Skip to content
GharKundli

GLOBAL CITY

by DIVINE DEVELOPERS · Vadgaon Maval, PuneAlso near Panshet, P.C.N.T

Possession date of GLOBAL CITY: 30 March 2024, moved from 15 June 2021 (33 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100012401. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (March 2024) has passed.

What do you want to know about GLOBAL CITY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GLOBAL CITY has moved

  1. 15 June 2021

    Completion date given when the project was registered

  2. 15 December 2021

    Extended at the builder's request (MahaRERA application EXT52100009061)

    Reason the builder gave MahaRERA:
    “We Have Completed Half Project & Obtain occupancy Certificate From Competent Authority For Bldg 1 Wing A & B, Bldg No. 3, Bldg No. 4 Wing A, B, C & D, Those Bldg Are Completed & Have Occupancy Certificate Attached In Document Upload Folder…” Read the full reason“We Have Completed Half Project & Obtain occupancy Certificate From Competent Authority For Bldg 1 Wing A & B, Bldg No. 3, Bldg No. 4 Wing A, B, C & D, Those Bldg Are Completed & Have Occupancy Certificate Attached In Document Upload Folder in Completion Certificate Column Remaining Bldg 2 Wing A & B, Bldg No. 4 Wing E & F & Bldg No. 5, Are In Process So We Need Some Extension Time For Those Bldg's Completion.”
  3. 30 March 2024

    Extended at the builder's request (MahaRERA application EXT52100012179)

    Reason the builder gave MahaRERA:
    “The reason for the extension is we did not started the whole project work at the same time instead we started one building work at a time and completed the same on time. but we delayed to complete the whole project work soo we need the exte…” Read the full reason“The reason for the extension is we did not started the whole project work at the same time instead we started one building work at a time and completed the same on time. but we delayed to complete the whole project work soo we need the extension. we have completed 7 wings from the whole project and also have obtained the completion certificated for the same from competent authority. remaining 4 wings work has also been completed 50 to 70 percent. we have also taken NOC consent from the allottees to whom which we have sold the flats. soo we request you to please allow us the extension. we as…”

Source: GLOBAL CITY’s extension records on MahaRERA (P52100012401), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GLOBAL CITY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100012401
Status
Lapsed (registration period ended)
Builder
DIVINE DEVELOPERS
Location
Vadgaon Maval, Pune · 412106
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
June 2021
Latest completion date
March 2024
Delay so far
33 months
Homes
178
Towers
5
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of GLOBAL CITY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING 1 WING A AND B100%100%100%100%
BUILDING 2 WING A AND B100%100%100%100%
BUILDING 3100%100%100%100%
BUILDING 4 WING A, B, C, D, E AND F100%100%100%100%
BUILDING 5 ROW HOUSE A AND B0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GLOBAL CITY every month.

GLOBAL CITY: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING 1 WING A AND B (6 floors) · BUILDING 2 WING A AND B (6 floors) · BUILDING 3 (6 floors) · BUILDING 4 WING A, B, C, D, E AND F (6 floors) · BUILDING 5 ROW HOUSE A AND B (2 floors)
  • Land: 10,200 sq m (about 2.5 acres) · sanctioned built-up 7,802 sq m · recreational space 1,020 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GLOBAL CITY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GLOBAL CITY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GLOBAL CITY

What is the possession date of GLOBAL CITY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GLOBAL CITY in Vadgaon Maval, Pune is 30 March 2024 — 33 months later than 15 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for GLOBAL CITY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GLOBAL CITY's builder has filed on MahaRERA, the official one, is 30 March 2024, already 33 months later than the 15 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GLOBAL CITY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), GLOBAL CITY's builder applied to MahaRERA to extend the completion date 2 times: to 15 December 2021, giving the reason "We Have Completed Half Project & Obtain occupancy Certificate From Competent Authority For Bldg 1 Wing A & B, Bldg No. 3, Bldg No. 4 Wing A, B, C & D, Those Bldg Are Completed & Have Occupancy Certificate Attached In Document Upload Folder in Completion Certificate Column Remaining Bldg 2 Wing A & B, Bldg No. 4 Wing E & F & Bldg No. 5, Are In Process So We Need Some Extension Time For Those Bldg's Completion."; to 30 March 2024, giving the reason "The reason for the extension is we did not started the whole project work at the same time instead we started one building work at a time and completed the same on time. but we delayed to complete the whole project work soo we need the extension. we have completed 7 wings from the whole project and also have obtained the completion certificated for the same from competent authority. remaining 4 wings work has also been completed 50 to 70 percent. we have also taken NOC consent from the allottees to whom which we have sold the flats. soo we request you to please allow us the extension. we as…".

What is the RERA number of GLOBAL CITY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GLOBAL CITY in Vadgaon Maval, Pune is P52100012401.

Is GLOBAL CITY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GLOBAL CITY is registered as P52100012401 and its status is "Lapsed (registration period ended)".

What is the construction status of GLOBAL CITY?

According to GharKundli's check of MahaRERA records (updated November 2026), GLOBAL CITY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does GLOBAL CITY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is GLOBAL CITY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), GLOBAL CITY is registered on MahaRERA as P52100012401, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GLOBAL CITY's possession date changes?

The latest dates are on GLOBAL CITY's MahaRERA page (P52100012401). GharKundli's Kundli Watch sends a free WhatsApp update on GLOBAL CITY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GLOBAL CITY have?

According to GharKundli's check of MahaRERA records (updated November 2026), GLOBAL CITY has 5 buildings filed: BUILDING 1 WING A AND B with 6 floors; BUILDING 2 WING A AND B with 6 floors; BUILDING 3 with 6 floors; BUILDING 4 WING A, B, C, D, E AND F with 6 floors; BUILDING 5 ROW HOUSE A AND B with 2 floors.

How big is the land of GLOBAL CITY?

According to GharKundli's check of MahaRERA records (updated November 2026), GLOBAL CITY stands on 10,200 sq m of land (about 2.5 acres), with 7,802 sq m of sanctioned built-up area and 1,020 sq m of recreational open space.

Where can I read reviews of GLOBAL CITY?

Google Maps has reviews of GLOBAL CITY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GLOBAL CITY?

GLOBAL CITY by DIVINE DEVELOPERS is in Vadgaon Maval, Pune (pincode 412106), near Panshet, P.C.N.T, Maharashtra, and is registered on MahaRERA as P52100012401, per GharKundli's check of MahaRERA records.

How many homes are in GLOBAL CITY?

According to GharKundli's check of MahaRERA records (updated November 2026), GLOBAL CITY has 178 homes in 5 towers registered on MahaRERA.

When was GLOBAL CITY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GLOBAL CITY was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on GLOBAL CITY?

No court cases are listed for GLOBAL CITY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of GLOBAL CITY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DIVINE DEVELOPERS, which has 1 other project registered on MahaRERA.

Other projects in pincode 412106

All 83 projects in Vadgaon (412106) →

Other projects by DIVINE DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.