Possession date of Sai Avenue: 12 March 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000050553, and currently active. Its completion date is now March 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Sai Avenue?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sai Avenue has moved

  1. 12 November 2028

    Completion date given when the project was registered

  2. 12 March 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sai Avenue’s extension records on MahaRERA (P99000050553), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sai Avenue

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000050553
Status
Registered and active
Builder
Shabbir Kasamali Kachwala
Location
Vasai, Palghar · 401208
Project type
Residential / Group Housing
Registered on
21 Apr 2023
Completion date at registration
November 2028
Latest completion date
March 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
338
Sold or booked
38%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Sai Avenue, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Residential Bldg Wing B100%66%0%0%
Residential Bldg Wing A0%0%0%0%
Residential Bldg Wing C100%70%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Residential Bldg Wing B: covers 15 floors
  • Residential Bldg Wing A: covers 15 floors
  • Residential Bldg Wing C: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Avenue every month.

Sai Avenue: buildings, flats and land, as filed on MahaRERA

  • Buildings: Residential Bldg Wing B (15 floors, 95 units) · Residential Bldg Wing A (16 floors, 114 units) · Residential Bldg Wing C (21 floors, 133 units)
  • Land: 5,195 sq m (about 1.3 acres) · sanctioned built-up 18,382 sq m · recreational space 605 sq m
  • Boundaries filed include: Vasai Diva railway line, Vasai Diva Railway Line

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Sai Avenue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sai Avenue: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sai Avenue

What is the possession date of Sai Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sai Avenue in Vasai, Palghar is 12 March 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sai Avenue?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Avenue's builder has filed on MahaRERA, the official one, is 12 March 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Sai Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sai Avenue in Vasai, Palghar is P99000050553.

Is Sai Avenue registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Avenue is registered as P99000050553 and its status is "Registered and active".

What is the construction status of Sai Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Avenue's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 70% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Sai Avenue have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Sai Avenue safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Avenue is registered on MahaRERA as P99000050553, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sai Avenue's possession date changes?

The latest dates are on Sai Avenue's MahaRERA page (P99000050553). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Avenue every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sai Avenue have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Avenue has 3 buildings filed: Residential Bldg Wing B with 15 floors and 95 units; Residential Bldg Wing A with 16 floors and 114 units; Residential Bldg Wing C with 21 floors and 133 units.

How big is the land of Sai Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Avenue stands on 5,195 sq m of land (about 1.3 acres), with 18,382 sq m of sanctioned built-up area and 605 sq m of recreational open space.

Where can I read reviews of Sai Avenue?

Google Maps has reviews of Sai Avenue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sai Avenue?

Sai Avenue by Shabbir Kasamali Kachwala is in Vasai, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000050553, per GharKundli's check of MahaRERA records. Its boundaries filed there include Vasai Diva railway line, Vasai Diva Railway Line.

How many homes are in Sai Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Avenue has 338 homes in 3 towers registered on MahaRERA, and 38% of them are sold or booked.

When was Sai Avenue registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Avenue was registered on MahaRERA on 21 April 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Sai Avenue?

No court cases are listed for Sai Avenue on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Sai Avenue?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shabbir Kasamali Kachwala.

All projects with possession due in 2029 in Palghar →

Other projects in pincode 401208

All 242 projects in Vasai East IE (401208) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.