD's MahaRERA page (P52100018398). GharKundli's Kundli Watch sends a free WhatsApp update on BLUE BIRD CO OPERATIVE SOCIETY LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BLUE BIRD CO OPERATIVE SOCIETY LTD have?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BIRD CO OPERATIVE SOCIETY LTD has 3 buildings filed: A with 15 floors; B with 15 floors; C with 15 floors.

How big is the land of BLUE BIRD CO OPERATIVE SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BIRD CO OPERATIVE SOCIETY LTD stands on 3,500 sq m of land (about 0.9 acres), with 4,664 sq m of sanctioned built-up area and 3,500 sq m of recreational open space.

Where can I read reviews of BLUE BIRD CO OPERATIVE SOCIETY LTD?

Google Maps has reviews of BLUE BIRD CO OPERATIVE SOCIETY LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is BLUE BIRD CO OPERATIVE SOCIETY LTD?

BLUE BIRD CO OPERATIVE SOCIETY LTD by ASHA ARUN SANE is in Deccan Gymkhana, Pune (pincode 411004), near Shivajinagar Bhamburda, Model Colony, Shivaji Nagar, Maharashtra, and is registered on MahaRERA as P52100018398, per GharKundli's check of MahaRERA records.

How many homes are in BLUE BIRD CO OPERATIVE SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BIRD CO OPERATIVE SOCIETY LTD has 72 homes in 3 towers registered on MahaRERA.

When was BLUE BIRD CO OPERATIVE SOCIETY LTD registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BIRD CO OPERATIVE SOCIETY LTD was registered on MahaRERA on 30 October 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on BLUE BIRD CO OPERATIVE SOCIETY LTD?

1 court case is listed for BLUE BIRD CO OPERATIVE SOCIETY LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of BLUE BIRD CO OPERATIVE SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ASHA ARUN SANE.