SANGAMESHWAR PHASE A

by SABLE SANJIVANI SASWAD INFRASTRUCTURE LLP · Saswad, Pune

Possession: SANGAMESHWAR PHASE A is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100022448. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SANGAMESHWAR PHASE A?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SANGAMESHWAR PHASE A has moved

  1. 30 September 2022

    Completion date given when the project was registered

  2. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT52100008954)

    Reason the builder gave MahaRERA: “DUE TO CURRENT PANDEMIC SITUATION AND MARKET VOLATILITY IN CASE OF AFFORDABLE HOUSING, DEVELOPER IS HEREBY APPLYING FOR EXTENSION.”
  3. 15 April 2023

    Extended at the builder's request (MahaRERA application EXT52100012984)

    Reason the builder gave MahaRERA:
    “DUE TO MARKET VOLATILITY IN CASE OF AFFORDABLE HOUSING AND CURRENTLY LESS THAN 35% INVENTORY IS BOOKED AND REGISTERED IN THE NAME OF THE CUSTOMER FOR THE PROJECT SANGAMESHWAR PHASE A. DEVELOPER IS UNABLE TO KEEP THE SPEED OF CONSTRUCTION AT…” Read the full reason“DUE TO MARKET VOLATILITY IN CASE OF AFFORDABLE HOUSING AND CURRENTLY LESS THAN 35% INVENTORY IS BOOKED AND REGISTERED IN THE NAME OF THE CUSTOMER FOR THE PROJECT SANGAMESHWAR PHASE A. DEVELOPER IS UNABLE TO KEEP THE SPEED OF CONSTRUCTION AT PAR, DESPITE OF THIS FACT 100% OF RCC WORK, 90% OF BRICKWORK & PLASTER WORK ALMOST COMPLETED AND LIFT CONTRACT IS ALREADY GIVEN. INTERNAL ELECTRIC WORK ALMOSDT 70% DONE. INTERNAL PLUMBING WORK ALMOST 70% DONE. EXTERNAL DEVELOPMENT WORK ALMOST 50% DONE. 45% OF OTHER FINISHING WORK IS COMPLETED. THEREFORE DEVELOPER IS HEREBY APPLYING FOR EXTENSION FOR FURT…”
  4. 15 June 2023

    Extended at the builder's request (MahaRERA application EXT52100015273)

    Reason the builder gave MahaRERA:
    “DUE TO MARKET VOLATILITY IN CASE OF AFFORDABLE HOUSING AND CURRENTLY LESS THAN 35% INVENTORY IS BOOKED AND REGISTERED IN THE NAME OF THE CUSTOMER FOR THE PROJECT SANGAMESHWAR PHASE A. DEVELOPER IS UNABLE TO KEEP THE SPEED OF CONSTRUCTION AT…” Read the full reason“DUE TO MARKET VOLATILITY IN CASE OF AFFORDABLE HOUSING AND CURRENTLY LESS THAN 35% INVENTORY IS BOOKED AND REGISTERED IN THE NAME OF THE CUSTOMER FOR THE PROJECT SANGAMESHWAR PHASE A. DEVELOPER IS UNABLE TO KEEP THE SPEED OF CONSTRUCTION AT PAR. DESPITE OF THIS FACT: A) 100% OF RCC WORK, 100% OF BRICKWORK & PLASTER WORK ALMOST COMPLETED, AND B) LIFT WORK & FIRE FIGHTING SYSTEM ALMOST COMPLETED ONLY LIFT NOC AND FIRE NOC FROM COMPETENT AUTHORITY ARE PENDING. C) INTERNAL ELECTRIC WORK ALMOSDT 95% DONE AND ELECTRIC TRANSFORMER IS ERRECTED AT SITE ONLY CHARGING IS PENDING. D) INTERNAL PLUMBING…”
  5. 15 September 2023

    Extended at the builder's request (MahaRERA application EXT52100017581)

