Possession date of Sky Garden Hills: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P50300055399, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Sky Garden Hills?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sky Garden Hills has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sky Garden Hills’s extension records on MahaRERA (P50300055399), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sky Garden Hills

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P50300055399
Status
Registered and active
Builder
V & M BUILDERS & DEVELOPERS
Location
Mouje Benoda, Amravati · 444606
Project type
Others
Registered on
22 Mar 2024
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
48
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Sky Garden Hills, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sky Garden Hills0%8%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sky Garden Hills every month.

Sky Garden Hills: buildings, flats and land, as filed on MahaRERA

  • Buildings: Sky Garden Hills (11 floors)
  • Land: 1,000 sq m (about 0.2 acres) · sanctioned built-up 4,041 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Sky Garden Hills →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sky Garden Hills: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sky Garden Hills

What is the possession date of Sky Garden Hills?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sky Garden Hills in Mouje Benoda, Amravati is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Sky Garden Hills?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sky Garden Hills's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Sky Garden Hills?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sky Garden Hills in Mouje Benoda, Amravati is P50300055399.

Is Sky Garden Hills registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sky Garden Hills is registered as P50300055399 and its status is "Registered and active".

What is the construction status of Sky Garden Hills?

According to GharKundli's check of MahaRERA records (updated October 2026), Sky Garden Hills's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sky Garden Hills is 8% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Sky Garden Hills have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sky Garden Hills safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sky Garden Hills is registered on MahaRERA as P50300055399, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sky Garden Hills's possession date changes?

The latest dates are on Sky Garden Hills's MahaRERA page (P50300055399). GharKundli's Kundli Watch sends a free WhatsApp update on Sky Garden Hills every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sky Garden Hills have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sky Garden Hills has one building filed: Sky Garden Hills with 11 floors.

How big is the land of Sky Garden Hills?

According to GharKundli's check of MahaRERA records (updated October 2026), Sky Garden Hills stands on 1,000 sq m of land (about 0.2 acres), with 4,041 sq m of sanctioned built-up area.

Where can I read reviews of Sky Garden Hills?

Google Maps has reviews of Sky Garden Hills written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sky Garden Hills?

Sky Garden Hills by V & M BUILDERS & DEVELOPERS is in Mouje Benoda, Amravati (pincode 444606), Maharashtra, and is registered on MahaRERA as P50300055399, per GharKundli's check of MahaRERA records.

How many homes are in Sky Garden Hills?

According to GharKundli's check of MahaRERA records (updated October 2026), Sky Garden Hills has 48 homes in 1 tower registered on MahaRERA.

When was Sky Garden Hills registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sky Garden Hills was registered on MahaRERA on 22 March 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on Sky Garden Hills?

No court cases are listed for Sky Garden Hills on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Sky Garden Hills?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is V & M BUILDERS & DEVELOPERS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Amravati →

Other projects in Amravati

All 19 projects in Rukhmini Nagar (444606) →

Other projects by V & M BUILDERS & DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.