What do you want to know about DNYANJYOT?
How the possession date of DNYANJYOT has moved
30 December 2022
Completion date given when the project was registered
31 December 2023
Extended at the builder's request (MahaRERA application EXT52100013394)
Reason the builder gave MahaRERA: “Lack of manpower and labour supply post covid time. Most of the North Indian labourers were away and hence we had a very bad time to re establish the work momentum.”
Source: DNYANJYOT’s extension records on MahaRERA (P52100027319), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DNYANJYOT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100027319
- Status
- Completed
- Builder
- DNYANJYOT LANDMARKS LLP
- Location
- Erandwane, Pune · 411004
- Project type
- Residential / Group Housing
- Registered on
- 1 Dec 2020
- Completion date at registration
- December 2022
- Latest completion date
- December 2023
- Delay so far
- 12 months
- Homes
- 10
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of DNYANJYOT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DNYANJYOT | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DNYANJYOT every month.
DNYANJYOT: buildings, flats and land, as filed on MahaRERA
- Buildings: DNYANJYOT (3 floors)
- Land: 296 sq m (about 0.1 acres) · sanctioned built-up 325 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of DNYANJYOT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DNYANJYOT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DNYANJYOT
What is the possession date of DNYANJYOT?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for DNYANJYOT in Erandwane, Pune is 31 December 2023 — 12 months later than 30 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for DNYANJYOT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DNYANJYOT's builder has filed on MahaRERA, the official one, is 31 December 2023, already 12 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of DNYANJYOT extended?
According to GharKundli's check of MahaRERA records (updated November 2026), DNYANJYOT's builder applied to MahaRERA to extend the completion date once: to 31 December 2023, giving the reason "Lack of manpower and labour supply post covid time. Most of the North Indian labourers were away and hence we had a very bad time to re establish the work momentum.".
What is the RERA number of DNYANJYOT?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of DNYANJYOT in Erandwane, Pune is P52100027319.
Is DNYANJYOT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DNYANJYOT is registered as P52100027319 and its status is "Completed".
What is the construction status of DNYANJYOT?
According to GharKundli's check of MahaRERA records (updated November 2026), DNYANJYOT's status on MahaRERA is "Completed". As filed by the builder, slab work on DNYANJYOT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does DNYANJYOT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is DNYANJYOT safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), DNYANJYOT is registered on MahaRERA as P52100027319, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DNYANJYOT's possession date changes?
The latest dates are on DNYANJYOT's MahaRERA page (P52100027319). GharKundli's Kundli Watch sends a free WhatsApp update on DNYANJYOT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DNYANJYOT have?
According to GharKundli's check of MahaRERA records (updated November 2026), DNYANJYOT has one building filed: DNYANJYOT with 3 floors.
How big is the land of DNYANJYOT?
According to GharKundli's check of MahaRERA records (updated November 2026), DNYANJYOT stands on 296 sq m of land (about 0.1 acres), with 325 sq m of sanctioned built-up area.
Where can I read reviews of DNYANJYOT?
Google Maps has reviews of DNYANJYOT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DNYANJYOT?
DNYANJYOT by DNYANJYOT LANDMARKS LLP is in Erandwane, Pune (pincode 411004), Maharashtra, and is registered on MahaRERA as P52100027319, per GharKundli's check of MahaRERA records.
How many homes are in DNYANJYOT?
According to GharKundli's check of MahaRERA records (updated November 2026), DNYANJYOT has 10 homes in 1 tower registered on MahaRERA.
When was DNYANJYOT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DNYANJYOT was registered on MahaRERA on 1 December 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on DNYANJYOT?
No court cases are listed for DNYANJYOT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of DNYANJYOT?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DNYANJYOT LANDMARKS LLP.
Check it yourself on MahaRERA
- How to check the possession date of DNYANJYOT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Erandwane
- BALWANT EMPIRE
- EKA Sattva
- Amardeep Jyoti CHSL
- Triveni Co-operative Housing Society Ltd PH 2
- JAGDEEP
- GANGADHAR
- Sarita Co-Operative Hsg Soc Ltd
- DHANASAMPADA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.