Possession date of Aranya: 31 July 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100052216, and currently active. Its completion date is now July 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Aranya?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Aranya has moved

  1. 31 March 2027

    Completion date given when the project was registered

  2. 31 July 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Aranya’s extension records on MahaRERA (P52100052216), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Aranya

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100052216
Status
Registered and active
Builder
Naiknavare Township LLP.
Location
Wadgaon, Pune · 412106
Project type
Residential / Group Housing
Registered on
31 Jul 2023
Completion date at registration
March 2027
Latest completion date
July 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
333
Sold or booked
100%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Aranya, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Aranaya A100%100%100%90%
Aranya B100%100%100%100%
Aranya C100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Aranaya A: covers 14 floors
  • Aranya B: covers 14 floors
  • Aranya C: covers 14 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aranya every month.

Aranya: buildings, flats and land, as filed on MahaRERA

  • Buildings: Aranaya A (14 floors, 106 units) · Aranya B (14 floors, 107 units) · Aranya C (14 floors, 155 units)
  • Land: 5,185 sq m (about 1.3 acres) · sanctioned built-up 20,710 sq m · recreational space 576 sq m

The builder’s record and reviews

Naiknavare Buildcon (a group of 4 linked companies) has 27 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 8 finished, 2 within the promised date and 6 needed more time (typically 40 months); 9 still being built, 2 past the promised date (typically 52 months late); 7 lapsed. 34 complaints on MahaRERA across 7 projects.

Read Google reviews of Aranya →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aranya: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Aranya

What is the possession date of Aranya?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aranya in Wadgaon, Pune is 31 July 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Aranya?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aranya's builder has filed on MahaRERA, the official one, is 31 July 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Aranya?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aranya in Wadgaon, Pune is P52100052216.

Is Aranya registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aranya is registered as P52100052216 and its status is "Registered and active".

What is the construction status of Aranya?

According to GharKundli's check of MahaRERA records (updated November 2026), Aranya's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Aranya have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Aranya safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Aranya is registered on MahaRERA as P52100052216, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Aranya's possession date changes?

The latest dates are on Aranya's MahaRERA page (P52100052216). GharKundli's Kundli Watch sends a free WhatsApp update on Aranya every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aranya have?

According to GharKundli's check of MahaRERA records (updated November 2026), Aranya has 3 buildings filed: Aranaya A with 14 floors and 106 units; Aranya B with 14 floors and 107 units; Aranya C with 14 floors and 155 units.

How big is the land of Aranya?

According to GharKundli's check of MahaRERA records (updated November 2026), Aranya stands on 5,185 sq m of land (about 1.3 acres), with 20,710 sq m of sanctioned built-up area and 576 sq m of recreational open space.

What is the track record of Aranya's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Naiknavare Buildcon (a group of 4 linked companies) has 27 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 8 finished, 2 within the promised date and 6 needed more time (typically 40 months); 9 still being built, 2 past the promised date (typically 52 months late); 7 lapsed. 34 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Aranya?

Google Maps has reviews of Aranya written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Aranya?

Aranya by Naiknavare Township LLP. is in Wadgaon, Pune (pincode 412106), Maharashtra, and is registered on MahaRERA as P52100052216, per GharKundli's check of MahaRERA records.

How many homes are in Aranya?

According to GharKundli's check of MahaRERA records (updated November 2026), Aranya has 333 homes in 3 towers registered on MahaRERA, and 100% of them are sold or booked.

When was Aranya registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aranya was registered on MahaRERA on 31 July 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Aranya?

No court cases are listed for Aranya on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Aranya?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Naiknavare Township LLP..

All projects with possession due in 2027 in Pune →

Other projects in Wadgaon

All 85 projects in Vadgaon (412106) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.