QUEENS TOWER

by SHREE MAHAVIR DEVELOPERS · Achole, Palghar

Possession date of QUEENS TOWER: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000056161, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about QUEENS TOWER?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of QUEENS TOWER has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: QUEENS TOWER’s extension records on MahaRERA (P99000056161), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on QUEENS TOWER

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000056161
Status
Registered and active
Builder
SHREE MAHAVIR DEVELOPERS
Location
Achole, Palghar · 401209
Project type
Residential / Group Housing
Registered on
16 May 2024
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
190
Sold or booked
11%
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of QUEENS TOWER, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building No 1 - A Wing100%6%0%0%
Building No 1 - B Wing0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on QUEENS TOWER every month.

QUEENS TOWER: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building No 1 - A Wing (15 floors) · Building No 1 - B Wing (15 floors)
  • Land: 6,338 sq m (about 1.6 acres) · sanctioned built-up 12,367 sq m · recreational space 635 sq m

The builder’s record and reviews

Shree Mahavir Developers has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.

Read Google reviews of QUEENS TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

QUEENS TOWER: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about QUEENS TOWER

What is the possession date of QUEENS TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for QUEENS TOWER in Achole, Palghar is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for QUEENS TOWER?

Builders and listing sites often quote an earlier "target" date for handover. The completion date QUEENS TOWER's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of QUEENS TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of QUEENS TOWER in Achole, Palghar is P99000056161.

Is QUEENS TOWER registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), QUEENS TOWER is registered as P99000056161 and its status is "Registered and active".

What is the construction status of QUEENS TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), QUEENS TOWER's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 6% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does QUEENS TOWER have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is QUEENS TOWER safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), QUEENS TOWER is registered on MahaRERA as P99000056161, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if QUEENS TOWER's possession date changes?

The latest dates are on QUEENS TOWER's MahaRERA page (P99000056161). GharKundli's Kundli Watch sends a free WhatsApp update on QUEENS TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does QUEENS TOWER have?

According to GharKundli's check of MahaRERA records (updated October 2026), QUEENS TOWER has 2 buildings filed: Building No 1 - A Wing with 15 floors; Building No 1 - B Wing with 15 floors.

How big is the land of QUEENS TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), QUEENS TOWER stands on 6,338 sq m of land (about 1.6 acres), with 12,367 sq m of sanctioned built-up area and 635 sq m of recreational open space.

What is the track record of QUEENS TOWER's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Mahavir Developers has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of QUEENS TOWER?

Google Maps has reviews of QUEENS TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is QUEENS TOWER?

QUEENS TOWER by SHREE MAHAVIR DEVELOPERS is in Achole, Palghar (pincode 401209), Maharashtra, and is registered on MahaRERA as P99000056161, per GharKundli's check of MahaRERA records.

How many homes are in QUEENS TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), QUEENS TOWER has 190 homes in 2 towers registered on MahaRERA, and 11% of them are sold or booked.

When was QUEENS TOWER registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), QUEENS TOWER was registered on MahaRERA on 16 May 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on QUEENS TOWER?

No court cases are listed for QUEENS TOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of QUEENS TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE MAHAVIR DEVELOPERS, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2030 in Palghar →

Other projects in Achole

All 96 projects in Nallasopara East (401209) →

Other projects by SHREE MAHAVIR DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.