by RAMA SPACES · Chikhali, Pune 412114Also near Borhadewadi, Moshi, Dehu Alandi RoadRegistered on MahaRERA as “PARADISE ONE”

What’s in the report? →

Possession: Rama Paradise One (MahaRERA P52100018033) is marked completed on MahaRERA. It has 200 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100018033. Status: Completed.

Source: MahaRERA website — records for P52100018033, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Rama Paradise One?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Rama Paradise One has moved

  1. 30 September 2021

    Completion date given when the project was registered

  2. 30 September 2022

    Extended at the builder's request (MahaRERA application EXT52100010531)

    Reason the builder gave MahaRERA:
    “We would like to explain that the recent wave of covid-19 has disrupted the development of our under construction project. Also, supply chains for obtaining construction material has been distinctively challenging to us. Furthermore, to add…” Read the full reason“We would like to explain that the recent wave of covid-19 has disrupted the development of our under construction project. Also, supply chains for obtaining construction material has been distinctively challenging to us. Furthermore, to add on to these crucial circumstances, the exodus of labor to their natives has adversely impacted the pace of construction & scheduled work plan.”
  3. 30 March 2023

    Revised completion date on MahaRERA

Source: Rama Paradise One’s extension records on MahaRERA (P52100018033), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Rama Paradise One

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100018033
Status
Completed
Builder
RAMA SPACES
Location
Chikhali, Pune · 412114
Project type
Residential / Group Housing
Registered on
10 Oct 2018
Completion date at registration
September 2021
Latest completion date
March 2023
Delay so far
18 months
Homes
200
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Rama Paradise One, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING - ABC100%100%100%100%
MHADA100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rama Paradise One every 1–2 months.

Rama Paradise One: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Rama Synergy Spaces (a group of 5 linked companies) has 28 projects on MahaRERA since 2017, this one included. Of the 28 GharKundli has checked: 17 finished, 6 within the promised date and 11 needed more time (typically 8 months); 10 still being built, 7 past the promised date (typically 22 months late); 1 lapsed. 60 complaints on MahaRERA across 13 projects.

Read Google reviews of Rama Paradise One →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Rama Paradise One: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Rama Paradise One

What is the possession date of Rama Paradise One?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Rama Paradise One in Chikhali, Pune is 30 March 2023 — 18 months later than 30 September 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Rama Paradise One?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Rama Paradise One's builder has filed on MahaRERA, the official one, is 30 March 2023, already 18 months later than the 30 September 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Rama Paradise One extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Paradise One's builder applied to MahaRERA to extend the completion date once: to 30 September 2022, giving the reason "We would like to explain that the recent wave of covid-19 has disrupted the development of our under construction project. Also, supply chains for obtaining construction material has been distinctively challenging to us. Furthermore, to add on to these crucial circumstances, the exodus of labor to their natives has adversely impacted the pace of construction & scheduled work plan.".

What is the RERA number of Rama Paradise One?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Rama Paradise One in Chikhali, Pune is P52100018033.

Is Rama Paradise One registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Paradise One is registered as P52100018033 and its status is "Completed".

What is the current construction status of Rama Paradise One? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Paradise One's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Rama Paradise One have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Rama Paradise One safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Paradise One is registered on MahaRERA as P52100018033, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Rama Paradise One?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Paradise One is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Rama Paradise One?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Rama Paradise One: gharkundli.com/tools/property-cost-calculator

Has Rama Paradise One received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Paradise One is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Rama Paradise One completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Paradise One is marked completed on MahaRERA, and the completion date filed there is 30 March 2023. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Rama Paradise One uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Rama Paradise One was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Rama Paradise One's possession date changes?

The latest dates are on Rama Paradise One's MahaRERA page (P52100018033). GharKundli's Kundli Watch sends a free WhatsApp update on Rama Paradise One every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Rama Paradise One have?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Paradise One has 2 buildings filed: BUILDING - ABC with 14 floors; MHADA with 15 floors.

How big is the land of Rama Paradise One?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Paradise One stands on 4,076 sq m of land (about 1.0 acres), with 11,021 sq m of sanctioned built-up area and 408 sq m of recreational open space.

What is the track record of Rama Paradise One's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Synergy Spaces (a group of 5 linked companies) has 28 projects on MahaRERA since 2017, this one included. Of the 28 GharKundli has checked: 17 finished, 6 within the promised date and 11 needed more time (typically 8 months); 10 still being built, 7 past the promised date (typically 22 months late); 1 lapsed. 60 complaints on MahaRERA across 13 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Rama Paradise One?

Google Maps has reviews of Rama Paradise One written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Rama Paradise One?

Rama Paradise One by RAMA SPACES is in Chikhali, Pune, pincode 412114 (near Borhadewadi, Moshi, Dehu Alandi Road), Maharashtra, and is registered on MahaRERA as P52100018033, per GharKundli's check of MahaRERA records. Its land is filed as GAT NO 96 AND 97 PLOT A.

How many flats are in Rama Paradise One?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Paradise One has 200 homes in 2 towers registered on MahaRERA.

When was Rama Paradise One registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Rama Paradise One was registered on MahaRERA on 10 October 2018. GharKundli did not find a title report on the land on file there.

Does Rama Paradise One have any legal issues or court cases?

No court cases are listed for Rama Paradise One on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Rama Paradise One?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAMA SPACES, which has 5 other projects registered on MahaRERA.

Other projects in Pincode not filed (412114)

Other projects by RAMA SPACES

All Pune projects with no pincode on MahaRERA →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.