Sunteck Beach Residences 1

by SUNTECK REAL ESTATES PRIVATE LIMITED · Village Dhovali, Palghar

Possession date of Sunteck Beach Residences 1: 30 April 2030, moved from 31 December 2027 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000045490, and currently active. Its completion date has moved from December 2027 to April 2030: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Sunteck Beach Residences 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sunteck Beach Residences 1 has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 31 December 2029

    Extended at the builder's request (MahaRERA application EA19012619497)

    Reason the builder gave MahaRERA: “As per order of the Hon'ble Chairman (MahaRERA) Dated 07/07/2026, we request you kindly to grant us extension till 31/12/2029.”
  3. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sunteck Beach Residences 1’s extension records on MahaRERA (P99000045490), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sunteck Beach Residences 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints and 3 court cases, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P99000045490
Status
Registered and active
Builder
SUNTECK REAL ESTATES PRIVATE LIMITED
Location
Village Dhovali, Palghar · 401201
Project type
Residential / Group Housing
Registered on
24 May 2022
Completion date at registration
December 2027
Latest completion date
April 2030
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
286
Sold or booked
46%
Towers
2
Complaints on MahaRERA
4
Court cases listed
3
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Sunteck Beach Residences 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tower-B1100%64%0%0%
Tower-B2100%61%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Tower-B1: covers Ground + 28
  • Tower-B2: covers Ground + 28

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sunteck Beach Residences 1 every month.

Sunteck Beach Residences 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: Tower-B1 (35 floors, 143 units) · Tower-B2 (35 floors, 143 units)
  • Land: 2,580 sq m (about 0.6 acres) · sanctioned built-up 25,026 sq m

The builder’s record and reviews

Sunteck Realty (a group of 7 linked companies) has 42 projects on MahaRERA since 2017, this one included. Of the 34 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 20 months); 24 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 130 complaints on MahaRERA across 16 projects.

Read Google reviews of Sunteck Beach Residences 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sunteck Beach Residences 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sunteck Beach Residences 1

What is the possession date of Sunteck Beach Residences 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sunteck Beach Residences 1 in Village Dhovali, Palghar is 30 April 2030 — 24 months later than 31 December 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sunteck Beach Residences 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sunteck Beach Residences 1's builder has filed on MahaRERA, the official one, is 30 April 2030, already 24 months later than the 31 December 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sunteck Beach Residences 1 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Beach Residences 1's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "As per order of the Hon'ble Chairman (MahaRERA) Dated 07/07/2026, we request you kindly to grant us extension till 31/12/2029.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Sunteck Beach Residences 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sunteck Beach Residences 1 in Village Dhovali, Palghar is P99000045490.

Is Sunteck Beach Residences 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Beach Residences 1 is registered as P99000045490 and its status is "Registered and active".

What is the construction status of Sunteck Beach Residences 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Beach Residences 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 61% to 64% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Sunteck Beach Residences 1 have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sunteck Beach Residences 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Beach Residences 1 is registered on MahaRERA as P99000045490, its completion date has moved 24 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Sunteck Beach Residences 1 have other wings or phases?

Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: Sunteck Beach Residences 2 (P99000045499, possession 30 Apr 2030); Sunteck Beach Residences 4 (P99000045599, possession 31 Jul 2030); Sunteck Beach Residences - Tower A4 (PR1240002600854, possession 30 Apr 2035); Sunteck Beach Residences - Tower A8 (PR1240002600716, possession 30 Apr 2035). Check that your agreement names the registration of your own wing.

How can I get updates if Sunteck Beach Residences 1's possession date changes?

The latest dates are on Sunteck Beach Residences 1's MahaRERA page (P99000045490). GharKundli's Kundli Watch sends a free WhatsApp update on Sunteck Beach Residences 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sunteck Beach Residences 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Beach Residences 1 has 2 buildings filed: Tower-B1 with 35 floors and 143 units; Tower-B2 with 35 floors and 143 units.

How big is the land of Sunteck Beach Residences 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Beach Residences 1 stands on 2,580 sq m of land (about 0.6 acres), with 25,026 sq m of sanctioned built-up area.

What is the track record of Sunteck Beach Residences 1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Realty (a group of 7 linked companies) has 42 projects on MahaRERA since 2017, this one included. Of the 34 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 20 months); 24 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 130 complaints on MahaRERA across 16 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sunteck Beach Residences 1?

Google Maps has reviews of Sunteck Beach Residences 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sunteck Beach Residences 1?

Sunteck Beach Residences 1 by SUNTECK REAL ESTATES PRIVATE LIMITED is in Village Dhovali, Palghar (pincode 401201), Maharashtra, and is registered on MahaRERA as P99000045490, per GharKundli's check of MahaRERA records.

How many homes are in Sunteck Beach Residences 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Beach Residences 1 has 286 homes in 2 towers registered on MahaRERA, and 46% of them are sold or booked.

When was Sunteck Beach Residences 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sunteck Beach Residences 1 was registered on MahaRERA on 24 May 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Sunteck Beach Residences 1?

3 court cases are listed for Sunteck Beach Residences 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Sunteck Beach Residences 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUNTECK REAL ESTATES PRIVATE LIMITED, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2030 in Palghar →

Other projects in Vasai

All 60 projects in Bassein (401201) →

Other projects by SUNTECK REAL ESTATES PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.