SANKALP ICON
by SANKALP DREAM SPACES LLP · Rahatgaon, AmravatiAlso near Amravati Camp
Possession date of SANKALP ICON: 30 April 2031. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1030002600302, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SANKALP ICON?
How the possession date of SANKALP ICON has moved
31 December 2030
Completion date given when the project was registered
30 April 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SANKALP ICON’s extension records on MahaRERA (PR1030002600302), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SANKALP ICON
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1030002600302
- Status
- Registered and active
- Builder
- SANKALP DREAM SPACES LLP
- Location
- Rahatgaon, Amravati · 444602
- Project type
- Residential / Group Housing
- Registered on
- 29 Apr 2026
- Completion date at registration
- December 2030
- Latest completion date
- April 2031
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 126
- Sold or booked
- 1%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SANKALP ICON, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KUNAL JIWARKAR | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- KUNAL JIWARKAR: covers 15 floors
Latest CC order on MahaRERA: dated 30/03/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SANKALP ICON every month.
SANKALP ICON: buildings, flats and land, as filed on MahaRERA
- Buildings: KUNAL JIWARKAR (15 floors, 126 units)
- Car parking: 129 covered
- Land: 2,920 sq m (about 0.7 acres) · sanctioned built-up 13,884 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SANKALP ICON →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SANKALP ICON: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SANKALP ICON
What is the possession date of SANKALP ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SANKALP ICON in Rahatgaon, Amravati is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SANKALP ICON?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SANKALP ICON's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SANKALP ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SANKALP ICON in Rahatgaon, Amravati is PR1030002600302.
Is SANKALP ICON registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SANKALP ICON is registered as PR1030002600302 and its status is "Registered and active".
What is the construction status of SANKALP ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), SANKALP ICON's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KUNAL JIWARKAR is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does SANKALP ICON have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SANKALP ICON safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SANKALP ICON is registered on MahaRERA as PR1030002600302, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SANKALP ICON's possession date changes?
The latest dates are on SANKALP ICON's MahaRERA page (PR1030002600302). GharKundli's Kundli Watch sends a free WhatsApp update on SANKALP ICON every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SANKALP ICON have?
According to GharKundli's check of MahaRERA records (updated October 2026), SANKALP ICON has one building filed: KUNAL JIWARKAR with 15 floors and 126 units.
How much parking does SANKALP ICON have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 129 covered car parking spaces for SANKALP ICON.
How big is the land of SANKALP ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), SANKALP ICON stands on 2,920 sq m of land (about 0.7 acres), with 13,884 sq m of sanctioned built-up area.
Where can I read reviews of SANKALP ICON?
Google Maps has reviews of SANKALP ICON written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SANKALP ICON?
SANKALP ICON by SANKALP DREAM SPACES LLP is in Rahatgaon, Amravati (pincode 444602), near Amravati Camp, Maharashtra, and is registered on MahaRERA as PR1030002600302, per GharKundli's check of MahaRERA records.
How many homes are in SANKALP ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), SANKALP ICON has 126 homes in 1 tower registered on MahaRERA, and 1% of them are sold or booked.
When was SANKALP ICON registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SANKALP ICON was registered on MahaRERA on 29 April 2026. GharKundli did not find a title report on the land on file there.
Are there court cases on SANKALP ICON?
No court cases are listed for SANKALP ICON on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SANKALP ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SANKALP DREAM SPACES LLP.
Check it yourself on MahaRERA
- How to check the possession date of SANKALP ICON
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Amravati →
Other projects in pincode 444602
- Vivanta Infinity Private Limited
- RACHANA SRUSHTI PHASE II
- Krushnayan Villas
- SOLARIS CUBE
- Vidhi Heights
- Jai Amba Palm City- Areca Palm Wing A,B,C
- OMKAR GALAXY
- Jai Amba Palm City- Queen Palm Wing A B
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.