MERKEZ
by SAGAR DEVELOPER · Waliv, Palghar
Possession date of MERKEZ: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000052992, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about MERKEZ?
How the possession date of MERKEZ has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: MERKEZ’s extension records on MahaRERA (P99000052992), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MERKEZ
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 court cases, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000052992
- Status
- Registered and active
- Builder
- SAGAR DEVELOPER
- Location
- Waliv, Palghar · 401208
- Project type
- Residential / Group Housing
- Registered on
- 10 Oct 2023
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 324
- Sold or booked
- 64%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 3
- Title report on file
- Not found
Construction progress of MERKEZ, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 1,- WING A AND B | 100% | 50% | 10% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 1,- WING A AND B: covers 23 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MERKEZ every month.
MERKEZ: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 1,- WING A AND B (23 floors, 324 units)
- Car parking: 190 open
- Land: 3,433 sq m (about 0.8 acres) · sanctioned built-up 21,916 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MERKEZ →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MERKEZ: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MERKEZ
What is the possession date of MERKEZ?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MERKEZ in Waliv, Palghar is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MERKEZ?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MERKEZ's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of MERKEZ?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MERKEZ in Waliv, Palghar is P99000052992.
Is MERKEZ registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MERKEZ is registered as P99000052992 and its status is "Registered and active".
What is the construction status of MERKEZ?
According to GharKundli's check of MahaRERA records (updated November 2026), MERKEZ's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING NO 1,- WING A AND B is 50% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.
Does MERKEZ have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is MERKEZ safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), MERKEZ is registered on MahaRERA as P99000052992, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MERKEZ's possession date changes?
The latest dates are on MERKEZ's MahaRERA page (P99000052992). GharKundli's Kundli Watch sends a free WhatsApp update on MERKEZ every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MERKEZ have?
According to GharKundli's check of MahaRERA records (updated November 2026), MERKEZ has one building filed: BUILDING NO 1,- WING A AND B with 23 floors and 324 units.
How much parking does MERKEZ have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 190 open car parking spaces for MERKEZ.
How big is the land of MERKEZ?
According to GharKundli's check of MahaRERA records (updated November 2026), MERKEZ stands on 3,433 sq m of land (about 0.8 acres), with 21,916 sq m of sanctioned built-up area.
Where can I read reviews of MERKEZ?
Google Maps has reviews of MERKEZ written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MERKEZ?
MERKEZ by SAGAR DEVELOPER is in Waliv, Palghar (pincode 401208), Maharashtra, and is registered on MahaRERA as P99000052992, per GharKundli's check of MahaRERA records.
How many homes are in MERKEZ?
According to GharKundli's check of MahaRERA records (updated November 2026), MERKEZ has 324 homes in 1 tower registered on MahaRERA, and 64% of them are sold or booked.
When was MERKEZ registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MERKEZ was registered on MahaRERA on 10 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on MERKEZ?
3 court cases are listed for MERKEZ on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of MERKEZ?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAGAR DEVELOPER.
Check it yourself on MahaRERA
- How to check the possession date of MERKEZ
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Palghar →
Other projects in Waliv
- Govind Enclave
- ASHIYANA
- LAXMI HEIGHTS
- POONAM IMPERIA PHASE II
- POONAM IMPERIA PHASE I
- DHANANJAY AND HAYAAT INDUSTRIAL ESTATE
- APEKSHA COMPLEX
- PEARL AND RUBY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.