    Reason the builder gave MahaRERA:
    “2. Explanatory note: DUE TO MARKET VOLATILITY IN CASE OF AFFORDABLE HOUSING AND CURRENTLY LESS THAN 35% INVENTORY IS BOOKED AND REGISTERED IN THE NAME OF THE CUSTOMER FOR THE PROJECT SANGAMESHWAR PHASE A. DEVELOPER IS UNABLE TO KEEP THE SPE…” Read the full reason“2. Explanatory note: DUE TO MARKET VOLATILITY IN CASE OF AFFORDABLE HOUSING AND CURRENTLY LESS THAN 35% INVENTORY IS BOOKED AND REGISTERED IN THE NAME OF THE CUSTOMER FOR THE PROJECT SANGAMESHWAR PHASE A. DEVELOPER IS UNABLE TO KEEP THE SPEED OF CONSTRUCTION AT PAR. DESPITE OF THIS FACT: A) 100% OF RCC WORK, 100% OF BRICKWORK & PLASTER WORK ALMOST COMPLETED, AND B) LIFT WORK & FIRE FIGHTING SYSTEM ALMOST COMPLETED ONLY LIFT NOC AND FIRE NOC FROM COMPETENT AUTHORITY ARE PENDING. C) INTERNAL ELECTRIC WORK 100% DONE AND ELECTRIC TRANSFORMER IS ERRECTED AT SITE ONLY CHARGING IS PENDING. D) INTE…”

Source: SANGAMESHWAR PHASE A’s extension records on MahaRERA (P52100022448), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SANGAMESHWAR PHASE A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100022448
Status
Completed
Builder
SABLE SANJIVANI SASWAD INFRASTRUCTURE LLP
Location
Saswad, Pune · 412301
Project type
Others
Registered on
24 Sep 2019
Completion date at registration
September 2022
Latest completion date
September 2023
Delay so far
12 months
Homes
106
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SANGAMESHWAR PHASE A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SANGAMESHWAR PHASE A100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SANGAMESHWAR PHASE A every month.

SANGAMESHWAR PHASE A: buildings, flats and land, as filed on MahaRERA

  • Buildings: SANGAMESHWAR PHASE A (10 floors)
  • Land: 1,933 sq m (about 0.5 acres) · sanctioned built-up 6,857 sq m · recreational space 364 sq m

The builder’s record and reviews

Sable Sanjivani Saswad Infrastructure has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 3 finished, all within the promised date. No complaints on MahaRERA.

Read Google reviews of SANGAMESHWAR PHASE A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SANGAMESHWAR PHASE A: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SANGAMESHWAR PHASE A

What is the possession date of SANGAMESHWAR PHASE A?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SANGAMESHWAR PHASE A in Saswad, Pune is 15 September 2023 — 12 months later than 30 September 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SANGAMESHWAR PHASE A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SANGAMESHWAR PHASE A's builder has filed on MahaRERA, the official one, is 15 September 2023, already 12 months later than the 30 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SANGAMESHWAR PHASE A extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SANGAMESHWAR PHASE A's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2022, giving the reason "DUE TO CURRENT PANDEMIC SITUATION AND MARKET VOLATILITY IN CASE OF AFFORDABLE HOUSING, DEVELOPER IS HEREBY APPLYING FOR EXTENSION."; to 15 April 2023, giving the reason "DUE TO MARKET VOLATILITY IN CASE OF AFFORDABLE HOUSING AND CURRENTLY LESS THAN 35% INVENTORY IS BOOKED AND REGISTERED IN THE NAME OF THE CUSTOMER FOR THE PROJECT SANGAMESHWAR PHASE A. DEVELOPER IS UNABLE TO KEEP THE SPEED OF CONSTRUCTION AT PAR, DESPITE OF THIS FACT 100% OF RCC WORK, 90% OF BRICKWORK & PLASTER WORK ALMOST COMPLETED AND LIFT CONTRACT IS ALREADY GIVEN. INTERNAL ELECTRIC WORK ALMOSDT 70% DONE. INTERNAL PLUMBING WORK ALMOST 70% DONE. EXTERNAL DEVELOPMENT WORK ALMOST 50% DONE. 45% OF OTHER FINISHING WORK IS COMPLETED. THEREFORE DEVELOPER IS HEREBY APPLYING FOR EXTENSION FOR FURT…"; to 15 June 2023, giving the reason "DUE TO MARKET VOLATILITY IN CASE OF AFFORDABLE HOUSING AND CURRENTLY LESS THAN 35% INVENTORY IS BOOKED AND REGISTERED IN THE NAME OF THE CUSTOMER FOR THE PROJECT SANGAMESHWAR PHASE A. DEVELOPER IS UNABLE TO KEEP THE SPEED OF CONSTRUCTION AT PAR. DESPITE OF THIS FACT: A) 100% OF RCC WORK, 100% OF BRICKWORK & PLASTER WORK ALMOST COMPLETED, AND B) LIFT WORK & FIRE FIGHTING SYSTEM ALMOST COMPLETED ONLY LIFT NOC AND FIRE NOC FROM COMPETENT AUTHORITY ARE PENDING. C) INTERNAL ELECTRIC WORK ALMOSDT 95% DONE AND ELECTRIC TRANSFORMER IS ERRECTED AT SITE ONLY CHARGING IS PENDING. D) INTERNAL PLUMBING…"; to 15 September 2023, giving the reason "2. Explanatory note: DUE TO MARKET VOLATILITY IN CASE OF AFFORDABLE HOUSING AND CURRENTLY LESS THAN 35% INVENTORY IS BOOKED AND REGISTERED IN THE NAME OF THE CUSTOMER FOR THE PROJECT SANGAMESHWAR PHASE A. DEVELOPER IS UNABLE TO KEEP THE SPEED OF CONSTRUCTION AT PAR. DESPITE OF THIS FACT: A) 100% OF RCC WORK, 100% OF BRICKWORK & PLASTER WORK ALMOST COMPLETED, AND B) LIFT WORK & FIRE FIGHTING SYSTEM ALMOST COMPLETED ONLY LIFT NOC AND FIRE NOC FROM COMPETENT AUTHORITY ARE PENDING. C) INTERNAL ELECTRIC WORK 100% DONE AND ELECTRIC TRANSFORMER IS ERRECTED AT SITE ONLY CHARGING IS PENDING. D) INTE…".

