Skip to content
GharKundli

HIGHSTREET VASAI

by GANADHAR INFRA DEVELOPERS PVT. LTD · Railway Station Vasai Road East, Palghar

Possession date of HIGHSTREET VASAI: 29 June 2024, moved from 30 June 2023 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P99000026489. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2024) has passed.

What do you want to know about HIGHSTREET VASAI?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HIGHSTREET VASAI has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 29 June 2024

    Extended at the builder's request (MahaRERA application EXT99000017558)

    Reason the builder gave MahaRERA:
    “Sir, We, Gangadhar Infra Developers Pvt. Ltd are promoters of the project ‘Highstreet Vasai’ registered vide MahaRERA registration number ‘P99000026489’. The project initially was planned to be completed by 30/06/2023. But due to certain si…” Read the full reason“Sir, We, Gangadhar Infra Developers Pvt. Ltd are promoters of the project ‘Highstreet Vasai’ registered vide MahaRERA registration number ‘P99000026489’. The project initially was planned to be completed by 30/06/2023. But due to certain site conditions and covid 19, there was a huge shortage in labor and material provisions. Although we have tried to complete the project within the provided time, we need extension of one year to complete the project with required quality and amenities and receive occupancy certificate. We hereby request you to please grant us one year extension for MahaRER…”

Source: HIGHSTREET VASAI’s extension records on MahaRERA (P99000026489), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HIGHSTREET VASAI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000026489
Status
Lapsed (registration period ended)
Builder
GANADHAR INFRA DEVELOPERS PVT. LTD
Location
Railway Station Vasai Road East, Palghar · 401208
Project type
Commercial
Registered on
26 Sep 2020
Completion date at registration
June 2023
Latest completion date
June 2024
Delay so far
12 months
Homes
190
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of HIGHSTREET VASAI, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
HIGHSTREET VASAI PHASE 1100%100%85%40%
HIGHSTREET VASAI PHASE 2100%100%85%40%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HIGHSTREET VASAI every month.

HIGHSTREET VASAI: buildings, flats and land, as filed on MahaRERA

  • Buildings: HIGHSTREET VASAI PHASE 1 (6 floors) · HIGHSTREET VASAI PHASE 2 (6 floors)
  • Land: 1,983 sq m (about 0.5 acres) · sanctioned built-up 1,789 sq m · recreational space 1,983 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of HIGHSTREET VASAI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HIGHSTREET VASAI: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HIGHSTREET VASAI

What is the possession date of HIGHSTREET VASAI?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for HIGHSTREET VASAI in Railway Station Vasai Road East, Palghar is 29 June 2024 — 12 months later than 30 June 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for HIGHSTREET VASAI?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HIGHSTREET VASAI's builder has filed on MahaRERA, the official one, is 29 June 2024, already 12 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of HIGHSTREET VASAI extended?

According to GharKundli's check of MahaRERA records (updated November 2026), HIGHSTREET VASAI's builder applied to MahaRERA to extend the completion date once: to 29 June 2024, giving the reason "Sir, We, Gangadhar Infra Developers Pvt. Ltd are promoters of the project ‘Highstreet Vasai’ registered vide MahaRERA registration number ‘P99000026489’. The project initially was planned to be completed by 30/06/2023. But due to certain site conditions and covid 19, there was a huge shortage in labor and material provisions. Although we have tried to complete the project within the provided time, we need extension of one year to complete the project with required quality and amenities and receive occupancy certificate. We hereby request you to please grant us one year extension for MahaRER…".

What is the RERA number of HIGHSTREET VASAI?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of HIGHSTREET VASAI in Railway Station Vasai Road East, Palghar is P99000026489.

Is HIGHSTREET VASAI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HIGHSTREET VASAI is registered as P99000026489 and its status is "Lapsed (registration period ended)".

What is the construction status of HIGHSTREET VASAI?

According to GharKundli's check of MahaRERA records (updated November 2026), HIGHSTREET VASAI's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does HIGHSTREET VASAI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is HIGHSTREET VASAI safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), HIGHSTREET VASAI is registered on MahaRERA as P99000026489, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if HIGHSTREET VASAI's possession date changes?

The latest dates are on HIGHSTREET VASAI's MahaRERA page (P99000026489). GharKundli's Kundli Watch sends a free WhatsApp update on HIGHSTREET VASAI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HIGHSTREET VASAI have?

According to GharKundli's check of MahaRERA records (updated November 2026), HIGHSTREET VASAI has 2 buildings filed: HIGHSTREET VASAI PHASE 1 with 6 floors; HIGHSTREET VASAI PHASE 2 with 6 floors.

How big is the land of HIGHSTREET VASAI?

According to GharKundli's check of MahaRERA records (updated November 2026), HIGHSTREET VASAI stands on 1,983 sq m of land (about 0.5 acres), with 1,789 sq m of sanctioned built-up area and 1,983 sq m of recreational open space.

Where can I read reviews of HIGHSTREET VASAI?

Google Maps has reviews of HIGHSTREET VASAI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HIGHSTREET VASAI?

HIGHSTREET VASAI by GANADHAR INFRA DEVELOPERS PVT. LTD is in Railway Station Vasai Road East, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000026489, per GharKundli's check of MahaRERA records.

How many homes are in HIGHSTREET VASAI?

According to GharKundli's check of MahaRERA records (updated November 2026), HIGHSTREET VASAI has 190 homes in 2 towers registered on MahaRERA.

When was HIGHSTREET VASAI registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HIGHSTREET VASAI was registered on MahaRERA on 26 September 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on HIGHSTREET VASAI?

No court cases are listed for HIGHSTREET VASAI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of HIGHSTREET VASAI?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GANADHAR INFRA DEVELOPERS PVT. LTD.

Other projects in Vasai

All 257 projects in Vasai East IE (401208) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.