Shreeji Towers
by NEUMEC DEVELOPER AND BUILDERS · Barkat Ali Naka, Mumbai
Possession date of Shreeji Towers: 30 September 2027, moved from 28 February 2020 (91 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900012467, and currently active. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Shreeji Towers?
How the possession date of Shreeji Towers has moved
28 February 2020
Completion date given when the project was registered
27 February 2021
Extended at the builder's request (MahaRERA application EXT51900005829)
Reason the builder gave MahaRERA:
“As per the details mentioned at the time of registration of the project at the MahaRERA Website we have mentioned 28/02/2020 as the project completion date. Unfortunately, due to various reasons being lack of labour due to de-monetization,…” Read the full reason
“As per the details mentioned at the time of registration of the project at the MahaRERA Website we have mentioned 28/02/2020 as the project completion date. Unfortunately, due to various reasons being lack of labour due to de-monetization, implementation of GST and introduction of DCPR 2034 by the Competent Authority, Therefore we would like to seek an extension period of one year ie. Till 27/02/2021.”31 March 2023
Extended at the builder's request (MahaRERA application EXT51900011984)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 54% allottees for purpose of extension of RERA registration period of the said project.”30 September 2023
Extended at the builder's request (MahaRERA application EXT51900015436)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 61.81% allottees for purpose of extension of RERA registration period of the said project.”30 September 2024
Extended at the builder's request (MahaRERA application EXT51900019671)
Reason the builder gave MahaRERA:
“1) M/s Neumec Developers and Builders, Limited Liability Partnership Firm having Partners namely 1) Rakesh Jhunjhunwala [deceased] age, 62 years 2) Rekha Jhunjhunwala age, 62 years 3) Rajesh Jhunjhunwala, age 66 years 4) Dinesh Purohit age…” Read the full reason
“1) M/s Neumec Developers and Builders, Limited Liability Partnership Firm having Partners namely 1) Rakesh Jhunjhunwala [deceased] age, 62 years 2) Rekha Jhunjhunwala age, 62 years 3) Rajesh Jhunjhunwala, age 66 years 4) Dinesh Purohit age 45 years 5) Hemchand Purohit, age 73 years having address at 201. Regent Chambers above Status Restaurant, Nariman Point, Mumbai- 400021. Hereinafter Referred to as ‘ The Applicant’. 2) The Applicant made an Application before the Maharashtra Real Estate (Regulatory ) Authority through their Website for Rera Certificate Extention as per Section 6 of RERA…”30 September 2025
Extended at the builder's request (MahaRERA application EXT51900024760)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints.…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. we kindly request an extension until 30-09-2025 to complete the project and fulfil all regulatory requirements. In accordance with circular no 28, we hereb…”30 September 2027
Extended at the builder's request (MahaRERA application EA03112518221)
Reason the builder gave MahaRERA:
“We sincerely apologize for the delay in completing the project and for the late submission of this extension request. The delay has been primarily due to several unforeseen and unavoidable circumstances that have adversely affected the proj…” Read the full reason
“We sincerely apologize for the delay in completing the project and for the late submission of this extension request. The delay has been primarily due to several unforeseen and unavoidable circumstances that have adversely affected the project's progress. These include: 1. Procurement Delays: We experienced significant setbacks due to the delay in the construction and operationalization of the RMC (Ready-Mix Concrete) plant/tower, which is critical to the progress of construction activities. 2. Financial Constraints: The project faced temporary liquidity issues that impacted our ability to…”
Source: Shreeji Towers’s extension records on MahaRERA (P51900012467), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shreeji Towers
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints and 4 court cases, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900012467
- Status
- Registered and active
- Builder
- NEUMEC DEVELOPER AND BUILDERS
- Location
- Barkat Ali Naka, Mumbai · 400037
- Project type
- Residential / Group Housing
- Registered on
- 1 Sep 2017
- Completion date at registration
- February 2020
- Latest completion date
- September 2027
- Delay so far
- 91 months
- Homes
- 84
- Sold or booked
- 70%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 4
- Appeals at the tribunal
- 4
- Title report on file
- Not found
Construction progress of Shreeji Towers, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shreeji Towers | 100% | 100% | 100% | 88% |
Commencement certificate (CC), as filed on MahaRERA
- Shreeji Towers: covers 36 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shreeji Towers every month.
