Possession: Rahul Eastview II - Wing D and E is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100031662. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Rahul Eastview II - Wing D and E?
How the possession date of Rahul Eastview II - Wing D and E has moved
15 April 2023
Completion date given when the project was registered
31 March 2024
Extended at the builder's request (MahaRERA application EXT52100015203)
Reason the builder gave MahaRERA: “We have already submitted the file for to obtain completion certificate to PMC”
Source: Rahul Eastview II - Wing D and E’s extension records on MahaRERA (P52100031662), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Rahul Eastview II - Wing D and E
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- RAHUL EASTVIEW IP52100000845
- Rahul Eastview IIP52100017005
- Rahul Eastview II - Wing FP52100050478 · possession 31 Dec 2023
- MahaRERA registration
- P52100031662
- Status
- Completed
- Builder
- RAHUL CONSTRUCTIONS
- Location
- Hadapsar, Pune · 411028
- Project type
- Residential / Group Housing
- Registered on
- 3 Nov 2021
- Completion date at registration
- April 2023
- Latest completion date
- March 2024
- Delay so far
- 11 months
- Homes
- 158
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Rahul Eastview II - Wing D and E, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing D | 100% | 50% | 0% | 0% |
| Wing E | 100% | 50% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rahul Eastview II - Wing D and E every month.
Rahul Eastview II - Wing D and E: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing D (13 floors) · Wing E (13 floors)
- Land: 4,375 sq m (about 1.1 acres) · sanctioned built-up 11,192 sq m
The builder’s record and reviews
Rahul Constructions has 4 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 5 months). No complaints on MahaRERA.
Read Google reviews of Rahul Eastview II - Wing D and E →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Rahul Eastview II - Wing D and E: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Rahul Eastview II - Wing D and E
What is the possession date of Rahul Eastview II - Wing D and E?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Rahul Eastview II - Wing D and E in Hadapsar, Pune is 31 March 2024 — 11 months later than 15 April 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Rahul Eastview II - Wing D and E?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Rahul Eastview II - Wing D and E's builder has filed on MahaRERA, the official one, is 31 March 2024, already 11 months later than the 15 April 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Rahul Eastview II - Wing D and E extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Rahul Eastview II - Wing D and E's builder applied to MahaRERA to extend the completion date once: to 31 March 2024, giving the reason "We have already submitted the file for to obtain completion certificate to PMC".
What is the RERA number of Rahul Eastview II - Wing D and E?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Rahul Eastview II - Wing D and E in Hadapsar, Pune is P52100031662.
Is Rahul Eastview II - Wing D and E registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Rahul Eastview II - Wing D and E is registered as P52100031662 and its status is "Completed".
What is the construction status of Rahul Eastview II - Wing D and E?
According to GharKundli's check of MahaRERA records (updated November 2026), Rahul Eastview II - Wing D and E's status on MahaRERA is "Completed". As filed by the builder, slab work is 50% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Rahul Eastview II - Wing D and E have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Rahul Eastview II - Wing D and E safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Rahul Eastview II - Wing D and E is registered on MahaRERA as P52100031662, its MahaRERA status is "Completed", its completion date has moved 11 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Rahul Eastview II - Wing D and E have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: RAHUL EASTVIEW I (P52100000845); Rahul Eastview II (P52100017005); Rahul Eastview II - Wing F (P52100050478, possession 31 Dec 2023). Check that your agreement names the registration of your own wing.
How can I get updates if Rahul Eastview II - Wing D and E's possession date changes?
The latest dates are on Rahul Eastview II - Wing D and E's MahaRERA page (P52100031662). GharKundli's Kundli Watch sends a free WhatsApp update on Rahul Eastview II - Wing D and E every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Rahul Eastview II - Wing D and E have?
According to GharKundli's check of MahaRERA records (updated November 2026), Rahul Eastview II - Wing D and E has 2 buildings filed: Wing D with 13 floors; Wing E with 13 floors.
How big is the land of Rahul Eastview II - Wing D and E?
According to GharKundli's check of MahaRERA records (updated November 2026), Rahul Eastview II - Wing D and E stands on 4,375 sq m of land (about 1.1 acres), with 11,192 sq m of sanctioned built-up area.
What is the track record of Rahul Eastview II - Wing D and E's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Rahul Constructions has 4 projects on MahaRERA since 2021, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 5 months). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Rahul Eastview II - Wing D and E?
Google Maps has reviews of Rahul Eastview II - Wing D and E written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Rahul Eastview II - Wing D and E?
Rahul Eastview II - Wing D and E by RAHUL CONSTRUCTIONS is in Hadapsar, Pune (pincode 411028), Maharashtra, and is registered on MahaRERA as P52100031662, per GharKundli's check of MahaRERA records.
How many homes are in Rahul Eastview II - Wing D and E?
According to GharKundli's check of MahaRERA records (updated November 2026), Rahul Eastview II - Wing D and E has 158 homes in 2 towers registered on MahaRERA.
When was Rahul Eastview II - Wing D and E registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Rahul Eastview II - Wing D and E was registered on MahaRERA on 3 November 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Rahul Eastview II - Wing D and E?
No court cases are listed for Rahul Eastview II - Wing D and E on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Rahul Eastview II - Wing D and E?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAHUL CONSTRUCTIONS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Rahul Eastview II - Wing D and E
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 411028
- ANUTHAM PHASE II
- 47 East- B (Wing B)
- Astrana
- UNITY TOWERS
- MARVEL ISOLA J BUILDING
- MAHADEV PRANGAN
- Vertical Alcinia Phase III
- Kingston Aura Wing F and G
Other projects by RAHUL CONSTRUCTIONS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.