126 FLORENCIO

by ARHAM ENGINEERS · Ghatkopar West, MumbaiAlso near chembur, Tilak Nagar, Vikhroli East

Possession: 126 FLORENCIO is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800005828. Status: Completed. 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about 126 FLORENCIO?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on 126 FLORENCIO

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints, and how it ended
  • Construction pace against the September 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800005828
Status
Completed
Builder
ARHAM ENGINEERS
Location
Ghatkopar West, Mumbai · 400089
Project type
Others
Registered on
14 Aug 2017
Completion date at registration
March 2019
Latest completion date
September 2020
Delay so far
18 months
Homes
67
Towers
1
Complaints on MahaRERA
7
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found

Construction progress of 126 FLORENCIO, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
126 FLORENCIO100%100%88%30%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on 126 FLORENCIO every month.

126 FLORENCIO: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Ayyappa Developers (a group of 4 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 29 months); 1 still being built, none past the promised date yet; 2 lapsed. 23 complaints on MahaRERA across 3 projects.

Read Google reviews of 126 FLORENCIO →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

126 FLORENCIO: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about 126 FLORENCIO

What is the possession date of 126 FLORENCIO?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 126 FLORENCIO in Ghatkopar West, Mumbai is 30 September 2020 — 18 months later than 31 March 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for 126 FLORENCIO?

Builders and listing sites often quote an earlier "target" date for handover. The completion date 126 FLORENCIO's builder has filed on MahaRERA, the official one, is 30 September 2020, already 18 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of 126 FLORENCIO?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 126 FLORENCIO in Ghatkopar West, Mumbai is P51800005828.

Is 126 FLORENCIO registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 126 FLORENCIO is registered as P51800005828 and its status is "Completed".

What is the construction status of 126 FLORENCIO?

According to GharKundli's check of MahaRERA records (updated November 2026), 126 FLORENCIO's status on MahaRERA is "Completed". As filed by the builder, slab work on 126 FLORENCIO is 100% done and internal work 88%. GharKundli's full report compares construction progress with the deadline.

Does 126 FLORENCIO have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is 126 FLORENCIO safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), 126 FLORENCIO is registered on MahaRERA as P51800005828, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if 126 FLORENCIO's possession date changes?

The latest dates are on 126 FLORENCIO's MahaRERA page (P51800005828). GharKundli's Kundli Watch sends a free WhatsApp update on 126 FLORENCIO every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does 126 FLORENCIO have?

According to GharKundli's check of MahaRERA records (updated November 2026), 126 FLORENCIO has one building filed: 126 FLORENCIO with 15 floors.

How big is the land of 126 FLORENCIO?

According to GharKundli's check of MahaRERA records (updated November 2026), 126 FLORENCIO stands on 1,041 sq m of land (about 0.3 acres), with 5,723 sq m of sanctioned built-up area.

What is the track record of 126 FLORENCIO's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Ayyappa Developers (a group of 4 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 29 months); 1 still being built, none past the promised date yet; 2 lapsed. 23 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of 126 FLORENCIO?

Google Maps has reviews of 126 FLORENCIO written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is 126 FLORENCIO?

126 FLORENCIO by ARHAM ENGINEERS is in Ghatkopar West, Mumbai (pincode 400089), near chembur, Tilak Nagar, Vikhroli East, Maharashtra, and is registered on MahaRERA as P51800005828, per GharKundli's check of MahaRERA records.

How many homes are in 126 FLORENCIO?

According to GharKundli's check of MahaRERA records (updated November 2026), 126 FLORENCIO has 67 homes in 1 tower registered on MahaRERA.

When was 126 FLORENCIO registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), 126 FLORENCIO was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on 126 FLORENCIO?

No court cases are listed for 126 FLORENCIO on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of 126 FLORENCIO?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ARHAM ENGINEERS.

All projects in Chembur (400089) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.