Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon

by Nashik Housing And Area Development Board · HUDCO Coloney, West, Jalgaon 425201

What’s in the report? →

Possession: Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon (MahaRERA P49900007208) is marked completed on MahaRERA. It has 33 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P49900007208. Status: Completed.

Source: MahaRERA website — records for P49900007208, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2018 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P49900007208
Status
Completed
Builder
Nashik Housing And Area Development Board
Location
HUDCO Coloney, West, Jalgaon · 425201
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
October 2018
Homes
33
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
13

Construction progress of Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MIG TYPE BUNGLOWS90%90%60%30%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon every 1–2 months.

Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon: buildings, flats and land, as filed on MahaRERA

  • Buildings: MIG TYPE BUNGLOWS (42 floors)
  • Land: 4,085 sq m (about 1.0 acres) · sanctioned built-up 2,788 sq m · recreational space 2,673 sq m
  • Land, as filed: S. No. 300/1B
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon

What is the possession date of Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon in HUDCO Coloney, West, Jalgaon is 5 October 2018.

Is the builder's possession date different from the MahaRERA date for Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon's builder has filed on MahaRERA, the official one, is 5 October 2018, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon in HUDCO Coloney, West, Jalgaon is P49900007208.

Is Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon is registered as P49900007208 and its status is "Completed".

What is the current construction status of Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon's status on MahaRERA is "Completed". As filed by the builder, slab work on MIG TYPE BUNGLOWS is 90% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon is registered on MahaRERA as P49900007208, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon?

According to GharKundli's check of MahaRERA records (updated November 2026), Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon: gharkundli.com/tools/property-cost-calculator

Has Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon is marked completed on MahaRERA, and the completion date filed there is 5 October 2018. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon's possession date changes?

The latest dates are on Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon's MahaRERA page (P49900007208). GharKundli's Kundli Watch sends a free WhatsApp update on Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon have?

According to GharKundli's check of MahaRERA records (updated November 2026), Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon has one building filed: MIG TYPE BUNGLOWS with 42 floors.

How big is the land of Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon?

According to GharKundli's check of MahaRERA records (updated November 2026), Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon stands on 4,085 sq m of land (about 1.0 acres), with 2,788 sq m of sanctioned built-up area and 2,673 sq m of recreational open space.

What are the reviews of Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon?

Google Maps has reviews of Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon?

Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon by Nashik Housing And Area Development Board is in HUDCO Coloney, West, Jalgaon, pincode 425201, Maharashtra, and is registered on MahaRERA as P49900007208, per GharKundli's check of MahaRERA records. Its land is filed as S. No. 300/1B. GharKundli lists all 27 MahaRERA projects in Bhusawal (425201).

How many flats are in Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon?

According to GharKundli's check of MahaRERA records (updated November 2026), Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon has 33 homes in 1 tower registered on MahaRERA.

When was Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Does Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon have any legal issues or court cases?

No court cases are listed for Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Construction of 33 Ts MIG on S. No. 300/1 B at Sakegaon, Bhusawal, Dist. Jalgaon?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Nashik Housing And Area Development Board, which has 13 other projects registered on MahaRERA.

Other projects in Bhusawal

All 27 projects in Bhusawal (425201) →

Other projects by Nashik Housing And Area Development Board

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.