Possession: Avenue Park - I is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800005425. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Avenue Park - I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Avenue Park - I has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51800009119)

    Reason the builder gave MahaRERA:
    “We are partnership firm ,M/s C B Enterprise and had commenced a SRA project comprised of 2 buildings under the name “Avenue Park I” at CTS No 590/1 to 6, 591,592,59/1 to 12, 593, 593/1 to 3, 594, 594/1 to 37 at Pathanwadi, Malad- East, Mumb…” Read the full reason“We are partnership firm ,M/s C B Enterprise and had commenced a SRA project comprised of 2 buildings under the name “Avenue Park I” at CTS No 590/1 to 6, 591,592,59/1 to 12, 593, 593/1 to 3, 594, 594/1 to 37 at Pathanwadi, Malad- East, Mumbai. We submit that the CC permission for building no 2 upto plinth level was granted on 02/11/2012. And permission for further work was obtained by us in parts for Ground + 3 level podium and 4th to 6th Upper Floor on 29-01-2016 and for floor up to 13th Floor (pt) was obtained on 07-03-2017. We have registered ourself as per RERA Act on 11/08/2017 as ongo…”
  3. 30 September 2024

    Extended at the builder's request (MahaRERA application EXT51800018576)

    Reason the builder gave MahaRERA:
    “We would like to inform that we have amended our project plan, and we have received the necessary sanctions for the construction of the building up to the 23rd floors on 10th August 2021. However, we have encountered a discrepancy between t…” Read the full reason“We would like to inform that we have amended our project plan, and we have received the necessary sanctions for the construction of the building up to the 23rd floors on 10th August 2021. However, we have encountered a discrepancy between the sanctioned plan and the Commencement Certificate (CC) issued to us. The current CC dated 13th August 2021 only covers construction up to the 21st floors. As per the rules and regulations, we understand the importance of obtaining the CC for the entire project up to the 23rd floors. However, this process is time-consuming and involves several regulatory…”

Source: Avenue Park - I’s extension records on MahaRERA (P51800005425), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Avenue Park - I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the September 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800005425
Status
Completed
Builder
CB Enterprises
Location
pathanwadi, Mumbai · 400097
Project type
Others
Registered on
11 Aug 2017
Completion date at registration
June 2022
Latest completion date
September 2024
Delay so far
27 months
Homes
226
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of Avenue Park - I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building No 1100%100%100%100%
Building No 2100%91%75%15%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Avenue Park - I every month.

Avenue Park - I: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building No 1 (24 floors) · Building No 2 (24 floors)
  • Land: 5,564 sq m (about 1.4 acres) · sanctioned built-up 11,547 sq m · recreational space 708 sq m
  • Boundaries filed include: Road Rani Sati Marg
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Avenue Park - I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Avenue Park - I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Avenue Park - I

What is the possession date of Avenue Park - I?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Avenue Park - I in pathanwadi, Mumbai is 30 September 2024 — 27 months later than 30 June 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Avenue Park - I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Avenue Park - I's builder has filed on MahaRERA, the official one, is 30 September 2024, already 27 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Avenue Park - I extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Park - I's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2023, giving the reason "We are partnership firm ,M/s C B Enterprise and had commenced a SRA project comprised of 2 buildings under the name “Avenue Park I” at CTS No 590/1 to 6, 591,592,59/1 to 12, 593, 593/1 to 3, 594, 594/1 to 37 at Pathanwadi, Malad- East, Mumbai. We submit that the CC permission for building no 2 upto plinth level was granted on 02/11/2012. And permission for further work was obtained by us in parts for Ground + 3 level podium and 4th to 6th Upper Floor on 29-01-2016 and for floor up to 13th Floor (pt) was obtained on 07-03-2017. We have registered ourself as per RERA Act on 11/08/2017 as ongo…"; to 30 September 2024, giving the reason "We would like to inform that we have amended our project plan, and we have received the necessary sanctions for the construction of the building up to the 23rd floors on 10th August 2021. However, we have encountered a discrepancy between the sanctioned plan and the Commencement Certificate (CC) issued to us. The current CC dated 13th August 2021 only covers construction up to the 21st floors. As per the rules and regulations, we understand the importance of obtaining the CC for the entire project up to the 23rd floors. However, this process is time-consuming and involves several regulatory…".

What is the RERA number of Avenue Park - I?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Avenue Park - I in pathanwadi, Mumbai is P51800005425.

Is Avenue Park - I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Park - I is registered as P51800005425 and its status is "Completed".

What is the construction status of Avenue Park - I?

According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Park - I's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 91% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Avenue Park - I have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Avenue Park - I safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Park - I is registered on MahaRERA as P51800005425, its MahaRERA status is "Completed", its completion date has moved 27 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Avenue Park - I's possession date changes?

The latest dates are on Avenue Park - I's MahaRERA page (P51800005425). GharKundli's Kundli Watch sends a free WhatsApp update on Avenue Park - I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Avenue Park - I have?

According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Park - I has 2 buildings filed: Building No 1 with 24 floors; Building No 2 with 24 floors.

How big is the land of Avenue Park - I?

According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Park - I stands on 5,564 sq m of land (about 1.4 acres), with 11,547 sq m of sanctioned built-up area and 708 sq m of recreational open space.

Where can I read reviews of Avenue Park - I?

Google Maps has reviews of Avenue Park - I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Avenue Park - I?

Avenue Park - I by CB Enterprises is in pathanwadi, Mumbai (pincode 400097), near Jogeshwari WEst, Jogeshwari East, Ambivali West, Maharashtra, and is registered on MahaRERA as P51800005425, per GharKundli's check of MahaRERA records. Its boundaries filed there include Road Rani Sati Marg.

How many homes are in Avenue Park - I?

According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Park - I has 226 homes in 2 towers registered on MahaRERA.

When was Avenue Park - I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Park - I was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Avenue Park - I?

No court cases are listed for Avenue Park - I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Avenue Park - I?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is CB Enterprises.

Other projects in Borivali

All 195 projects in Malad East (400097) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.