Saif towers

by Mustanshir Saifuddin Merchant · Byculla, MumbaiAlso near Mazgaon, Chinchbunder, Sewri

Possession date of Saif towers: 31 December 2025, moved from 31 December 2019 (72 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51900012891. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Saif towers?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Saif towers has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT51900010042)

    Reason the builder gave MahaRERA: “We would be requiring an extension as construction is not yet completed and we are planning to complete it by next year and ensure possession with in the time frame.”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51900017285)

    Reason the builder gave MahaRERA:
    “Due to certain permission issues project could not be completed on time and due to changes in policy and Incentive FSI we were in process of getting approvals upto 22 Habitable floors we got the IOD and are expecting CC by mid of june 2024…” Read the full reason“Due to certain permission issues project could not be completed on time and due to changes in policy and Incentive FSI we were in process of getting approvals upto 22 Habitable floors we got the IOD and are expecting CC by mid of june 2024 (which we were supposed to get by March 24 but due to elections etc were not able to get the same), Hence we request to kindly extend the completion date to 31-12-24”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51900027130)

    Reason the builder gave MahaRERA:
    “The construction project is nearing completion, with only a few finishing tasks remaining. Due to funding constraints, there was a delay in the completion of the project. However, work is now back on track and is expected to be finished bef…” Read the full reason“The construction project is nearing completion, with only a few finishing tasks remaining. Due to funding constraints, there was a delay in the completion of the project. However, work is now back on track and is expected to be finished before December 2025. An extension request has been submitted for a deadline of December 2025. Further as per clause 14 (2) (ii) (Explanation Note) the allottees, irrespective of the number of apartments or plots, as the case may be, booked by him or booked in the name of his family, or companies or firms or any association etc;, booked in its name or its as…”

Source: Saif towers’s extension records on MahaRERA (P51900012891), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Saif towers

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900012891
Status
Lapsed (registration period ended)
Builder
Mustanshir Saifuddin Merchant
Location
Byculla, Mumbai · 400010
Project type
Residential / Group Housing
Registered on
7 Sep 2017
Completion date at registration
December 2019
Latest completion date
December 2025
Delay so far
72 months
Homes
67
Sold or booked
73%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of Saif towers, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Saif Towers100%100%98%95%

Commencement certificate (CC), as filed on MahaRERA

  • Saif Towers: covers 22 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Saif towers every month.

Saif towers: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK350 – 59467
Shops122 – 2545

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Saif towers →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Saif towers: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Saif towers

What is the possession date of Saif towers?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Saif towers in Byculla, Mumbai is 31 December 2025 — 72 months later than 31 December 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Saif towers?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Saif towers's builder has filed on MahaRERA, the official one, is 31 December 2025, already 72 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Saif towers extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Saif towers's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2022, giving the reason "We would be requiring an extension as construction is not yet completed and we are planning to complete it by next year and ensure possession with in the time frame."; to 31 December 2024, giving the reason "Due to certain permission issues project could not be completed on time and due to changes in policy and Incentive FSI we were in process of getting approvals upto 22 Habitable floors we got the IOD and are expecting CC by mid of june 2024 (which we were supposed to get by March 24 but due to elections etc were not able to get the same), Hence we request to kindly extend the completion date to 31-12-24"; to 31 December 2025, giving the reason "The construction project is nearing completion, with only a few finishing tasks remaining. Due to funding constraints, there was a delay in the completion of the project. However, work is now back on track and is expected to be finished before December 2025. An extension request has been submitted for a deadline of December 2025. Further as per clause 14 (2) (ii) (Explanation Note) the allottees, irrespective of the number of apartments or plots, as the case may be, booked by him or booked in the name of his family, or companies or firms or any association etc;, booked in its name or its as…".

What is the RERA number of Saif towers?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Saif towers in Byculla, Mumbai is P51900012891.

Is Saif towers registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Saif towers is registered as P51900012891 and its status is "Lapsed (registration period ended)".

What is the construction status of Saif towers?

According to GharKundli's check of MahaRERA records (updated October 2026), Saif towers's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Saif Towers is 100% done and internal work 98%. GharKundli's full report compares construction progress with the deadline.

Does Saif towers have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Saif towers safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Saif towers is registered on MahaRERA as P51900012891, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 72 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Saif towers's possession date changes?

The latest dates are on Saif towers's MahaRERA page (P51900012891). GharKundli's Kundli Watch sends a free WhatsApp update on Saif towers every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Saif towers have?

According to GharKundli's check of MahaRERA records (updated October 2026), Saif towers has one building filed: Saif Towers with 26 floors and 72 units.

What are the flat sizes (carpet area) in Saif towers?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Saif towers: 1 BHK: 350 to 594 sq ft carpet (67 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Saif towers?

According to GharKundli's check of MahaRERA records (updated October 2026), Saif towers stands on 380 sq m of land (about 0.1 acres), with 1,674 sq m of sanctioned built-up area.

Where can I read reviews of Saif towers?

Google Maps has reviews of Saif towers written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Saif towers?

Saif towers by Mustanshir Saifuddin Merchant is in Byculla, Mumbai (pincode 400010), near Mazgaon, Chinchbunder, Sewri, Maharashtra, and is registered on MahaRERA as P51900012891, per GharKundli's check of MahaRERA records.

How many homes are in Saif towers?

According to GharKundli's check of MahaRERA records (updated October 2026), Saif towers has 67 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.

When was Saif towers registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Saif towers was registered on MahaRERA on 7 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Saif towers?

No court cases are listed for Saif towers on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Saif towers?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mustanshir Saifuddin Merchant.