Shubh Shiv Zen World Phase III

by Shubh Housing · Behind Vista Luxuria, Pune 412307Registered on MahaRERA as “SHIV ZEN WORLD PHASE III”

What’s in the report? →

Possession date of Shubh Shiv Zen World Phase III (MahaRERA P52100031835): 1 August 2025, and it has already passed. It has 103 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100031835. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100031835, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (August 2025) has passed.

What do you want to know about Shubh Shiv Zen World Phase III?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Shubh Shiv Zen World Phase III

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100031835
Status
Lapsed (registration period ended)
Builder
Shubh Housing
Location
Behind Vista Luxuria, Pune · 412307
Project type
Residential / Group Housing
Registered on
22 Nov 2021
Completion date at registration
August 2025
Homes
103
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
9

Construction progress of Shubh Shiv Zen World Phase III, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
D BUILDING100%30%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shubh Shiv Zen World Phase III every 1–2 months.

Shubh Shiv Zen World Phase III: buildings, flats and land, as filed on MahaRERA

  • Buildings: D BUILDING (14 floors)
  • Land: 2,690 sq m (about 0.7 acres) · sanctioned built-up 7,319 sq m
  • Land, as filed: SURVEY NO 76 HISSA NO 1, 2, 3 / 1 PART
  • Map: Get directions

The builder’s record and reviews

Shubh Housing has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Shubh Shiv Zen World Phase III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shubh Shiv Zen World Phase III: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shubh Shiv Zen World Phase III

What is the possession date of Shubh Shiv Zen World Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shubh Shiv Zen World Phase III in Behind Vista Luxuria, Pune is 1 August 2025. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Shubh Shiv Zen World Phase III?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shubh Shiv Zen World Phase III's builder has filed on MahaRERA, the official one, is 1 August 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shubh Shiv Zen World Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shubh Shiv Zen World Phase III in Behind Vista Luxuria, Pune is P52100031835.

Is Shubh Shiv Zen World Phase III registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shiv Zen World Phase III is registered as P52100031835 and its status is "Lapsed (registration period ended)".

What is the current construction status of Shubh Shiv Zen World Phase III? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shiv Zen World Phase III's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on D BUILDING is 30% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Shubh Shiv Zen World Phase III have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Shubh Shiv Zen World Phase III safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shiv Zen World Phase III is registered on MahaRERA as P52100031835, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shubh Shiv Zen World Phase III?

Shubh Shiv Zen World Phase III isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shubh Shiv Zen World Phase III?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shubh Shiv Zen World Phase III: gharkundli.com/tools/property-cost-calculator

Has Shubh Shiv Zen World Phase III received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shiv Zen World Phase III isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 1 August 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Shubh Shiv Zen World Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shiv Zen World Phase III's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (1 August 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Shubh Shiv Zen World Phase III uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shubh Shiv Zen World Phase III was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Shubh Shiv Zen World Phase III have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: SHIV ZEN WORLD - PHASE I (P52100007579, possession 30 Dec 2021); Shiv Zen World Phase II (P52100022397, possession 30 Dec 2023); SHIV ZEN WORLD PHASE IV (PR1263032601891, possession 31 Dec 2032). Check that your agreement names the registration of your own wing.

How can I get updates if Shubh Shiv Zen World Phase III's possession date changes?

The latest dates are on Shubh Shiv Zen World Phase III's MahaRERA page (P52100031835). GharKundli's Kundli Watch sends a free WhatsApp update on Shubh Shiv Zen World Phase III every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shubh Shiv Zen World Phase III have?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shiv Zen World Phase III has one building filed: D BUILDING with 14 floors.

How big is the land of Shubh Shiv Zen World Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shiv Zen World Phase III stands on 2,690 sq m of land (about 0.7 acres), with 7,319 sq m of sanctioned built-up area.

What is the track record of Shubh Shiv Zen World Phase III's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Housing has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shubh Shiv Zen World Phase III?

Google Maps has reviews of Shubh Shiv Zen World Phase III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shubh Shiv Zen World Phase III?

Shubh Shiv Zen World Phase III by Shubh Housing is in Behind Vista Luxuria, Pune, pincode 412307, Maharashtra, and is registered on MahaRERA as P52100031835, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 76 HISSA NO 1, 2, 3 / 1 PART. GharKundli lists all 136 MahaRERA projects in Manjari Farm (412307).

How many flats are in Shubh Shiv Zen World Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shiv Zen World Phase III has 103 homes in 1 tower registered on MahaRERA.

When was Shubh Shiv Zen World Phase III registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shubh Shiv Zen World Phase III was registered on MahaRERA on 22 November 2021. GharKundli did not find a title report on the land on file there.

Does Shubh Shiv Zen World Phase III have any legal issues or court cases?

No court cases are listed for Shubh Shiv Zen World Phase III on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Shubh Shiv Zen World Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shubh Housing, which has 9 other projects registered on MahaRERA.