by JSB Shelters LLP · Vasai, Palghar

Possession: Nakshatra Aarambh is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000027563. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Nakshatra Aarambh?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Nakshatra Aarambh has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 15 September 2026

    Extended at the builder's request (MahaRERA application EA19052621021)

    Reason the builder gave MahaRERA:
    “The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 09/04/2025 and we have also initiated the process for…” Read the full reason“The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 09/04/2025 and we have also initiated the process for the possession as well. In view of this as the said project obtained full OC uploading consents from allottees will not be required. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring timely execution, and addressing any issues that may arise. This proactive approach aims to ensure…”

Source: Nakshatra Aarambh’s extension records on MahaRERA (P99000027563), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Nakshatra Aarambh

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the September 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000027563
Status
Completed
Builder
JSB Shelters LLP
Location
Vasai, Palghar · 401208
Project type
Residential / Group Housing
Registered on
16 Dec 2020
Completion date at registration
June 2025
Latest completion date
September 2026
Delay so far
15 months
Homes
264
Sold or booked
96%
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of Nakshatra Aarambh, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
8A100%100%100%100%
8B100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • 8A: covers 24 (Ground/Stilt + 23 Upper Floors)
  • 8B: covers 24 (Ground/Stilt + 23 Upper Floors)

Latest CC order on MahaRERA: dated 10/10/2024.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nakshatra Aarambh every month.

Nakshatra Aarambh: buildings, flats and land, as filed on MahaRERA

  • Buildings: 8A (24 floors, 132 units) · 8B (24 floors, 132 units)
  • Car parking: 18 covered
  • Land: 7,000 sq m (about 1.7 acres) · sanctioned built-up 9,764 sq m
  • Boundaries filed include: Vasai Diva Railway Line, Juchandra Station

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Nakshatra Aarambh →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Nakshatra Aarambh: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Nakshatra Aarambh

What is the possession date of Nakshatra Aarambh?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nakshatra Aarambh in Vasai, Palghar is 15 September 2026 — 15 months later than 30 June 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Nakshatra Aarambh?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Nakshatra Aarambh's builder has filed on MahaRERA, the official one, is 15 September 2026, already 15 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Nakshatra Aarambh extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Nakshatra Aarambh's builder applied to MahaRERA to extend the completion date once: to 15 September 2026, giving the reason "The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 09/04/2025 and we have also initiated the process for the possession as well. In view of this as the said project obtained full OC uploading consents from allottees will not be required. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring timely execution, and addressing any issues that may arise. This proactive approach aims to ensure…".

What is the RERA number of Nakshatra Aarambh?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nakshatra Aarambh in Vasai, Palghar is P99000027563.

Is Nakshatra Aarambh registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nakshatra Aarambh is registered as P99000027563 and its status is "Completed".

What is the construction status of Nakshatra Aarambh?

According to GharKundli's check of MahaRERA records (updated October 2026), Nakshatra Aarambh's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Nakshatra Aarambh have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Nakshatra Aarambh safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Nakshatra Aarambh is registered on MahaRERA as P99000027563, its MahaRERA status is "Completed", its completion date has moved 15 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Nakshatra Aarambh's possession date changes?

The latest dates are on Nakshatra Aarambh's MahaRERA page (P99000027563). GharKundli's Kundli Watch sends a free WhatsApp update on Nakshatra Aarambh every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Nakshatra Aarambh have?

According to GharKundli's check of MahaRERA records (updated October 2026), Nakshatra Aarambh has 2 buildings filed: 8A with 24 floors and 132 units; 8B with 24 floors and 132 units.

How much parking does Nakshatra Aarambh have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 18 covered car parking spaces for Nakshatra Aarambh.

How big is the land of Nakshatra Aarambh?

According to GharKundli's check of MahaRERA records (updated October 2026), Nakshatra Aarambh stands on 7,000 sq m of land (about 1.7 acres), with 9,764 sq m of sanctioned built-up area.

Where can I read reviews of Nakshatra Aarambh?

Google Maps has reviews of Nakshatra Aarambh written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Nakshatra Aarambh?

Nakshatra Aarambh by JSB Shelters LLP is in Vasai, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000027563, per GharKundli's check of MahaRERA records. Its boundaries filed there include Vasai Diva Railway Line, Juchandra Station.

How many homes are in Nakshatra Aarambh?

According to GharKundli's check of MahaRERA records (updated October 2026), Nakshatra Aarambh has 264 homes in 2 towers registered on MahaRERA, and 96% of them are sold or booked.

When was Nakshatra Aarambh registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nakshatra Aarambh was registered on MahaRERA on 16 December 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Nakshatra Aarambh?

No court cases are listed for Nakshatra Aarambh on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Nakshatra Aarambh?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JSB Shelters LLP.

Other projects in pincode 401208

All 257 projects in Vasai East IE (401208) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.