Skip to content
GharKundli

SWAPNALOK- BUILDING B

by GANDHI BAFNA CONSTRUCTION PRIVATE LIMITED · Khadki, Pune

Possession date of SWAPNALOK- BUILDING B: 31 March 2023, moved from 30 April 2019 (47 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100006177. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (March 2023) has passed.

What do you want to know about SWAPNALOK- BUILDING B?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SWAPNALOK- BUILDING B has moved

  1. 30 April 2019

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT52100000955)

    Reason the builder gave MahaRERA: “Delay in obtaining TDR and no units have been sold from project Wing B”
  3. 31 August 2021

    Extended at the builder's request (MahaRERA application EXT52100006293)

    Reason the builder gave MahaRERA:
    “We would like to inform you that we have NOT SOLD ANY FLAT/UNIT to third party/customers under the said project. The units shown on MahaRERA website are the ones that have been allotted to the landowner as per area sharing agreement. We are…” Read the full reason“We would like to inform you that we have NOT SOLD ANY FLAT/UNIT to third party/customers under the said project. The units shown on MahaRERA website are the ones that have been allotted to the landowner as per area sharing agreement. We are hereby using our power of attorney to instate NoC from them. power of attorney No.: 4897 dated 5'6.2008 The copy of power of attorney document is attached herewith and also uploaded in other/s section on MahaRERA website.”
  4. 31 March 2023

    Extended at the builder's request (MahaRERA application EXT52100011955)

    Reason the builder gave MahaRERA: “Delay due to delay in obtaining sanction”

Source: SWAPNALOK- BUILDING B’s extension records on MahaRERA (P52100006177), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SWAPNALOK- BUILDING B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100006177
Status
Lapsed (registration period ended)
Builder
GANDHI BAFNA CONSTRUCTION PRIVATE LIMITED
Location
Khadki, Pune · 411003
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
April 2019
Latest completion date
March 2023
Delay so far
47 months
Homes
26
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SWAPNALOK- BUILDING B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SWAPNALOK- BUILDING B100%100%95%85%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SWAPNALOK- BUILDING B every month.

SWAPNALOK- BUILDING B: buildings, flats and land, as filed on MahaRERA

  • Buildings: SWAPNALOK- BUILDING B (13 floors)
  • Land: 698 sq m (about 0.2 acres) · sanctioned built-up 1,390 sq m · recreational space 67 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SWAPNALOK- BUILDING B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SWAPNALOK- BUILDING B: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SWAPNALOK- BUILDING B

What is the possession date of SWAPNALOK- BUILDING B?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SWAPNALOK- BUILDING B in Khadki, Pune is 31 March 2023 — 47 months later than 30 April 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SWAPNALOK- BUILDING B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SWAPNALOK- BUILDING B's builder has filed on MahaRERA, the official one, is 31 March 2023, already 47 months later than the 30 April 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SWAPNALOK- BUILDING B extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SWAPNALOK- BUILDING B's builder applied to MahaRERA to extend the completion date 3 times: to 30 April 2020, giving the reason "Delay in obtaining TDR and no units have been sold from project Wing B"; to 31 August 2021, giving the reason "We would like to inform you that we have NOT SOLD ANY FLAT/UNIT to third party/customers under the said project. The units shown on MahaRERA website are the ones that have been allotted to the landowner as per area sharing agreement. We are hereby using our power of attorney to instate NoC from them. power of attorney No.: 4897 dated 5'6.2008 The copy of power of attorney document is attached herewith and also uploaded in other/s section on MahaRERA website."; to 31 March 2023, giving the reason "Delay due to delay in obtaining sanction".

What is the RERA number of SWAPNALOK- BUILDING B?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SWAPNALOK- BUILDING B in Khadki, Pune is P52100006177.

Is SWAPNALOK- BUILDING B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SWAPNALOK- BUILDING B is registered as P52100006177 and its status is "Lapsed (registration period ended)".

What is the construction status of SWAPNALOK- BUILDING B?

According to GharKundli's check of MahaRERA records (updated November 2026), SWAPNALOK- BUILDING B's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SWAPNALOK- BUILDING B is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does SWAPNALOK- BUILDING B have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SWAPNALOK- BUILDING B safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SWAPNALOK- BUILDING B is registered on MahaRERA as P52100006177, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 47 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does SWAPNALOK- BUILDING B have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SWAPNALOK- BUILDING C (P52100005515). Check that your agreement names the registration of your own wing.

How can I get updates if SWAPNALOK- BUILDING B's possession date changes?

The latest dates are on SWAPNALOK- BUILDING B's MahaRERA page (P52100006177). GharKundli's Kundli Watch sends a free WhatsApp update on SWAPNALOK- BUILDING B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SWAPNALOK- BUILDING B have?

According to GharKundli's check of MahaRERA records (updated November 2026), SWAPNALOK- BUILDING B has one building filed: SWAPNALOK- BUILDING B with 13 floors.

How big is the land of SWAPNALOK- BUILDING B?

According to GharKundli's check of MahaRERA records (updated November 2026), SWAPNALOK- BUILDING B stands on 698 sq m of land (about 0.2 acres), with 1,390 sq m of sanctioned built-up area and 67 sq m of recreational open space.

Where can I read reviews of SWAPNALOK- BUILDING B?

Google Maps has reviews of SWAPNALOK- BUILDING B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SWAPNALOK- BUILDING B?

SWAPNALOK- BUILDING B by GANDHI BAFNA CONSTRUCTION PRIVATE LIMITED is in Khadki, Pune (pincode 411003), Maharashtra, and is registered on MahaRERA as P52100006177, per GharKundli's check of MahaRERA records.

How many homes are in SWAPNALOK- BUILDING B?

According to GharKundli's check of MahaRERA records (updated November 2026), SWAPNALOK- BUILDING B has 26 homes in 1 tower registered on MahaRERA.

When was SWAPNALOK- BUILDING B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SWAPNALOK- BUILDING B was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SWAPNALOK- BUILDING B?

No court cases are listed for SWAPNALOK- BUILDING B on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SWAPNALOK- BUILDING B?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GANDHI BAFNA CONSTRUCTION PRIVATE LIMITED, which has 1 other project registered on MahaRERA.

Other projects in Haveli

All 7 projects in Khadki (411003) →

Other projects by GANDHI BAFNA CONSTRUCTION PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.