Skip to content
GharKundli

MANTRA MONARCH PHASE 3

by MANTRA KINGDOM PRIVATE LIMITED · Balewadi, PuneAlso near Wakad, Baner, N.I.A

Possession date of MANTRA MONARCH PHASE 3: 30 October 2026. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100024918. Status: Lapsed (registration period ended). Its completion date is now October 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about MANTRA MONARCH PHASE 3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MANTRA MONARCH PHASE 3 has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MANTRA MONARCH PHASE 3’s extension records on MahaRERA (P52100024918), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MANTRA MONARCH PHASE 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100024918
Status
Lapsed (registration period ended)
Builder
MANTRA KINGDOM PRIVATE LIMITED
Location
Balewadi, Pune · 411045
Project type
Residential / Group Housing
Registered on
12 Mar 2020
Completion date at registration
June 2026
Latest completion date
October 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
144
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of MANTRA MONARCH PHASE 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING A4100%100%100%100%
BUILDING A5100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MANTRA MONARCH PHASE 3 every month.

MANTRA MONARCH PHASE 3: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING A4 (23 floors) · BUILDING A5 (23 floors)
  • Land: 4,000 sq m (about 1.0 acres) · sanctioned built-up 10,694 sq m · recreational space 1,117 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Mantra Zirconia (a group of 15 linked companies) has 78 projects on MahaRERA since 2017, this one included. Of the 52 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 38 months); 35 still being built, none past the promised date yet; 9 lapsed. 31 complaints on MahaRERA across 14 projects.

Read Google reviews of MANTRA MONARCH PHASE 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MANTRA MONARCH PHASE 3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MANTRA MONARCH PHASE 3

What is the possession date of MANTRA MONARCH PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MANTRA MONARCH PHASE 3 in Balewadi, Pune is 30 October 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for MANTRA MONARCH PHASE 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MANTRA MONARCH PHASE 3's builder has filed on MahaRERA, the official one, is 30 October 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of MANTRA MONARCH PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MANTRA MONARCH PHASE 3 in Balewadi, Pune is P52100024918.

Is MANTRA MONARCH PHASE 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MANTRA MONARCH PHASE 3 is registered as P52100024918 and its status is "Lapsed (registration period ended)".

What is the construction status of MANTRA MONARCH PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), MANTRA MONARCH PHASE 3's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does MANTRA MONARCH PHASE 3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is MANTRA MONARCH PHASE 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), MANTRA MONARCH PHASE 3 is registered on MahaRERA as P52100024918, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does MANTRA MONARCH PHASE 3 have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: MANTRA MONARCH PHASE 1 (P52100023453); MANTRA MONARCH PHASE 2 (P52100024453). Check that your agreement names the registration of your own wing.

How can I get updates if MANTRA MONARCH PHASE 3's possession date changes?

The latest dates are on MANTRA MONARCH PHASE 3's MahaRERA page (P52100024918). GharKundli's Kundli Watch sends a free WhatsApp update on MANTRA MONARCH PHASE 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MANTRA MONARCH PHASE 3 have?

According to GharKundli's check of MahaRERA records (updated November 2026), MANTRA MONARCH PHASE 3 has 2 buildings filed: BUILDING A4 with 23 floors; BUILDING A5 with 23 floors.

How big is the land of MANTRA MONARCH PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), MANTRA MONARCH PHASE 3 stands on 4,000 sq m of land (about 1.0 acres), with 10,694 sq m of sanctioned built-up area and 1,117 sq m of recreational open space.

What is the track record of MANTRA MONARCH PHASE 3's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Mantra Zirconia (a group of 15 linked companies) has 78 projects on MahaRERA since 2017, this one included. Of the 52 GharKundli has checked: 8 finished, 7 within the promised date and 1 needed more time (typically 38 months); 35 still being built, none past the promised date yet; 9 lapsed. 31 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of MANTRA MONARCH PHASE 3?

Google Maps has reviews of MANTRA MONARCH PHASE 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MANTRA MONARCH PHASE 3?

MANTRA MONARCH PHASE 3 by MANTRA KINGDOM PRIVATE LIMITED is in Balewadi, Pune (pincode 411045), near Wakad, Baner, N.I.A, Maharashtra, and is registered on MahaRERA as P52100024918, per GharKundli's check of MahaRERA records.

How many homes are in MANTRA MONARCH PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), MANTRA MONARCH PHASE 3 has 144 homes in 2 towers registered on MahaRERA.

When was MANTRA MONARCH PHASE 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MANTRA MONARCH PHASE 3 was registered on MahaRERA on 12 March 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on MANTRA MONARCH PHASE 3?

No court cases are listed for MANTRA MONARCH PHASE 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of MANTRA MONARCH PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MANTRA KINGDOM PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.

Other projects in Balewadi

Other projects by MANTRA KINGDOM PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.