PANCHRATNA
by GANGA BUILDERS AND DEVELOPERS · Satyakrupa Colony, Amravati
Possession: PANCHRATNA is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P50300019703. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about PANCHRATNA?
How the possession date of PANCHRATNA has moved
30 December 2021
Completion date given when the project was registered
6 May 2023
Extended at the builder's request (MahaRERA application EXT50300016687)
Reason the builder gave MahaRERA:
“Project of Panchratna building is completed on 09.04.2022. We have received occupancy certificate from Town Planning Authority of Municipal Corporation of Amravati. We have failed to intimate such completion to MAHARERA within time. We kind…” Read the full reason
“Project of Panchratna building is completed on 09.04.2022. We have received occupancy certificate from Town Planning Authority of Municipal Corporation of Amravati. We have failed to intimate such completion to MAHARERA within time. We kindly request you to take a note of the same and grant us project completion status by MAHARERA. Our project was supposed to be completed by 30.12.2021, but due to covid period, we have faced difficulty to complete the project within time frame but finally we received completion certificate on 09.04.2022. Request you to condone our delay and grant us complet…”
Source: PANCHRATNA’s extension records on MahaRERA (P50300019703), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PANCHRATNA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P50300019703
- Status
- Completed
- Builder
- GANGA BUILDERS AND DEVELOPERS
- Location
- Satyakrupa Colony, Amravati · 444606
- Project type
- Residential / Group Housing
- Registered on
- 22 Feb 2019
- Completion date at registration
- December 2021
- Latest completion date
- May 2023
- Delay so far
- 17 months
- Homes
- 15
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of PANCHRATNA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PANCHRATNA | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PANCHRATNA every month.
PANCHRATNA: buildings, flats and land, as filed on MahaRERA
- Buildings: PANCHRATNA (9 floors)
- Land: 471 sq m (about 0.1 acres) · sanctioned built-up 965 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of PANCHRATNA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PANCHRATNA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PANCHRATNA
What is the possession date of PANCHRATNA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PANCHRATNA in Satyakrupa Colony, Amravati is 6 May 2023 — 17 months later than 30 December 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for PANCHRATNA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PANCHRATNA's builder has filed on MahaRERA, the official one, is 6 May 2023, already 17 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PANCHRATNA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), PANCHRATNA's builder applied to MahaRERA to extend the completion date once: to 6 May 2023, giving the reason "Project of Panchratna building is completed on 09.04.2022. We have received occupancy certificate from Town Planning Authority of Municipal Corporation of Amravati. We have failed to intimate such completion to MAHARERA within time. We kindly request you to take a note of the same and grant us project completion status by MAHARERA. Our project was supposed to be completed by 30.12.2021, but due to covid period, we have faced difficulty to complete the project within time frame but finally we received completion certificate on 09.04.2022. Request you to condone our delay and grant us complet…".
What is the RERA number of PANCHRATNA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PANCHRATNA in Satyakrupa Colony, Amravati is P50300019703.
Is PANCHRATNA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PANCHRATNA is registered as P50300019703 and its status is "Completed".
What is the construction status of PANCHRATNA?
According to GharKundli's check of MahaRERA records (updated November 2026), PANCHRATNA's status on MahaRERA is "Completed". As filed by the builder, slab work on PANCHRATNA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does PANCHRATNA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is PANCHRATNA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), PANCHRATNA is registered on MahaRERA as P50300019703, its MahaRERA status is "Completed", its completion date has moved 17 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PANCHRATNA's possession date changes?
The latest dates are on PANCHRATNA's MahaRERA page (P50300019703). GharKundli's Kundli Watch sends a free WhatsApp update on PANCHRATNA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PANCHRATNA have?
According to GharKundli's check of MahaRERA records (updated November 2026), PANCHRATNA has one building filed: PANCHRATNA with 9 floors.
How big is the land of PANCHRATNA?
According to GharKundli's check of MahaRERA records (updated November 2026), PANCHRATNA stands on 471 sq m of land (about 0.1 acres), with 965 sq m of sanctioned built-up area.
Where can I read reviews of PANCHRATNA?
Google Maps has reviews of PANCHRATNA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PANCHRATNA?
PANCHRATNA by GANGA BUILDERS AND DEVELOPERS is in Satyakrupa Colony, Amravati (pincode 444606), Maharashtra, and is registered on MahaRERA as P50300019703, per GharKundli's check of MahaRERA records.
How many homes are in PANCHRATNA?
According to GharKundli's check of MahaRERA records (updated November 2026), PANCHRATNA has 15 homes in 1 tower registered on MahaRERA.
When was PANCHRATNA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PANCHRATNA was registered on MahaRERA on 22 February 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on PANCHRATNA?
No court cases are listed for PANCHRATNA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of PANCHRATNA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GANGA BUILDERS AND DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of PANCHRATNA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Amravati
- JANNAT COMPLEX
- LAKSHMI SHRI RESIMERCIAL
- RACHANA SRUSHTI PHASE II
- Dream Imperia
- RAJ TOWNSHIP
- DUBAI CITY
- Green Heights
- DCC Dreamz City Chambers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.