Shreeji Towers: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 573 – 781 | 57 |
| 1 BHK | 398 – 562 | 27 |
- Buildings: Shreeji Towers (45 floors, 84 units)
- Land: 4,181 sq m (about 1.0 acres) · sanctioned built-up 7,970 sq m · recreational space 198 sq m
- Boundaries filed include: Antophill WH Bhaiyasaab Nagar, Sewri Chembur Road, Vidyalankar College Road
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shreeji Towers →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shreeji Towers: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shreeji Towers
What is the possession date of Shreeji Towers?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shreeji Towers in Barkat Ali Naka, Mumbai is 30 September 2027 — 91 months later than 28 February 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Shreeji Towers?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shreeji Towers's builder has filed on MahaRERA, the official one, is 30 September 2027, already 91 months later than the 28 February 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shreeji Towers extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Towers's builder applied to MahaRERA to extend the completion date 6 times: to 27 February 2021, giving the reason "As per the details mentioned at the time of registration of the project at the MahaRERA Website we have mentioned 28/02/2020 as the project completion date. Unfortunately, due to various reasons being lack of labour due to de-monetization, implementation of GST and introduction of DCPR 2034 by the Competent Authority, Therefore we would like to seek an extension period of one year ie. Till 27/02/2021."; to 31 March 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19. We have consent of 54% allottees for purpose of extension of RERA registration period of the said project."; to 30 September 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 61.81% allottees for purpose of extension of RERA registration period of the said project."; to 30 September 2024, giving the reason "1) M/s Neumec Developers and Builders, Limited Liability Partnership Firm having Partners namely 1) Rakesh Jhunjhunwala [deceased] age, 62 years 2) Rekha Jhunjhunwala age, 62 years 3) Rajesh Jhunjhunwala, age 66 years 4) Dinesh Purohit age 45 years 5) Hemchand Purohit, age 73 years having address at 201. Regent Chambers above Status Restaurant, Nariman Point, Mumbai- 400021. Hereinafter Referred to as ‘ The Applicant’. 2) The Applicant made an Application before the Maharashtra Real Estate (Regulatory ) Authority through their Website for Rera Certificate Extention as per Section 6 of RERA…"; to 30 September 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. we kindly request an extension until 30-09-2025 to complete the project and fulfil all regulatory requirements. In accordance with circular no 28, we hereb…"; to 30 September 2027, giving the reason "We sincerely apologize for the delay in completing the project and for the late submission of this extension request. The delay has been primarily due to several unforeseen and unavoidable circumstances that have adversely affected the project's progress. These include: 1. Procurement Delays: We experienced significant setbacks due to the delay in the construction and operationalization of the RMC (Ready-Mix Concrete) plant/tower, which is critical to the progress of construction activities. 2. Financial Constraints: The project faced temporary liquidity issues that impacted our ability to…".
What is the RERA number of Shreeji Towers?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shreeji Towers in Barkat Ali Naka, Mumbai is P51900012467.
Is Shreeji Towers registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Towers is registered as P51900012467 and its status is "Registered and active".
What is the construction status of Shreeji Towers?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Towers's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Shreeji Towers is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Shreeji Towers have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Shreeji Towers safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Towers is registered on MahaRERA as P51900012467, its completion date has moved 91 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shreeji Towers's possession date changes?
The latest dates are on Shreeji Towers's MahaRERA page (P51900012467). GharKundli's Kundli Watch sends a free WhatsApp update on Shreeji Towers every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shreeji Towers have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Towers has one building filed: Shreeji Towers with 45 floors and 84 units.
What are the flat sizes (carpet area) in Shreeji Towers?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shreeji Towers: 2 BHK: 573 to 781 sq ft carpet (57 homes); 1 BHK: 398 to 562 sq ft carpet (27 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Shreeji Towers?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Towers stands on 4,181 sq m of land (about 1.0 acres), with 7,970 sq m of sanctioned built-up area and 198 sq m of recreational open space.
Where can I read reviews of Shreeji Towers?
Google Maps has reviews of Shreeji Towers written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shreeji Towers?
Shreeji Towers by NEUMEC DEVELOPER AND BUILDERS is in Barkat Ali Naka, Mumbai (pincode 400037), Maharashtra, and is registered on MahaRERA as P51900012467, per GharKundli's check of MahaRERA records. Its boundaries filed there include Antophill WH Bhaiyasaab Nagar, Sewri Chembur Road, Vidyalankar College Road.
How many homes are in Shreeji Towers?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Towers has 84 homes in 1 tower registered on MahaRERA, and 70% of them are sold or booked.
When was Shreeji Towers registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Towers was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Shreeji Towers?
4 court cases are listed for Shreeji Towers on MahaRERA, and 4 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Shreeji Towers?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NEUMEC DEVELOPER AND BUILDERS.
Check it yourself on MahaRERA
- How to check the possession date of Shreeji Towers
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Ward FNorth
- OM BUILDING CO-OPERATIVE HOUSING SOCIETY LIMITED
- SIDDHA SKY PHASE V
- Paramount
- MAARIA ANNEXE
- DOSTI MEZZO 22
- SOM NIWAS
- RIGVED WINDSONG
- DNS ANUUTHAM
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.