by SAI AASHIRWAD ENTERPRISES · Gokhiware, Palghar 401208Also near Vasai East IERegistered on MahaRERA as “SAI SAMRIDDHI”

What’s in the report? →

Possession date of Aashirwad Sai Samriddhi (MahaRERA P99000025166): 28 February 2026, and it has already passed. It has 182 homes, 89% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000025166. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P99000025166, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (February 2026) has passed.

What do you want to know about Aashirwad Sai Samriddhi?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Aashirwad Sai Samriddhi

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000025166
Status
Lapsed (registration period ended)
Builder
SAI AASHIRWAD ENTERPRISES
Location
Gokhiware, Palghar · 401208
Project type
Residential / Group Housing
Registered on
20 Mar 2020
Completion date at registration
February 2026
Latest completion date
February 2026
Homes
182
Sold or booked
89%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Aashirwad Sai Samriddhi, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI SAMRIDDHI100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • SAI SAMRIDDHI: covers 18 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aashirwad Sai Samriddhi every 1–2 months.

Aashirwad Sai Samriddhi: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAI SAMRIDDHI (18 floors, 189 units)
  • Land: 773 sq m (about 0.2 acres) · sanctioned built-up 7,797 sq m · recreational space 1,559 sq m
  • Boundaries filed include: 12 MTS INTERNAL ROAD
  • Land, as filed: SURVEY NO 76, 77, H. NO. 3,4,5
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Aashirwad Sai Samriddhi →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aashirwad Sai Samriddhi: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aashirwad Sai Samriddhi

What is the possession date of Aashirwad Sai Samriddhi?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Aashirwad Sai Samriddhi in Gokhiware, Palghar is 28 February 2026. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Aashirwad Sai Samriddhi?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aashirwad Sai Samriddhi's builder has filed on MahaRERA, the official one, is 28 February 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Aashirwad Sai Samriddhi?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Aashirwad Sai Samriddhi in Gokhiware, Palghar is P99000025166.

Is Aashirwad Sai Samriddhi registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashirwad Sai Samriddhi is registered as P99000025166 and its status is "Lapsed (registration period ended)".

What is the current construction status of Aashirwad Sai Samriddhi? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashirwad Sai Samriddhi's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAI SAMRIDDHI is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Aashirwad Sai Samriddhi have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Aashirwad Sai Samriddhi safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashirwad Sai Samriddhi is registered on MahaRERA as P99000025166, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aashirwad Sai Samriddhi?

Aashirwad Sai Samriddhi isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aashirwad Sai Samriddhi?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Aashirwad Sai Samriddhi: gharkundli.com/tools/property-cost-calculator

Has Aashirwad Sai Samriddhi received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Aashirwad Sai Samriddhi isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 28 February 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Aashirwad Sai Samriddhi?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashirwad Sai Samriddhi's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (28 February 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Aashirwad Sai Samriddhi uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Aashirwad Sai Samriddhi was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Aashirwad Sai Samriddhi's possession date changes?

The latest dates are on Aashirwad Sai Samriddhi's MahaRERA page (P99000025166). GharKundli's Kundli Watch sends a free WhatsApp update on Aashirwad Sai Samriddhi every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aashirwad Sai Samriddhi have?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashirwad Sai Samriddhi has one building filed: SAI SAMRIDDHI with 18 floors and 189 units.

How big is the land of Aashirwad Sai Samriddhi?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashirwad Sai Samriddhi stands on 773 sq m of land (about 0.2 acres), with 7,797 sq m of sanctioned built-up area and 1,559 sq m of recreational open space.

What are the reviews of Aashirwad Sai Samriddhi?

Google Maps has reviews of Aashirwad Sai Samriddhi written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aashirwad Sai Samriddhi?

Aashirwad Sai Samriddhi by SAI AASHIRWAD ENTERPRISES is in Gokhiware, Palghar, pincode 401208 (near Vasai East IE), Maharashtra, and is registered on MahaRERA as P99000025166, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 MTS INTERNAL ROAD. Its land is filed as SURVEY NO 76, 77, H. NO. 3,4,5. GharKundli lists all 378 MahaRERA projects in Vasai East IE (401208).

How many flats are in Aashirwad Sai Samriddhi, and how many are sold?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashirwad Sai Samriddhi has 182 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.

When was Aashirwad Sai Samriddhi registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Aashirwad Sai Samriddhi was registered on MahaRERA on 20 March 2020. GharKundli did not find a title report on the land on file there.

Does Aashirwad Sai Samriddhi have any legal issues or court cases?

No court cases are listed for Aashirwad Sai Samriddhi on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Aashirwad Sai Samriddhi?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAI AASHIRWAD ENTERPRISES.

All projects with possession due in 2026 in Palghar →

Other projects in Vasai East IE (401208)

All 378 projects in Vasai East IE (401208) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.