by M/S.KSA DEVELOPERS · Byculla, Mumbai 400008Also near Agripada, Nagpada, Mazgaon
What’s in the report? →Possession date of Ksa Royale (MahaRERA P51900001206): 30 June 2026, moved from 30 June 2021 (60 months later), and it has already passed. It has 68 homes (1 BHK and 2 BHK, 405–654 sq ft carpet), 100% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900001206. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51900001206, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2026) has passed.
What do you want to know about Ksa Royale?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Ksa Royale has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51900010626)
Reason the builder gave MahaRERA: “Due to Covid-19 and Lockdown CC is valid till NOV-2021”
31 March 2024
Extended at the builder's request (MahaRERA application EXT51900015378)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 86.76% allottees for purpose of extension of RERA registration period of the said project.”30 June 2026
Extended at the builder's request (MahaRERA application EXT51900024891)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints.…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. We have consent of 82.35 % allottees for purpose of e…”
Source: Ksa Royale’s extension records on MahaRERA (P51900001206), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ksa Royale
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 court cases, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900001206
- Status
- Lapsed (registration period ended)
- Builder
- M/S.KSA DEVELOPERS
- Location
- Byculla, Mumbai · 400008
- Project type
- Residential / Group Housing
- Registered on
- 27 Jul 2017
- Completion date at registration
- June 2021
- Latest completion date
- June 2026
- Delay so far
- 60 months
- Homes
- 68
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 2
- Title report on file
- Not found
Construction progress of Ksa Royale, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KSA ROYALE | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- KSA ROYALE: covers Upto 23
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ksa Royale every 1–2 months.
Ksa Royale: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 405 – 501 | 60 |
| 2 BHK | 576 – 654 | 8 |
- Buildings: KSA ROYALE (25 floors, 68 units)
- Land: 763 sq m (about 0.2 acres) · sanctioned built-up 7,762 sq m
- Boundaries filed include: Public Road
- Land, as filed: 1787, 2/1787
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
KSA Developers (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 7 months); 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Ksa Royale →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ksa Royale: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Ksa Royale
What is the possession date of Ksa Royale?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ksa Royale in Byculla, Mumbai is 30 June 2026 — 60 months later than 30 June 2021, the date given at registration. That date has already passed.
The date has already moved 60 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Ksa Royale?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ksa Royale's builder has filed on MahaRERA, the official one, is 30 June 2026, already 60 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Ksa Royale extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Ksa Royale's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "Due to Covid-19 and Lockdown CC is valid till NOV-2021"; to 31 March 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 86.76% allottees for purpose of extension of RERA registration period of the said project."; to 30 June 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. We have consent of 82.35 % allottees for purpose of e…".
What is the RERA number of Ksa Royale?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ksa Royale in Byculla, Mumbai is P51900001206.
Is Ksa Royale registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ksa Royale is registered as P51900001206 and its status is "Lapsed (registration period ended)".
What is the current construction status of Ksa Royale? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Ksa Royale's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on KSA ROYALE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Ksa Royale have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Ksa Royale safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Ksa Royale is registered on MahaRERA as P51900001206, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Ksa Royale?
Ksa Royale isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Ksa Royale are 405 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Ksa Royale?
For a flat in Ksa Royale (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Ksa Royale received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ksa Royale isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Ksa Royale?
According to GharKundli's check of MahaRERA records (updated October 2026), Ksa Royale's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Ksa Royale uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ksa Royale was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Ksa Royale's possession date changes?
The latest dates are on Ksa Royale's MahaRERA page (P51900001206). GharKundli's Kundli Watch sends a free WhatsApp update on Ksa Royale every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ksa Royale have?
According to GharKundli's check of MahaRERA records (updated October 2026), Ksa Royale has one building filed: KSA ROYALE with 25 floors and 68 units.
What are the flat sizes (carpet area) in Ksa Royale?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ksa Royale: 1 BHK: 405 to 501 sq ft carpet (60 homes); 2 BHK: 576 to 654 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Ksa Royale?
According to GharKundli's check of MahaRERA records (updated October 2026), Ksa Royale stands on 763 sq m of land (about 0.2 acres), with 7,762 sq m of sanctioned built-up area.
What is the track record of Ksa Royale's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), KSA Developers (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 7 months); 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Ksa Royale?
Google Maps has reviews of Ksa Royale written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Ksa Royale?
Ksa Royale by M/S.KSA DEVELOPERS is in Byculla, Mumbai, pincode 400008 (near Agripada, Nagpada, Mazgaon), Maharashtra, and is registered on MahaRERA as P51900001206, per GharKundli's check of MahaRERA records. Its boundaries filed there include Public Road. Its land is filed as 1787, 2/1787. GharKundli lists all 75 MahaRERA projects in Mumbai Central (400008).
How many flats are in Ksa Royale, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Ksa Royale has 68 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Ksa Royale registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ksa Royale was registered on MahaRERA on 27 July 2017. GharKundli did not find a title report on the land on file there.
Does Ksa Royale have any legal issues or court cases?
2 court cases are listed for Ksa Royale on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Ksa Royale?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S.KSA DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Ksa Royale
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai City →
Other projects in Mumbai Central (400008)
- Bismillah Arcade 2
- Olympia Tower
- Rawdah Living
- Lodha Bellevue
- Bellevue Tower - 3
- Mahindra BeaconHill
- Salsette27 Centre
- Saif towers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.