Asha Residency
by Sanjeet Buildcon · Dhanori, Pune
Possession date of Asha Residency: 29 April 2023, moved from 30 April 2022 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100021210. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (April 2023) has passed.
What do you want to know about Asha Residency?
How the possession date of Asha Residency has moved
30 April 2022
Completion date given when the project was registered
29 April 2023
Extended at the builder's request (MahaRERA application EXT52100012378)
Reason the builder gave MahaRERA: “Issues concerning covid and finance impacted the work speed.”
Source: Asha Residency’s extension records on MahaRERA (P52100021210), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Asha Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100021210
- Status
- Lapsed (registration period ended)
- Builder
- Sanjeet Buildcon
- Location
- Dhanori, Pune · 411032
- Project type
- Residential / Group Housing
- Registered on
- 14 Jun 2019
- Completion date at registration
- April 2022
- Latest completion date
- April 2023
- Delay so far
- 12 months
- Homes
- 10
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Asha Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Asha Residency | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Asha Residency every month.
Asha Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: Asha Residency (5 floors)
- Land: 466 sq m (about 0.1 acres) · sanctioned built-up 786 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Asha Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Asha Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Asha Residency
What is the possession date of Asha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Asha Residency in Dhanori, Pune is 29 April 2023 — 12 months later than 30 April 2022, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Asha Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Asha Residency's builder has filed on MahaRERA, the official one, is 29 April 2023, already 12 months later than the 30 April 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Asha Residency extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Asha Residency's builder applied to MahaRERA to extend the completion date once: to 29 April 2023, giving the reason "Issues concerning covid and finance impacted the work speed.".
What is the RERA number of Asha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Asha Residency in Dhanori, Pune is P52100021210.
Is Asha Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Asha Residency is registered as P52100021210 and its status is "Lapsed (registration period ended)".
What is the construction status of Asha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Asha Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Asha Residency is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Asha Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Asha Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Asha Residency is registered on MahaRERA as P52100021210, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Asha Residency's possession date changes?
The latest dates are on Asha Residency's MahaRERA page (P52100021210). GharKundli's Kundli Watch sends a free WhatsApp update on Asha Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Asha Residency have?
According to GharKundli's check of MahaRERA records (updated November 2026), Asha Residency has one building filed: Asha Residency with 5 floors.
How big is the land of Asha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Asha Residency stands on 466 sq m of land (about 0.1 acres), with 786 sq m of sanctioned built-up area.
Where can I read reviews of Asha Residency?
Google Maps has reviews of Asha Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Asha Residency?
Asha Residency by Sanjeet Buildcon is in Dhanori, Pune (pincode 411032), Maharashtra, and is registered on MahaRERA as P52100021210, per GharKundli's check of MahaRERA records.
How many homes are in Asha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Asha Residency has 10 homes in 1 tower registered on MahaRERA.
When was Asha Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Asha Residency was registered on MahaRERA on 14 June 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Asha Residency?
No court cases are listed for Asha Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Asha Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sanjeet Buildcon, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Asha Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Dhanori
- Kohinoor Viva Pixel- Phase II
- TRIAA VASANTAM CITY CENTER PHASE 1
- Galaxy Co-operative Housing Society Ltd
- ONE ARETHA PHASE 1
- AUSTIN
- Nivaan Sparsh II
- AAIJI CASTLE
- Belmont Celosia
Other projects by Sanjeet Buildcon
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.