VEERA PRIME
by VEERA BUILDERS · Kewal Colony, AmravatiAlso near V.M.V. (Amravati)
Possession date of VEERA PRIME: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1030002600950, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VEERA PRIME?
How the possession date of VEERA PRIME has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: VEERA PRIME’s extension records on MahaRERA (PR1030002600950), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VEERA PRIME
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1030002600950
- Status
- Registered and active
- Builder
- VEERA BUILDERS
- Location
- Kewal Colony, Amravati · 444604
- Project type
- Residential / Group Housing
- Registered on
- 29 Jun 2026
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 24
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of VEERA PRIME, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WARDHEKAR | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WARDHEKAR: covers 7 floors
Latest CC order on MahaRERA: dated 17/04/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VEERA PRIME every month.
VEERA PRIME: buildings, flats and land, as filed on MahaRERA
- Buildings: WARDHEKAR (7 floors, 24 units)
- Car parking: 13 covered
- Land: 698 sq m (about 0.2 acres) · sanctioned built-up 1,639 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VEERA PRIME →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VEERA PRIME: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VEERA PRIME
What is the possession date of VEERA PRIME?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VEERA PRIME in Kewal Colony, Amravati is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for VEERA PRIME?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VEERA PRIME's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of VEERA PRIME?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VEERA PRIME in Kewal Colony, Amravati is PR1030002600950.
Is VEERA PRIME registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VEERA PRIME is registered as PR1030002600950 and its status is "Registered and active".
What is the construction status of VEERA PRIME?
According to GharKundli's check of MahaRERA records (updated October 2026), VEERA PRIME's status on MahaRERA is "Registered and active". As filed by the builder, slab work on WARDHEKAR is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does VEERA PRIME have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is VEERA PRIME safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VEERA PRIME is registered on MahaRERA as PR1030002600950, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VEERA PRIME's possession date changes?
The latest dates are on VEERA PRIME's MahaRERA page (PR1030002600950). GharKundli's Kundli Watch sends a free WhatsApp update on VEERA PRIME every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VEERA PRIME have?
According to GharKundli's check of MahaRERA records (updated October 2026), VEERA PRIME has one building filed: WARDHEKAR with 7 floors and 24 units.
How much parking does VEERA PRIME have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 13 covered car parking spaces for VEERA PRIME.
How big is the land of VEERA PRIME?
According to GharKundli's check of MahaRERA records (updated October 2026), VEERA PRIME stands on 698 sq m of land (about 0.2 acres), with 1,639 sq m of sanctioned built-up area.
Where can I read reviews of VEERA PRIME?
Google Maps has reviews of VEERA PRIME written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VEERA PRIME?
VEERA PRIME by VEERA BUILDERS is in Kewal Colony, Amravati (pincode 444604), near V.M.V. (Amravati), Maharashtra, and is registered on MahaRERA as PR1030002600950, per GharKundli's check of MahaRERA records.
How many homes are in VEERA PRIME?
According to GharKundli's check of MahaRERA records (updated October 2026), VEERA PRIME has 24 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was VEERA PRIME registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VEERA PRIME was registered on MahaRERA on 29 June 2026. GharKundli did not find a title report on the land on file there.
Are there court cases on VEERA PRIME?
No court cases are listed for VEERA PRIME on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VEERA PRIME?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VEERA BUILDERS.
Check it yourself on MahaRERA
- How to check the possession date of VEERA PRIME
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Amravati →
Other projects in Amravati
- JANNAT COMPLEX
- LAKSHMI SHRI RESIMERCIAL
- RACHANA SRUSHTI PHASE II
- Dream Imperia
- RAJ TOWNSHIP
- DUBAI CITY
- Green Heights
- DCC Dreamz City Chambers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.