Skip to content
GharKundli

ORCHID VILLAS

by SHARP DEVELOPERS (Shantee) · Chinchoti, Palghar

Possession date of ORCHID VILLAS: 31 December 2030, moved from 30 May 2027 (43 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000024168, and currently active. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ORCHID VILLAS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ORCHID VILLAS has moved

  1. 30 May 2027

    Completion date given when the project was registered

  2. 31 December 2030

    Extended at the builder's request (MahaRERA application EA18082502388)

    Reason the builder gave MahaRERA:
    “The issuance of the Occupation Certificate is delayed pending clarification on a matter between the VVCMC and the Forest Department. We wish to highlight the following key point: Our Commencement Certificate (CC No. WCMC/TP/CC/VP-5540/23/20…” Read the full reason“The issuance of the Occupation Certificate is delayed pending clarification on a matter between the VVCMC and the Forest Department. We wish to highlight the following key point: Our Commencement Certificate (CC No. WCMC/TP/CC/VP-5540/23/2019-20) was issued on 22nd May 2019. This predates the relevant Eco-Sensitive Zone (ESZ) Gazette Notification (REGD. NO. D.L. 33004/99), which was published on 11th September 2019. As our CC was granted prior to the gazette notification, a Forest Department NOC should not be applicable. While the WCMC seeks this procedural clarification, we are unable to s…”

Source: ORCHID VILLAS’s extension records on MahaRERA (P99000024168), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ORCHID VILLAS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the December 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000024168
Status
Registered and active
Builder
SHARP DEVELOPERS
Location
Chinchoti, Palghar · 401208
Project type
Residential / Group Housing
Registered on
23 Jan 2020
Completion date at registration
May 2027
Latest completion date
December 2030
Delay so far
43 months
Homes
130
Sold or booked
65%
Towers
19
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of ORCHID VILLAS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CLUSTER - 10100%100%100%100%
CLUSTER - 11100%100%100%100%
CLUSTER - 12100%100%100%100%
CLUSTER - 13100%100%100%100%
CLUSTER -14100%100%100%100%
CLUSTER -15100%100%100%100%
CLUSTER -16100%100%100%100%
CLUSTER - 17100%100%100%100%
CLUSTER -18100%100%100%100%
CLUSTER -19100%100%100%100%
CLUSTER 1100%100%100%100%
CLUSTER 2100%100%100%100%
CLUSTER 3100%100%100%100%
CLUSTER 4100%100%100%100%
CLUSTER 5100%100%100%100%
CLUSTER 6100%100%100%100%
CLUSTER 7A-7B100%100%100%100%
CLUSTER 8100%100%100%100%
CLUSTER 9100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • CLUSTER 1: covers 3 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ORCHID VILLAS every month.

ORCHID VILLAS: buildings, flats and land, as filed on MahaRERA

  • Buildings: CLUSTER - 10 (16 floors, 13 units) · CLUSTER - 11 (23 floors, 20 units) · CLUSTER - 12 (7 floors, 4 units) · CLUSTER - 13 (7 floors, 4 units) · CLUSTER -14 (9 floors, 6 units) · CLUSTER -15 (5 floors, 2 units) · CLUSTER -16 (7 floors, 4 units) · CLUSTER - 17 (7 floors, 4 units) · and 11 more
  • Land: 4,154 sq m (about 1.0 acres) · sanctioned built-up 4,154 sq m · recreational space 1,530 sq m

The builder’s record and reviews

Shantee Realty AND Life Space (a group of 3 linked companies) has 10 projects on MahaRERA since 2020, this one included. Of the 4 GharKundli has checked: 4 still being built, none past the promised date yet. 3 complaints on MahaRERA across 2 projects.

Read Google reviews of ORCHID VILLAS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ORCHID VILLAS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ORCHID VILLAS

What is the possession date of ORCHID VILLAS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ORCHID VILLAS in Chinchoti, Palghar is 31 December 2030 — 43 months later than 30 May 2027, the date given at registration.

Is the builder's possession date different from the MahaRERA date for ORCHID VILLAS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ORCHID VILLAS's builder has filed on MahaRERA, the official one, is 31 December 2030, already 43 months later than the 30 May 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ORCHID VILLAS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ORCHID VILLAS's builder applied to MahaRERA to extend the completion date once: to 31 December 2030, giving the reason "The issuance of the Occupation Certificate is delayed pending clarification on a matter between the VVCMC and the Forest Department. We wish to highlight the following key point: Our Commencement Certificate (CC No. WCMC/TP/CC/VP-5540/23/2019-20) was issued on 22nd May 2019. This predates the relevant Eco-Sensitive Zone (ESZ) Gazette Notification (REGD. NO. D.L. 33004/99), which was published on 11th September 2019. As our CC was granted prior to the gazette notification, a Forest Department NOC should not be applicable. While the WCMC seeks this procedural clarification, we are unable to s…".

What is the RERA number of ORCHID VILLAS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ORCHID VILLAS in Chinchoti, Palghar is P99000024168.

Is ORCHID VILLAS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ORCHID VILLAS is registered as P99000024168 and its status is "Registered and active".

What is the construction status of ORCHID VILLAS?

According to GharKundli's check of MahaRERA records (updated October 2026), ORCHID VILLAS's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 19 towers. GharKundli's full report compares construction progress with the deadline.

Does ORCHID VILLAS have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ORCHID VILLAS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ORCHID VILLAS is registered on MahaRERA as P99000024168, its completion date has moved 43 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ORCHID VILLAS's possession date changes?

The latest dates are on ORCHID VILLAS's MahaRERA page (P99000024168). GharKundli's Kundli Watch sends a free WhatsApp update on ORCHID VILLAS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ORCHID VILLAS have?

According to GharKundli's check of MahaRERA records (updated October 2026), ORCHID VILLAS has 19 buildings filed: CLUSTER - 10 with 16 floors and 13 units; CLUSTER - 11 with 23 floors and 20 units; CLUSTER - 12 with 7 floors and 4 units; CLUSTER - 13 with 7 floors and 4 units; CLUSTER -14 with 9 floors and 6 units; CLUSTER -15 with 5 floors and 2 units; and 13 more.

How big is the land of ORCHID VILLAS?

According to GharKundli's check of MahaRERA records (updated October 2026), ORCHID VILLAS stands on 4,154 sq m of land (about 1.0 acres), with 4,154 sq m of sanctioned built-up area and 1,530 sq m of recreational open space.

What is the track record of ORCHID VILLAS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shantee Realty AND Life Space (a group of 3 linked companies) has 10 projects on MahaRERA since 2020, this one included. Of the 4 GharKundli has checked: 4 still being built, none past the promised date yet. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ORCHID VILLAS?

Google Maps has reviews of ORCHID VILLAS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ORCHID VILLAS?

ORCHID VILLAS by SHARP DEVELOPERS (Shantee) is in Chinchoti, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000024168, per GharKundli's check of MahaRERA records.

How many homes are in ORCHID VILLAS?

According to GharKundli's check of MahaRERA records (updated October 2026), ORCHID VILLAS has 130 homes in 19 towers registered on MahaRERA, and 65% of them are sold or booked.

When was ORCHID VILLAS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ORCHID VILLAS was registered on MahaRERA on 23 January 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on ORCHID VILLAS?

No court cases are listed for ORCHID VILLAS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of ORCHID VILLAS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHARP DEVELOPERS, the company Shantee files this project under.

All projects with possession due in 2030 in Palghar →

Other projects in Vasai

All 245 projects in Vasai East IE (401208) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.