Imperial Complex

by Vipul Uttam Jadhao · Pragane Nandgaon Peth, Amravati 444601

What’s in the report? →

Possession date of Imperial Complex (MahaRERA P50300026473): 30 June 2024, and it has already passed. It has 14 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P50300026473. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P50300026473, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2024) has passed.

What do you want to know about Imperial Complex?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Imperial Complex

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50300026473
Status
Lapsed (registration period ended)
Builder
Vipul Uttam Jadhao
Location
Pragane Nandgaon Peth, Amravati · 444601
Project type
Residential / Group Housing
Registered on
24 Sep 2020
Completion date at registration
June 2024
Latest completion date
June 2024
Homes
14
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Imperial Complex, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Imperial Complex10%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Imperial Complex every 1–2 months.

Imperial Complex: buildings, flats and land, as filed on MahaRERA

  • Buildings: Imperial Complex (5 floors)
  • Land: 500 sq m (about 0.1 acres) · sanctioned built-up 1,002 sq m
  • Land, as filed: Survey No 187/1 and 187/2
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Imperial Complex →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Imperial Complex: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Imperial Complex

What is the possession date of Imperial Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Imperial Complex in Pragane Nandgaon Peth, Amravati is 30 June 2024. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Imperial Complex?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Imperial Complex's builder has filed on MahaRERA, the official one, is 30 June 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Imperial Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Imperial Complex in Pragane Nandgaon Peth, Amravati is P50300026473.

Is Imperial Complex registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Imperial Complex is registered as P50300026473 and its status is "Lapsed (registration period ended)".

What is the current construction status of Imperial Complex? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Imperial Complex's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Imperial Complex is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Imperial Complex have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Imperial Complex safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Imperial Complex is registered on MahaRERA as P50300026473, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Imperial Complex?

Imperial Complex isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Imperial Complex?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Imperial Complex: gharkundli.com/tools/property-cost-calculator

Has Imperial Complex received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Imperial Complex isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Imperial Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), Imperial Complex's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Imperial Complex uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Imperial Complex was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Imperial Complex's possession date changes?

The latest dates are on Imperial Complex's MahaRERA page (P50300026473). GharKundli's Kundli Watch sends a free WhatsApp update on Imperial Complex every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Imperial Complex have?

According to GharKundli's check of MahaRERA records (updated November 2026), Imperial Complex has one building filed: Imperial Complex with 5 floors.

How big is the land of Imperial Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), Imperial Complex stands on 500 sq m of land (about 0.1 acres), with 1,002 sq m of sanctioned built-up area.

What are the reviews of Imperial Complex?

Google Maps has reviews of Imperial Complex written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Imperial Complex?

Imperial Complex by Vipul Uttam Jadhao is in Pragane Nandgaon Peth, Amravati, pincode 444601, Maharashtra, and is registered on MahaRERA as P50300026473, per GharKundli's check of MahaRERA records. Its land is filed as Survey No 187/1 and 187/2. GharKundli lists all 69 MahaRERA projects in Amravati (444601).

How many flats are in Imperial Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), Imperial Complex has 14 homes in 1 tower registered on MahaRERA.

When was Imperial Complex registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Imperial Complex was registered on MahaRERA on 24 September 2020. GharKundli did not find a title report on the land on file there.

Does Imperial Complex have any legal issues or court cases?

No court cases are listed for Imperial Complex on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Imperial Complex?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Vipul Uttam Jadhao.