Skip to content
GharKundli

EVANA

by ROHAN KARAN INFRA · Mahavir Nagar, PuneAlso near Vadgaonsheri, Vadgaon Sheri, Mundhwa

Possession date of EVANA: 15 December 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100046988, and currently active. Its completion date is now December 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about EVANA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of EVANA has moved

  1. 15 August 2027

    Completion date given when the project was registered

  2. 15 December 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: EVANA’s extension records on MahaRERA (P52100046988), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on EVANA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100046988
Status
Registered and active
Builder
ROHAN KARAN INFRA
Location
Mahavir Nagar, Pune · 411014
Project type
Others
Registered on
26 Sep 2022
Completion date at registration
August 2027
Latest completion date
December 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
84
Sold or booked
93%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of EVANA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
EVANA A, B, C WING100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • EVANA A, B, C WING: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on EVANA every month.

EVANA: buildings, flats and land, as filed on MahaRERA

  • Buildings: EVANA A, B, C WING (9 floors, 87 units)
  • Car parking: 84 covered
  • Land: 2,108 sq m (about 0.5 acres) · sanctioned built-up 7,140 sq m
  • Boundaries filed include: 12 MTR GOVERNMENT ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of EVANA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

EVANA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about EVANA

What is the possession date of EVANA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for EVANA in Mahavir Nagar, Pune is 15 December 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for EVANA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date EVANA's builder has filed on MahaRERA, the official one, is 15 December 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of EVANA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of EVANA in Mahavir Nagar, Pune is P52100046988.

Is EVANA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), EVANA is registered as P52100046988 and its status is "Registered and active".

What is the construction status of EVANA?

According to GharKundli's check of MahaRERA records (updated November 2026), EVANA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on EVANA A, B, C WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does EVANA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is EVANA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), EVANA is registered on MahaRERA as P52100046988, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if EVANA's possession date changes?

The latest dates are on EVANA's MahaRERA page (P52100046988). GharKundli's Kundli Watch sends a free WhatsApp update on EVANA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does EVANA have?

According to GharKundli's check of MahaRERA records (updated November 2026), EVANA has one building filed: EVANA A, B, C WING with 9 floors and 87 units.

How much parking does EVANA have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 84 covered car parking spaces for EVANA.

How big is the land of EVANA?

According to GharKundli's check of MahaRERA records (updated November 2026), EVANA stands on 2,108 sq m of land (about 0.5 acres), with 7,140 sq m of sanctioned built-up area.

Where can I read reviews of EVANA?

Google Maps has reviews of EVANA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is EVANA?

EVANA by ROHAN KARAN INFRA is in Mahavir Nagar, Pune (pincode 411014), near Vadgaonsheri, Vadgaon Sheri, Mundhwa, Maharashtra, and is registered on MahaRERA as P52100046988, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 MTR GOVERNMENT ROAD.

How many homes are in EVANA?

According to GharKundli's check of MahaRERA records (updated November 2026), EVANA has 84 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.

When was EVANA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), EVANA was registered on MahaRERA on 26 September 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on EVANA?

No court cases are listed for EVANA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of EVANA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ROHAN KARAN INFRA.

All projects with possession due in 2027 in Pune →

Other projects in Haveli

All 211 projects in Kharadi (411014) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.