What is the RERA number of SANGAMESHWAR PHASE A?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SANGAMESHWAR PHASE A in Saswad, Pune is P52100022448.

Is SANGAMESHWAR PHASE A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SANGAMESHWAR PHASE A is registered as P52100022448 and its status is "Completed".

What is the construction status of SANGAMESHWAR PHASE A?

According to GharKundli's check of MahaRERA records (updated November 2026), SANGAMESHWAR PHASE A's status on MahaRERA is "Completed". As filed by the builder, slab work on SANGAMESHWAR PHASE A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SANGAMESHWAR PHASE A have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SANGAMESHWAR PHASE A safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SANGAMESHWAR PHASE A is registered on MahaRERA as P52100022448, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SANGAMESHWAR PHASE A's possession date changes?

The latest dates are on SANGAMESHWAR PHASE A's MahaRERA page (P52100022448). GharKundli's Kundli Watch sends a free WhatsApp update on SANGAMESHWAR PHASE A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SANGAMESHWAR PHASE A have?

According to GharKundli's check of MahaRERA records (updated November 2026), SANGAMESHWAR PHASE A has one building filed: SANGAMESHWAR PHASE A with 10 floors.

How big is the land of SANGAMESHWAR PHASE A?

According to GharKundli's check of MahaRERA records (updated November 2026), SANGAMESHWAR PHASE A stands on 1,933 sq m of land (about 0.5 acres), with 6,857 sq m of sanctioned built-up area and 364 sq m of recreational open space.

What is the track record of SANGAMESHWAR PHASE A's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Sable Sanjivani Saswad Infrastructure has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 3 finished, all within the promised date. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SANGAMESHWAR PHASE A?

Google Maps has reviews of SANGAMESHWAR PHASE A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SANGAMESHWAR PHASE A?

SANGAMESHWAR PHASE A by SABLE SANJIVANI SASWAD INFRASTRUCTURE LLP is in Saswad, Pune (pincode 412301), Maharashtra, and is registered on MahaRERA as P52100022448, per GharKundli's check of MahaRERA records.

How many homes are in SANGAMESHWAR PHASE A?

According to GharKundli's check of MahaRERA records (updated November 2026), SANGAMESHWAR PHASE A has 106 homes in 1 tower registered on MahaRERA.

When was SANGAMESHWAR PHASE A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SANGAMESHWAR PHASE A was registered on MahaRERA on 24 September 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on SANGAMESHWAR PHASE A?

No court cases are listed for SANGAMESHWAR PHASE A on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SANGAMESHWAR PHASE A?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SABLE SANJIVANI SASWAD INFRASTRUCTURE LLP, which has 2 other projects registered on MahaRERA.

Other projects in pincode 412301

All 56 projects in Saswad (412301) →

Other projects by SABLE SANJIVANI SASWAD INFRASTRUCTURE LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.