KRISHNA APARTMENT
by ASHOK THAKORBHAI PATEL · PalgharAlso near Mahim, Tembhode
Possession: KRISHNA APARTMENT is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000030577. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about KRISHNA APARTMENT?
How the possession date of KRISHNA APARTMENT has moved
31 December 2021
Completion date given when the project was registered
31 December 2022
Extended at the builder's request (MahaRERA application EXT99000011286)
Reason the builder gave MahaRERA:
“Non finance from Banking channel due to Builder under negative list as per banking norms and no outsider buyer other than buyer of flat no 202 till date purchased any of the flats. Builder under cash crunch due amid emerging Covid-19 which…” Read the full reason
“Non finance from Banking channel due to Builder under negative list as per banking norms and no outsider buyer other than buyer of flat no 202 till date purchased any of the flats. Builder under cash crunch due amid emerging Covid-19 which affected builders at large scale”
Source: KRISHNA APARTMENT’s extension records on MahaRERA (P99000030577), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KRISHNA APARTMENT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000030577
- Status
- Completed
- Builder
- ASHOK THAKORBHAI PATEL
- Location
- Palghar · 401404
- Project type
- Residential / Group Housing
- Registered on
- 1 Sep 2021
- Completion date at registration
- December 2021
- Latest completion date
- December 2022
- Delay so far
- 12 months
- Homes
- 16
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of KRISHNA APARTMENT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KRISHNA APARTMENT | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KRISHNA APARTMENT every month.
KRISHNA APARTMENT: buildings, flats and land, as filed on MahaRERA
- Buildings: KRISHNA APARTMENT (5 floors)
- Land: 604 sq m (about 0.1 acres) · sanctioned built-up 724 sq m
- Boundaries filed include: 6 METER LAYOUT ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of KRISHNA APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KRISHNA APARTMENT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KRISHNA APARTMENT
What is the possession date of KRISHNA APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KRISHNA APARTMENT in Palghar is 31 December 2022 — 12 months later than 31 December 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for KRISHNA APARTMENT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KRISHNA APARTMENT's builder has filed on MahaRERA, the official one, is 31 December 2022, already 12 months later than the 31 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KRISHNA APARTMENT extended?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA APARTMENT's builder applied to MahaRERA to extend the completion date once: to 31 December 2022, giving the reason "Non finance from Banking channel due to Builder under negative list as per banking norms and no outsider buyer other than buyer of flat no 202 till date purchased any of the flats. Builder under cash crunch due amid emerging Covid-19 which affected builders at large scale".
What is the RERA number of KRISHNA APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KRISHNA APARTMENT in Palghar is P99000030577.
Is KRISHNA APARTMENT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA APARTMENT is registered as P99000030577 and its status is "Completed".
What is the construction status of KRISHNA APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA APARTMENT's status on MahaRERA is "Completed". As filed by the builder, slab work on KRISHNA APARTMENT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does KRISHNA APARTMENT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is KRISHNA APARTMENT safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA APARTMENT is registered on MahaRERA as P99000030577, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KRISHNA APARTMENT's possession date changes?
The latest dates are on KRISHNA APARTMENT's MahaRERA page (P99000030577). GharKundli's Kundli Watch sends a free WhatsApp update on KRISHNA APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KRISHNA APARTMENT have?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA APARTMENT has one building filed: KRISHNA APARTMENT with 5 floors.
How big is the land of KRISHNA APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA APARTMENT stands on 604 sq m of land (about 0.1 acres), with 724 sq m of sanctioned built-up area.
Where can I read reviews of KRISHNA APARTMENT?
Google Maps has reviews of KRISHNA APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KRISHNA APARTMENT?
KRISHNA APARTMENT by ASHOK THAKORBHAI PATEL is in Palghar (pincode 401404), near Mahim, Tembhode, Maharashtra, and is registered on MahaRERA as P99000030577, per GharKundli's check of MahaRERA records. Its boundaries filed there include 6 METER LAYOUT ROAD.
How many homes are in KRISHNA APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA APARTMENT has 16 homes in 1 tower registered on MahaRERA.
When was KRISHNA APARTMENT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KRISHNA APARTMENT was registered on MahaRERA on 1 September 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on KRISHNA APARTMENT?
No court cases are listed for KRISHNA APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of KRISHNA APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ASHOK THAKORBHAI PATEL.
Check it yourself on MahaRERA
- How to check the possession date of KRISHNA APARTMENT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401404
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.