VIJAYSHREE PARK

by PANKAJKUMAR RAMESHRAO DESHMUKH · Shivaji Nagar S.O (Amravati), AmravatiAlso near Rukhmini Nagar, H. V. Nagar

Possession date of VIJAYSHREE PARK: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50300047720, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about VIJAYSHREE PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VIJAYSHREE PARK has moved

  1. 30 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VIJAYSHREE PARK’s extension records on MahaRERA (P50300047720), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VIJAYSHREE PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50300047720
Status
Registered and active
Builder
PANKAJKUMAR RAMESHRAO DESHMUKH
Location
Shivaji Nagar S.O (Amravati), Amravati · 444603
Project type
Others
Registered on
21 Nov 2022
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
50
Sold or booked
17%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of VIJAYSHREE PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VIJAYSHREE PARK- WING A90%50%50%45%
VIJAYSHREE PARK-WING B70%30%15%0%

Commencement certificate (CC), as filed on MahaRERA

  • VIJAYSHREE PARK- WING A: covers 8 floors
  • VIJAYSHREE PARK-WING B: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VIJAYSHREE PARK every month.

VIJAYSHREE PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: VIJAYSHREE PARK- WING A (8 floors, 58 units) · VIJAYSHREE PARK-WING B (8 floors, 26 units)
  • Land: 1,774 sq m (about 0.4 acres) · sanctioned built-up 5,745 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of VIJAYSHREE PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VIJAYSHREE PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VIJAYSHREE PARK

What is the possession date of VIJAYSHREE PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VIJAYSHREE PARK in Shivaji Nagar S.O (Amravati), Amravati is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VIJAYSHREE PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VIJAYSHREE PARK's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of VIJAYSHREE PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VIJAYSHREE PARK in Shivaji Nagar S.O (Amravati), Amravati is P50300047720.

Is VIJAYSHREE PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VIJAYSHREE PARK is registered as P50300047720 and its status is "Registered and active".

What is the construction status of VIJAYSHREE PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), VIJAYSHREE PARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 30% to 50% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does VIJAYSHREE PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is VIJAYSHREE PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), VIJAYSHREE PARK is registered on MahaRERA as P50300047720, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VIJAYSHREE PARK's possession date changes?

The latest dates are on VIJAYSHREE PARK's MahaRERA page (P50300047720). GharKundli's Kundli Watch sends a free WhatsApp update on VIJAYSHREE PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VIJAYSHREE PARK have?

According to GharKundli's check of MahaRERA records (updated November 2026), VIJAYSHREE PARK has 2 buildings filed: VIJAYSHREE PARK- WING A with 8 floors and 58 units; VIJAYSHREE PARK-WING B with 8 floors and 26 units.

How big is the land of VIJAYSHREE PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), VIJAYSHREE PARK stands on 1,774 sq m of land (about 0.4 acres), with 5,745 sq m of sanctioned built-up area.

Where can I read reviews of VIJAYSHREE PARK?

Google Maps has reviews of VIJAYSHREE PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VIJAYSHREE PARK?

VIJAYSHREE PARK by PANKAJKUMAR RAMESHRAO DESHMUKH is in Shivaji Nagar S.O (Amravati), Amravati (pincode 444603), near Rukhmini Nagar, H. V. Nagar, Maharashtra, and is registered on MahaRERA as P50300047720, per GharKundli's check of MahaRERA records.

How many homes are in VIJAYSHREE PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), VIJAYSHREE PARK has 50 homes in 2 towers registered on MahaRERA, and 17% of them are sold or booked.

When was VIJAYSHREE PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VIJAYSHREE PARK was registered on MahaRERA on 21 November 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on VIJAYSHREE PARK?

No court cases are listed for VIJAYSHREE PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of VIJAYSHREE PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PANKAJKUMAR RAMESHRAO DESHMUKH.

All projects with possession due in 2028 in Amravati →

Other projects in Amravati

All 8 projects in Amravati (444603) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.