SILVERLINES RESIDENCY
by M/S SILVER HOMES · Near St. Peter School, PalgharAlso near Virar, Behind D'Mart
Possession date of SILVERLINES RESIDENCY: 26 May 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000033389, and currently active. Its completion date is now May 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SILVERLINES RESIDENCY?
How the possession date of SILVERLINES RESIDENCY has moved
26 January 2030
Completion date given when the project was registered
26 May 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SILVERLINES RESIDENCY’s extension records on MahaRERA (P99000033389), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SILVERLINES RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the May 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000033389
- Status
- Registered and active
- Builder
- M/S SILVER HOMES
- Location
- Near St. Peter School, Palghar · 401305
- Project type
- Others
- Registered on
- 16 Feb 2022
- Completion date at registration
- January 2030
- Latest completion date
- May 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 72
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of SILVERLINES RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SILVER PRIDE | 100% | 100% | 100% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SILVERLINES RESIDENCY every month.
SILVERLINES RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: SILVER PRIDE (14 floors)
- Land: 7,160 sq m (about 1.8 acres) · sanctioned built-up 3,831 sq m · recreational space 310 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SILVERLINES RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SILVERLINES RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SILVERLINES RESIDENCY
What is the possession date of SILVERLINES RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SILVERLINES RESIDENCY in Near St. Peter School, Palghar is 26 May 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SILVERLINES RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SILVERLINES RESIDENCY's builder has filed on MahaRERA, the official one, is 26 May 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SILVERLINES RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SILVERLINES RESIDENCY in Near St. Peter School, Palghar is P99000033389.
Is SILVERLINES RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SILVERLINES RESIDENCY is registered as P99000033389 and its status is "Registered and active".
What is the construction status of SILVERLINES RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), SILVERLINES RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SILVER PRIDE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SILVERLINES RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SILVERLINES RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SILVERLINES RESIDENCY is registered on MahaRERA as P99000033389, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SILVERLINES RESIDENCY's possession date changes?
The latest dates are on SILVERLINES RESIDENCY's MahaRERA page (P99000033389). GharKundli's Kundli Watch sends a free WhatsApp update on SILVERLINES RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SILVERLINES RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), SILVERLINES RESIDENCY has one building filed: SILVER PRIDE with 14 floors.
How big is the land of SILVERLINES RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), SILVERLINES RESIDENCY stands on 7,160 sq m of land (about 1.8 acres), with 3,831 sq m of sanctioned built-up area and 310 sq m of recreational open space.
Where can I read reviews of SILVERLINES RESIDENCY?
Google Maps has reviews of SILVERLINES RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SILVERLINES RESIDENCY?
SILVERLINES RESIDENCY by M/S SILVER HOMES is in Near St. Peter School, Palghar (pincode 401305), near Virar, Behind D'Mart, Maharashtra, and is registered on MahaRERA as P99000033389, per GharKundli's check of MahaRERA records.
How many homes are in SILVERLINES RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), SILVERLINES RESIDENCY has 72 homes in 1 tower registered on MahaRERA.
When was SILVERLINES RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SILVERLINES RESIDENCY was registered on MahaRERA on 16 February 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SILVERLINES RESIDENCY?
1 court case is listed for SILVERLINES RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SILVERLINES RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/S SILVER HOMES.
Check it yourself on MahaRERA
- How to check the possession date of SILVERLINES RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Palghar →
Other projects in Vasai
- VIMALNATH Building no-2
- STAR LEGACY
- Acciano Bianca
- COMFORT AARADHYA
- DHANANJAY ICON
- GULMOHAR HERITAGE BUILDING NO 3 WING E PHASE I
- SHIVNERI
- Carpentry Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.